Delhi's underpass construction faces prolonged delay due to July floods
ROADS & HIGHWAYS

Delhi's underpass construction faces prolonged delay due to July floods

Delhi's underpass construction project along Bhairon Marg has encountered significant setbacks, primarily due to the unprecedented July floods in the city. These floods resulted in the accumulation of silt and the displacement of heavy structures within the underpass, leading officials to announce a substantial delay in its completion.

Initially designated as underpass No 5 and part of the Pragati Maidan integrated transit corridor, this infrastructure was originally scheduled to open in December 2022. However, the complex nature of the project, notably its passage through an area with an active railway overbridge, caused delays. A revised deadline was set to precede the G20 Summit scheduled for this month.

Unfortunately, progress came to a halt in July when the Yamuna River reached a record level of 208.33 meters, resulting in extensive flooding across the city. The root of the problem lies in the construction technique employed for the underpass, known as the box-push technique. This method involves pushing open-ended fabricated boxes through embankments of rail or road using a jacking system to create the tunnel's solid form.

A senior Public Works Department (PWD) official familiar with the situation stated, "Completing this stretch was already a difficult task with active railway lines overhead. Following the July floods, there was a lot of sediment in the area that is making it difficult to push the boxes. We need to remove the silt and treat the soil before we start pushing again. Besides, the boxes have shifted from their positions as these are not stitched to each other yet. These factors have caused serious delays."

PWD has taken the initiative to contact Indian Railways, seeking assistance in removing the deposits and realigning the boxes. Officials have emphasised that work can only recommence once the monsoon season concludes and the area becomes completely dry. Another PWD official commented, "We have written to Indian Railways asking if they have any technology that we can use to clear the uneven settlements and start pushing the boxes. No work can be done for now till the rain completely stops. So, anything can be done only after around another 20 days."

Indian Railways officials have not responded to inquiries regarding this development.

The integrated corridor, initially intended to offer seamless connectivity to the Pragati Maidan complex and alleviate congestion on surrounding arterial roads such as Ring Road, Mathura Road, and Bhairon Marg, has faced several challenges. The total length of underpass number 5, also known as the Bhairon Marg-Ring Road underpass, spans 110 meters, with work remaining on a 28-meter-long section.

While the underpass was originally anticipated to be completed by December of the previous year, various issues, including its proximity to the Yamuna River's banks and the presence of three active railway lines above the construction site, hindered progress. Despite the inauguration of the 1.3-kilometer main Pragati Maidan tunnel and five other underpasses for public use in June 2022, underpass 5's completion has been repeatedly delayed. Regrettably, officials now suggest that it is unlikely to be finished within this year.

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Delhi's underpass construction project along Bhairon Marg has encountered significant setbacks, primarily due to the unprecedented July floods in the city. These floods resulted in the accumulation of silt and the displacement of heavy structures within the underpass, leading officials to announce a substantial delay in its completion.Initially designated as underpass No 5 and part of the Pragati Maidan integrated transit corridor, this infrastructure was originally scheduled to open in December 2022. However, the complex nature of the project, notably its passage through an area with an active railway overbridge, caused delays. A revised deadline was set to precede the G20 Summit scheduled for this month.Unfortunately, progress came to a halt in July when the Yamuna River reached a record level of 208.33 meters, resulting in extensive flooding across the city. The root of the problem lies in the construction technique employed for the underpass, known as the box-push technique. This method involves pushing open-ended fabricated boxes through embankments of rail or road using a jacking system to create the tunnel's solid form.A senior Public Works Department (PWD) official familiar with the situation stated, Completing this stretch was already a difficult task with active railway lines overhead. Following the July floods, there was a lot of sediment in the area that is making it difficult to push the boxes. We need to remove the silt and treat the soil before we start pushing again. Besides, the boxes have shifted from their positions as these are not stitched to each other yet. These factors have caused serious delays.PWD has taken the initiative to contact Indian Railways, seeking assistance in removing the deposits and realigning the boxes. Officials have emphasised that work can only recommence once the monsoon season concludes and the area becomes completely dry. Another PWD official commented, We have written to Indian Railways asking if they have any technology that we can use to clear the uneven settlements and start pushing the boxes. No work can be done for now till the rain completely stops. So, anything can be done only after around another 20 days.Indian Railways officials have not responded to inquiries regarding this development.The integrated corridor, initially intended to offer seamless connectivity to the Pragati Maidan complex and alleviate congestion on surrounding arterial roads such as Ring Road, Mathura Road, and Bhairon Marg, has faced several challenges. The total length of underpass number 5, also known as the Bhairon Marg-Ring Road underpass, spans 110 meters, with work remaining on a 28-meter-long section.While the underpass was originally anticipated to be completed by December of the previous year, various issues, including its proximity to the Yamuna River's banks and the presence of three active railway lines above the construction site, hindered progress. Despite the inauguration of the 1.3-kilometer main Pragati Maidan tunnel and five other underpasses for public use in June 2022, underpass 5's completion has been repeatedly delayed. Regrettably, officials now suggest that it is unlikely to be finished within this year. If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi. Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Transport

Cabinet Approves Key Highway and Rail Projects in Bihar Region

The Union Cabinet on Wednesday approved the four-laning of the 84.2-km Mokama-Munger section of the Buxar-Bhagalpur high-speed corridor, a key industrial region in poll-bound Bihar. The Cabinet also sanctioned the doubling of the 177-km Bhagalpur-Dumka-Rampurhat railway line, which passes through Bihar, Jharkhand, and West Bengal, at a cost of Rs 31.7 billion.The Rs 44.5 billion highway project will be constructed under the hybrid annuity model, a variant of public-private partnership. The Mokama-Munger stretch was the only remaining two-lane section of the 363-km Buxar-Bhagalpur corridor. Fou..

Next Story
Infrastructure Transport

NGT Issues Notice on Bengaluru Twin Tunnel Project

The National Green Tribunal (NGT) on Wednesday issued notices in response to a petition filed by Bengaluru Praja Vedike and others, challenging the Bengaluru twin tunnel road project. Petitioners claim the project was “hastily announced” and bypassed mandatory environmental impact assessment procedures.Notices have been served to the Karnataka Government, Greater Bengaluru Authority, State Environment Impact Assessment Authority (SEIAA), Bengaluru Smart Infrastructure Ltd (B-SMILE), the Union Ministry of Environment, Forest and Climate Change, and project consultants.The 16.74-km twin-tube..

Next Story
Real Estate

India’s Residential Sales to Dip Slightly in FY26

Residential sales in India’s seven major cities are projected to decline by up to 3 per cent year-on-year in FY26 to 620–640 million square feet (msf), amid a moderation in sales velocity, according to ratings agency Icra.In FY25, sales stood at 643 msf, down 8 per cent YoY, following a sharp contraction in new launches and moderated demand in the affordable and mid-income segments. This slowdown came after the sector posted a robust compound annual growth rate of 26 per cent in area sales between FY22 and FY24.Icra noted: “Having seen a strong upcycle, the sector entered an equilibrium ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?