Ghatkopar Bridge Completion Pushed to June 2027
ROADS & HIGHWAYS

Ghatkopar Bridge Completion Pushed to June 2027

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.

Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.

The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.

Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.

Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.

Source:UrbanNews

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.Source:UrbanNews

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India’s first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India’s infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central–Gandhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India’s busiest business corridors. This upgrade, effective from 11 May, raised the train’s seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai–Ahmedabad–Gandhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi’s ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river’s health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?