Ghatkopar Bridge Completion Pushed to June 2027
ROADS & HIGHWAYS

Ghatkopar Bridge Completion Pushed to June 2027

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.

Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.

The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.

Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.

Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.

Source:UrbanNews

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.Source:UrbanNews

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement