Ghatkopar Bridge Completion Pushed to June 2027
ROADS & HIGHWAYS

Ghatkopar Bridge Completion Pushed to June 2027

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.

Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.

The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.

Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.

Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.

Source:UrbanNews

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.Source:UrbanNews

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->