Delhi's underpass construction faces prolonged delay due to July floods
ROADS & HIGHWAYS

Delhi's underpass construction faces prolonged delay due to July floods

Delhi's underpass construction project along Bhairon Marg has encountered significant setbacks, primarily due to the unprecedented July floods in the city. These floods resulted in the accumulation of silt and the displacement of heavy structures within the underpass, leading officials to announce a substantial delay in its completion.

Initially designated as underpass No 5 and part of the Pragati Maidan integrated transit corridor, this infrastructure was originally scheduled to open in December 2022. However, the complex nature of the project, notably its passage through an area with an active railway overbridge, caused delays. A revised deadline was set to precede the G20 Summit scheduled for this month.

Unfortunately, progress came to a halt in July when the Yamuna River reached a record level of 208.33 meters, resulting in extensive flooding across the city. The root of the problem lies in the construction technique employed for the underpass, known as the box-push technique. This method involves pushing open-ended fabricated boxes through embankments of rail or road using a jacking system to create the tunnel's solid form.

A senior Public Works Department (PWD) official familiar with the situation stated, "Completing this stretch was already a difficult task with active railway lines overhead. Following the July floods, there was a lot of sediment in the area that is making it difficult to push the boxes. We need to remove the silt and treat the soil before we start pushing again. Besides, the boxes have shifted from their positions as these are not stitched to each other yet. These factors have caused serious delays."

PWD has taken the initiative to contact Indian Railways, seeking assistance in removing the deposits and realigning the boxes. Officials have emphasised that work can only recommence once the monsoon season concludes and the area becomes completely dry. Another PWD official commented, "We have written to Indian Railways asking if they have any technology that we can use to clear the uneven settlements and start pushing the boxes. No work can be done for now till the rain completely stops. So, anything can be done only after around another 20 days."

Indian Railways officials have not responded to inquiries regarding this development.

The integrated corridor, initially intended to offer seamless connectivity to the Pragati Maidan complex and alleviate congestion on surrounding arterial roads such as Ring Road, Mathura Road, and Bhairon Marg, has faced several challenges. The total length of underpass number 5, also known as the Bhairon Marg-Ring Road underpass, spans 110 meters, with work remaining on a 28-meter-long section.

While the underpass was originally anticipated to be completed by December of the previous year, various issues, including its proximity to the Yamuna River's banks and the presence of three active railway lines above the construction site, hindered progress. Despite the inauguration of the 1.3-kilometer main Pragati Maidan tunnel and five other underpasses for public use in June 2022, underpass 5's completion has been repeatedly delayed. Regrettably, officials now suggest that it is unlikely to be finished within this year.

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Delhi's underpass construction project along Bhairon Marg has encountered significant setbacks, primarily due to the unprecedented July floods in the city. These floods resulted in the accumulation of silt and the displacement of heavy structures within the underpass, leading officials to announce a substantial delay in its completion.Initially designated as underpass No 5 and part of the Pragati Maidan integrated transit corridor, this infrastructure was originally scheduled to open in December 2022. However, the complex nature of the project, notably its passage through an area with an active railway overbridge, caused delays. A revised deadline was set to precede the G20 Summit scheduled for this month.Unfortunately, progress came to a halt in July when the Yamuna River reached a record level of 208.33 meters, resulting in extensive flooding across the city. The root of the problem lies in the construction technique employed for the underpass, known as the box-push technique. This method involves pushing open-ended fabricated boxes through embankments of rail or road using a jacking system to create the tunnel's solid form.A senior Public Works Department (PWD) official familiar with the situation stated, Completing this stretch was already a difficult task with active railway lines overhead. Following the July floods, there was a lot of sediment in the area that is making it difficult to push the boxes. We need to remove the silt and treat the soil before we start pushing again. Besides, the boxes have shifted from their positions as these are not stitched to each other yet. These factors have caused serious delays.PWD has taken the initiative to contact Indian Railways, seeking assistance in removing the deposits and realigning the boxes. Officials have emphasised that work can only recommence once the monsoon season concludes and the area becomes completely dry. Another PWD official commented, We have written to Indian Railways asking if they have any technology that we can use to clear the uneven settlements and start pushing the boxes. No work can be done for now till the rain completely stops. So, anything can be done only after around another 20 days.Indian Railways officials have not responded to inquiries regarding this development.The integrated corridor, initially intended to offer seamless connectivity to the Pragati Maidan complex and alleviate congestion on surrounding arterial roads such as Ring Road, Mathura Road, and Bhairon Marg, has faced several challenges. The total length of underpass number 5, also known as the Bhairon Marg-Ring Road underpass, spans 110 meters, with work remaining on a 28-meter-long section.While the underpass was originally anticipated to be completed by December of the previous year, various issues, including its proximity to the Yamuna River's banks and the presence of three active railway lines above the construction site, hindered progress. Despite the inauguration of the 1.3-kilometer main Pragati Maidan tunnel and five other underpasses for public use in June 2022, underpass 5's completion has been repeatedly delayed. Regrettably, officials now suggest that it is unlikely to be finished within this year. If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi. Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code