Final Phase of Rs 1.98 Billion Highway Project Begins Soon
ROADS & HIGHWAYS

Final Phase of Rs 1.98 Billion Highway Project Begins Soon

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.
Progress So Far
The first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.
The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.
As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.
Environmental Approvals and Replantation
Tree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.
In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.
Broader Replantation Efforts
Beyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.Progress So FarThe first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.Environmental Approvals and ReplantationTree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.Broader Replantation EffortsBeyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code