Final Phase of Rs 1.98 Billion Highway Project Begins Soon
ROADS & HIGHWAYS

Final Phase of Rs 1.98 Billion Highway Project Begins Soon

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.
Progress So Far
The first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.
The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.
As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.
Environmental Approvals and Replantation
Tree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.
In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.
Broader Replantation Efforts
Beyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.Progress So FarThe first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.Environmental Approvals and ReplantationTree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.Broader Replantation EffortsBeyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code