Despite second Covid wave, highway construction at 28 km per day in April
ROADS & HIGHWAYS

Despite second Covid wave, highway construction at 28 km per day in April

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown.

The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month.

According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built.

Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year.

Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders.

Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high.

NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19.

CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half.

CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.

Image Source

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown. The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month. According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built. Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year. Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders. Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high. NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19. CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half. CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.Image Source

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement