Despite second Covid wave, highway construction at 28 km per day in April
ROADS & HIGHWAYS

Despite second Covid wave, highway construction at 28 km per day in April

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown.

The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month.

According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built.

Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year.

Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders.

Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high.

NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19.

CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half.

CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.

Image Source

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown. The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month. According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built. Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year. Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders. Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high. NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19. CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half. CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.Image Source

Next Story
Real Estate

Eaton Signs Rs 165 Million-a-Month Baner Office Lease

Eaton Technologies, the Indian arm of global intelligent power management firm Eaton Corporation, has signed a 10-year lease for 150,000 sq ft of office space in an IT park in Pune’s Baner area, at a starting monthly rent of Rs 165 million.The agreement, finalised on 3 August 2025, includes 150 four-wheeler and 150 two-wheeler parking slots. The rent, set at Rs 110 per sq ft, will increase annually by 4.5 per cent. Eaton will pay a security deposit of Rs 990 million to lessor Astrope Properties Pvt Ltd. The deal also has a five-year lock-in period and a full-term fit-out lock-in, with fit-ou..

Next Story
Infrastructure Energy

Power Demand Rises 2.4 per cent in July to 154 BUs

India’s electricity demand grew 2.4 per cent year-on-year in July to 154 billion units (BUs), up from 150 BUs a year earlier, driven by buoyant industrial activity, according to a CRISIL report. This marked a turnaround from May and June, which saw on-year declines of 4.8 per cent and 2.3 per cent respectively.The HSBC India Manufacturing Purchasing Managers’ Index (PMI) – a key indicator of industrial activity – rose to a 16-month high of 59.1 in July, from 58.4 in June.Demand in the southern region jumped 11.4 per cent on-year, in line with a 1 per cent rainfall deficit in the South ..

Next Story
Infrastructure Transport

HBL Wins Rs 541.2 Million KAVACH Contract

HBL Engineering Limited has secured a contract worth Rs 541.2 million from the West Central Railway for the survey, design, supply, installation, testing, and commissioning of trackside KAVACH equipment. The project covers the Kota–Ruthiyai section and the Sogaria–Kota "C" section, spanning 166 route kilometres in the Kota division.The scope of work includes erecting towers and associated infrastructure for KAVACH at 18 stations and level crossing gates along the route. The initiative, which includes 18 per cent GST, is aimed at enhancing railway safety through the deployment of this advan..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?