Despite second Covid wave, highway construction at 28 km per day in April
ROADS & HIGHWAYS

Despite second Covid wave, highway construction at 28 km per day in April

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown.

The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month.

According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built.

Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year.

Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders.

Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high.

NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19.

CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half.

CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.

Image Source

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown. The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month. According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built. Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year. Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders. Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high. NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19. CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half. CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.Image Source

Next Story
Resources

Ajmera Realty launches tree drive on Environment Day

Ajmera Realty & Infra India marked World Environment Day with a large-scale tree plantation initiative—Plant-with-Purpose—across its projects in Mumbai and Bangalore. The drive was inaugurated at Ajmera Manhattan and Ajmera Greenfinity in Wadala, with senior company officials and residents in attendance. The campaign encourages residents to embrace eco-conscious, self-reliant lifestyles by growing useful plants and trees within their communities. Horticulture expert Devendra Bhekar guided residents on creating and maintaining green spaces. Ajmera Realty planted over 500 trees..

Next Story
Resources

Twaron®-reinforced tyre powers Brunel’s solar race car

Teijin Aramid’s Twaron® with circular content will debut in Bridgestone’s race tyres for the 2025 Bridgestone World Solar Challenge, supporting the Brunel Solar Team’s Nuna 13 car. This marks the first use of the recycled-content aramid in a high-performance race tyre. The Twaron®-reinforced belts help enhance durability, reduce rolling resistance, and maintain lightweight strength—critical for the 3,000-km solar race across Australia. Bridgestone combines this with ENLITENTM tech and other recycled inputs to maximise environmental and performance outcomes. Teijin Aramid, a..

Next Story
Building Material

Kamdhenu Paints launches new wood coating range

Kamdhenu Paints has launched a comprehensive premium wood coating range designed for both interior and exterior applications. The collection includes high-performance solutions like Kamwood 2K PU for a rich matt or high-gloss finish, Kamwood 1K PU for clarity and stain protection, and the Kamwood Melamyne system for a smooth, durable finish. Also featured are Kamwood Wood Stains, which enhance wood grains with vibrant colour, and NC Sanding Sealer for high-build grain filling. The range is supported by Kamwood Thinners for ease of application and optimal finish. Saurabh Agarwal, MD, ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?