Despite second Covid wave, highway construction at 28 km per day in April
ROADS & HIGHWAYS

Despite second Covid wave, highway construction at 28 km per day in April

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown.

The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month.

According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built.

Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year.

Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders.

Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high.

NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19.

CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half.

CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.

Image Source

Despite the Covid-19 pandemic, lockdowns, and limitations on movement in most parts of the country, highway construction in April quadrupled this year to 853 km compared to the same month last year, which saw an entire nationwide lockdown. The speed of construction was 28 km per day in April 2021, though as it declined by 61% month-on-month. According to data by the Ministry of Road Transport and Highways (MoRTH), every implementing agency including the National Highways Authority of India (NHAI), had built 210km of national highway in April previous year. In March 2021, a complete total of 2,189 km of highway were built. Highway development reached an all-time high of 13,298 km in 2020-21 at a record speed of 36.4 km per day. In April this year, project awards also progressed to 311 km from 260 km as awarded last year. Investigators attribute the report construction to a slew of industry-friendly measures that the government had taken proactively during the pandemic year, including those to assure better cash flow to the builders. Credit Rating Information Services of India Ltd (CRISIL) told the media that despite the pandemic, NHAI granted projects of a total of 4,818 km last year- a three fiscal high. NHAI has established an ambitious 4,600 km highway development target for the current fiscal. Previous fiscal, NHAI constructed a record 4,192 km, above from 3,979 km constructed in 2019-20, and 3,380 km in 2018-19. CRISIL added that despite Covid-19 in the previous fiscal, the national highways sector did a great job, taking on higher project awards, construction, and traffic that exceeded after lockdown limitations decreased in the second half. CRISIL said that the second wave of Covid-19 slowed this momentum, but it may not have a material bearing on growth for the current fiscal.Image Source

Next Story
Real Estate

Smartworks Unveils Largest Mumbai Campus at Intellion Park, Navi Mumbai

 Smartworks Coworking Spaces, India’s largest managed office platform by area under management, has launched its largest Mumbai campus with 557,000 sq. ft. at Intellion Park, Navi Mumbai, a Tata Realty development. With this addition, Smartworks’ leased portfolio in Mumbai has crossed 1 million sq. ft. Strategically located on Thane Belapur Road, Intellion Park is set to become Navi Mumbai’s largest IT Park, supported by strong infrastructure and connectivity. The new campus, with LEED Platinum, IFC Edge, and WELL Gold pre-certifications, incorporates solar power, smart automat..

Next Story
Real Estate

Major Developments Partners with Patrice Evra for Colibri Views Tower

Major Developments has named global football icon Patrice Evra as Project Partner for Colibri Views, its flagship tower at RAK Central. The announcement was made during the RAK Central event celebrating the completion of the district’s core infrastructure, led by H.E. Arch. Abdulla Al Abdouli, CEO of Marjan. Andrei Charapenak, CEO of Major Developments, and Evra unveiled Colibri Views as a development designed to blend business, lifestyle, and leisure. The tower will feature the UAE’s first rooftop Footbot football simulator, an award-winning performance-driven wellness innovation con..

Next Story
Real Estate

Vascon Engineers Targets Rs 40 billion EPC Orders and Rs 25 billion Realty

Vascon Engineers, a leading EPC and realty player with nearly four decades of experience, has set a target of achieving an EPC order book of Rs 40 billion and real estate projects worth Rs 25 billion by FY27. The company is active across 13 cities, with an EPC business split of 75:25 between government and private clients. Current projects include a Rs 6.06 billion medical college at Suphal, Bihar, Capgemini IT Park in Chennai worth Rs 4.16 billion, and the Rs 2.60 billion Vedanta Township project. “Vascon Engineers’ strength lies in balancing our EPC and real estate businesses a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?