Despite second Covid wave, highway construction at 28 km per day in April
ROADS & HIGHWAYS

Despite second Covid wave, highway construction at 28 km per day in April

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown.

The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month.

According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built.

Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year.

Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders.

Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high.

NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19.

CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half.

CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.

Image Source

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown. The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month. According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built. Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year. Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders. Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high. NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19. CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half. CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.Image Source

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement