Ghatkopar Bridge Completion Pushed to June 2027
ROADS & HIGHWAYS

Ghatkopar Bridge Completion Pushed to June 2027

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.

Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.

The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.

Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.

Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.

Source:UrbanNews

The completion of the Ghatkopar railway overbridge in Mumbai has been delayed to June 2027, nearly two years beyond the original 2025 deadline. The bridge, a key link between Ghatkopar East and West, is being reconstructed to ease traffic in the eastern suburbs.Built seventy-eight years ago, the structure was flagged as overloaded by the Indian Institute of Technology Bombay following the Gokhale Bridge collapse. The Maharashtra Rail Infrastructure Development Corporation, funded by Brihanmumbai Municipal Corporation, is overseeing the rebuild.The new design includes a cable-stayed span over railway tracks and a bowstring steel structure over Lal Bahadur Shastri Road, avoiding pillars beneath busy roads and intersecting two metro lines and the bullet train corridor.Work began in 2022, but progress has been hindered by encroachments near the west-side approach, including shops and a new Slum Rehabilitation Authority building. Heavy vehicles remain banned, forcing reroutes for buses and goods transport to Sakinaka and the airport.Right-hand lanes of the new bridge are expected to be ready in one year. The old bridge will then be dismantled. Until completion, nearby bridges at Vidyavihar and Vikhroli will offer limited relief.Source:UrbanNews

Next Story
Equipment

Escorts Kubota Unveils BS V Next-gen Construction Range at Excon 2025

Escorts Kubota (EKL), one of India’s major engineering groups in the agricultural and construction equipment sectors, unveiled its latest BS V–compliant construction machinery line-up at Excon 2025. The refreshed portfolio underscores the company’s push toward application-driven, high-productivity solutions that reduce ownership costs and meet the needs of India’s expanding infrastructure landscape. With demand rising across urban development, industrial logistics and mining, the new range aims to deliver higher performance, durability and operator comfort.In the earthmoving segment, E..

Next Story
Equipment

ACE and Kotak Mahindra Bank Join Hands to Boost Backhoe Loader Financing

Action Construction Equipment (ACE), the world’s largest Pick-n-Carry crane maker and a leading manufacturer of material handling and construction equipment in India, has entered into a Memorandum of Understanding with Kotak Mahindra Bank to enhance the availability of flexible financing options for backhoe loader customers across the country.The collaboration aims to support contractors, infrastructure companies, entrepreneurs, SMEs, and emerging businesses by offering smoother access to credit through customised loan schemes, quicker turnaround times, and the extensive footprint of Kotak M..

Next Story
Building Material

Suraj Estate Wins Euromoney Award for India’s Best Residential Developer

"Suraj Estate Developers Limited has received the Euromoney Real Estate Award 2025 for ‘India’s Best Residential Developer’, positioning the company among globally benchmarked leaders in the sector. The recognition reflects its four-decade legacy in delivering high-quality residential and redevelopment-led projects across South Central Mumbai. The Euromoney Real Estate Awards, presented by the London-based Euromoney magazine, are widely regarded as one of the most credible global assessments of performance in real estate, banking and finance. Winners are selected through surveys of inte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App