Final Phase of Rs 1.98 Billion Highway Project Begins Soon
ROADS & HIGHWAYS

Final Phase of Rs 1.98 Billion Highway Project Begins Soon

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.
Progress So Far
The first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.
The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.
As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.
Environmental Approvals and Replantation
Tree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.
In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.
Broader Replantation Efforts
Beyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.Progress So FarThe first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.Environmental Approvals and ReplantationTree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.Broader Replantation EffortsBeyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App