Delhi-Katra Expressway Delayed by Land Disputes in Ludhiana
ROADS & HIGHWAYS

Delhi-Katra Expressway Delayed by Land Disputes in Ludhiana

The Delhi-Katra expressway, a crucial infrastructure project for North India, is experiencing significant delays in Ludhiana district. National Highways Authority of India (NHAI) officials have revealed that construction is ongoing on only about half of the expressway's 38-kilometer stretch in Ludhiana due to unresolved land acquisition issues.

Of the 399 kilometers of road being constructed in Punjab as part of the Delhi-Katra Expressway project, 38 kilometers pass through Ludhiana, affecting 24 villages. Currently, work is progressing on approximately 19 kilometers across 11 villages. However, construction on the remaining 18.89 kilometers in 13 villages has been stalled.

Around 300 to 400 farmers are demanding higher compensation for their land. The competent authority for land acquisition has set a rate of approximately ?45 lakh per acre, while farmers are seeking between ?65 lakh and ?70 lakh per acre. This discrepancy has led to arbitration, with the possibility of the matter escalating to court if an agreement is not reached.

Construction on the expressway in Ludhiana began in 2022, following a survey conducted in 2020. As of now, 30% of the work between Malerkotla and Ludhiana (Package 8) and 57% of the work between Ludhiana and Phillaur (Package 9) have been completed. Meanwhile, 96% of Package 6 (Sangrur to Patiala) and 75% of Package 7 (Sangrur to Malerkotla) are nearing completion, according to Prashant Mahajan, Project Director of the Delhi-Katra Expressway Project.

Ludhiana Deputy Commissioner Sakshi Sawhney stated that the administration had acquired the land and handed it over to NHAI, but the authority failed to retain it. She assured that efforts were ongoing to resolve the compensation disputes through engagement with the protesting farmers.

Gurpreet Singh, block president of BKU Ekta Ugrahan, argued that the compensation offered was far below market rates and urged the government to offer fair compensation, as the completed expressway would generate revenue through toll charges.

Meanwhile, local residents are eager for the project to be completed swiftly, highlighting the urgent need for improved infrastructure in the region.

The Delhi-Katra expressway, a crucial infrastructure project for North India, is experiencing significant delays in Ludhiana district. National Highways Authority of India (NHAI) officials have revealed that construction is ongoing on only about half of the expressway's 38-kilometer stretch in Ludhiana due to unresolved land acquisition issues. Of the 399 kilometers of road being constructed in Punjab as part of the Delhi-Katra Expressway project, 38 kilometers pass through Ludhiana, affecting 24 villages. Currently, work is progressing on approximately 19 kilometers across 11 villages. However, construction on the remaining 18.89 kilometers in 13 villages has been stalled. Around 300 to 400 farmers are demanding higher compensation for their land. The competent authority for land acquisition has set a rate of approximately ?45 lakh per acre, while farmers are seeking between ?65 lakh and ?70 lakh per acre. This discrepancy has led to arbitration, with the possibility of the matter escalating to court if an agreement is not reached. Construction on the expressway in Ludhiana began in 2022, following a survey conducted in 2020. As of now, 30% of the work between Malerkotla and Ludhiana (Package 8) and 57% of the work between Ludhiana and Phillaur (Package 9) have been completed. Meanwhile, 96% of Package 6 (Sangrur to Patiala) and 75% of Package 7 (Sangrur to Malerkotla) are nearing completion, according to Prashant Mahajan, Project Director of the Delhi-Katra Expressway Project. Ludhiana Deputy Commissioner Sakshi Sawhney stated that the administration had acquired the land and handed it over to NHAI, but the authority failed to retain it. She assured that efforts were ongoing to resolve the compensation disputes through engagement with the protesting farmers. Gurpreet Singh, block president of BKU Ekta Ugrahan, argued that the compensation offered was far below market rates and urged the government to offer fair compensation, as the completed expressway would generate revenue through toll charges. Meanwhile, local residents are eager for the project to be completed swiftly, highlighting the urgent need for improved infrastructure in the region.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Infrastructure Opportunity Outlook by IMPACCT.Info

India’s infrastructure pipeline is witnessing dynamic activity across stages — from immediate bidding to future planning. IMPACCT segments these into three categories: Immediate, 3–6 Month, and Future Opportunities, enabling businesses to identify, prepare, and participate in high-value tenders and projects across sectors.To read full article Click Here ..

Next Story
Real Estate

Glass, Reframed!

Glass façades, quintessential aesthetic building envelopes globally, have been widely adopted in India as well. But when the focus is high-performance building systems that deliver energy efficiency, comfort and architectural identity, glass isn’t the only preference. Combination solutions, involving glass and some other material, improve façade outcomes. Some combinations come at comparable prices, some at a higher price. Here is a selection of performance-oriented solutions...To read the full story Click Here ..

Next Story
Infrastructure Urban

Beyond Building Faster

India’s cities are expanding at an unprecedented pace, bringing new infrastructure and development opportunities while also intensifying challenges around mobility, public spaces, liveability and supporting infrastructure. The question, therefore, is not simply whether India can build faster, but whether it can build cities that work better.At a CW webinar, Are We Designing Better Cities – or Just Building Faster?, moderator Ar. Samir Shaikh, Founding Principal, AR&UD Studio, brought together perspectives from design, development, master planning and technology...To read the full artic..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code