Final Phase of Rs 1.98 Billion Highway Project Begins Soon
ROADS & HIGHWAYS

Final Phase of Rs 1.98 Billion Highway Project Begins Soon

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.
Progress So Far
The first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.
The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.
As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.
Environmental Approvals and Replantation
Tree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.
In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.
Broader Replantation Efforts
Beyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

The State Highways Department is set to commence the final phase of the Pudukottai–Aranthangi Highway widening project, upgrading the corridor to a four-lane road. The entire project, undertaken under the Comprehensive Road Infrastructure Development Programme, involves an investment of Rs 1.98 billion, split across three phases.Progress So FarThe first phase, covering 4.8 km, was completed during 2023–24 at a cost of Rs 440 million. The second phase, comprising 6 km up to Vallathirakottai, was completed in 2024–25 for Rs 390 million.The final stretch of 19 km will be executed at a cost of Rs 1.15 billion, with tendering already underway. A senior official confirmed that land acquisition is not required, and the work is expected to begin next month, with a targeted completion period of 10 months.As part of the infrastructure upgrade, 32 culverts have already been constructed, and 31 more are planned in the final phase to improve drainage and road longevity.Environmental Approvals and ReplantationTree removal has been a key aspect of the project’s environmental management. In the earlier phases, the department removed 490 trees after receiving clearance from the District Green Committee. For the final phase, the department is seeking approval to remove approximately 340 additional trees. A joint inspection was recently conducted by officials from the Highways and Forest Departments, alongside NGO representatives, as part of the clearance process.In line with environmental guidelines, the department has committed to replantation ratios of 1:10 and 1:20 for trees removed and those to be removed, respectively. So far, it has planted 1,350 saplings of indigenous species such as tamarind, naanal, vembu, and pungai along the highway. Additionally, ‘arali’ and neem saplings have been planted on an 11-km median stretch.Broader Replantation EffortsBeyond the Pudukottai–Aranthangi route, sapling plantation has also been carried out on the Alangudi–Karambakudi Major District Road, the Alangudi–Kurumbur State Highway, and the Alangudi–Arimalam Major District Road. These efforts reflect the department’s broader commitment to eco-sensitive road infrastructure development in the region.

Next Story
Resources

Haworth India Hosts Women’s Leadership Panel Series

Haworth India marked International Women’s Day by hosting a leadership roundtable series titled ‘Give to Gain’, bringing together senior women leaders from architecture and design firms, corporates and project management consultancies. The series has been conducted in Delhi and Mumbai, with upcoming sessions scheduled in Bengaluru and Hyderabad on 27 March 2026. Structured as moderated panel discussions followed by audience interaction, the initiative examined the business impact of women’s leadership and the role of inclusive workplaces in supporting professional growth. Manish Khan..

Next Story
Real Estate

Max Estates Secures RERA For Max One Project

Max Estates has secured RERA approval (UPRERA No.: UPRERAPRJ9759) for its Max One development around Max Towers in Sector 16B, Noida, bringing renewed progress to a project previously stalled following the insolvency of its earlier developer. Spread across around 10 acres with an estimated development potential of about 2.5 million sq ft, Max One is planned as an integrated mixed-use campus combining serviced residences, premium offices, retail spaces and a private club. The project is expected to generate total sales potential of about Rs 20 billion along with an estimated annuity rental inc..

Next Story
Real Estate

Hindware Introduces Starc Smart Wall Mount Toilet

Hindware has introduced the Starc Smart Wall-Mount Toilet under its Hindware Italian Collection, designed to combine automation, hygiene and contemporary bathroom aesthetics. The model features automatic flushing, sensor-based seat opening and closing, and remote-controlled functions. It also includes an oscillating water spray and warm air dryer for cleaning, along with a self-cleaning nozzle designed to maintain hygiene. Additional features include adjustable heated seating, customisable water temperature and pressure settings, a foot-touch flush system and an LCD control interface. The wa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement