Despite second Covid wave, highway construction at 28 km per day in April

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown.

The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month.

According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built.

Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year.

Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders.

Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high.

NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19.

CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half.

CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.

Image Source

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown. The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month. According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built. Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year. Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders. Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high. NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19. CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half. CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.Image Source

Next Story
Real Estate

Mahindra Lifespaces Bags Rs 12.5 billion Redevelopment in Mulund

Mahindra Lifespace Developers (MLDL), the real estate and infrastructure development arm of the Mahindra Group, has been appointed as the preferred developer for the redevelopment of a premium housing society in Mulund (West), Mumbai. The project will be developed across a 3.08-acre land parcel, with an estimated development value of approximately Rs 12.5 billion. Strategically located, the site enjoys proximity to major connectivity points—just 1.4 km from the upcoming Mumbai Metro Line 5 and 0.8 km from the Goregaon-Mulund Link Road. It also offers seamless access to the Eastern Expre..

Next Story
Infrastructure Urban

Snowman Adds Warehouses in Kolkata and Krishnapatnam

Snowman Logistics, India’s leading integrated temperature-controlled logistics company, has announced the commencement of operations at its two new state-of-the-art, owned cold storage facilities in Kolkata and Krishnapatnam. With these additions, the company’s total pallet capacity has reached 1,50,754, spanning 43 warehouses in 20 cities across the country. The newly operational Kolkata facility offers a storage capacity of 5,630 pallets, while the Krishnapatnam facility holds 3,927 pallets. These warehouses are equipped with advanced automation and infrastructure designed to enhanc..

Next Story
Resources

Noesis Enables IHCL Hotel Deal in Udupi–Manipal Corridor

NOESIS Capital Advisors, India’s leading hotel investment advisory firm, has successfully facilitated a landmark hospitality transaction in the Udupi–Manipal region of Karnataka. The deal involves the acquisition of a nearly completed, 130-key upscale hotel that will operate under one of the premium brands of IHCL, reinforcing NOESIS’ position as a preferred partner for strategic hospitality transactions across India. Strategically located on the Udupi–Manipal Highway, the 1.03-acre property will cater to business travellers, pilgrims and families visiting Manipal University. With..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?