Final Phase of Rs 1.98 Billion Highway Project Begins Soon
ROADS & HIGHWAYS

Final Phase of Rs 1.98 Billion Highway Project Begins Soon

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.
Progress So Far
The first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.
The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.
As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.
Environmental Approvals and Replantation
Tree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.
In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.
Broader Replantation Efforts
Beyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.Progress So FarThe first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.Environmental Approvals and ReplantationTree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.Broader Replantation EffortsBeyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement