GMDA Fines Contractor Rs 9.9 Million for Road Repair Delays
ROADS & HIGHWAYS

GMDA Fines Contractor Rs 9.9 Million for Road Repair Delays

The Gurugram Metropolitan Development Authority (GMDA) has imposed a penalty of Rs 9.9 million on a contractor based in Hisar for delays in the special repair of nine major sector roads across the city. Officials stated that this is the second such penalty, with a previous fine exceeding Rs 10 million already levied against the same contractor for delays in repairing 13 other critical roads, including Major Sushil Aima Road in Palam Vihar and roads in Sector 9 and 9A.
A senior GMDA official confirmed that the authority took serious note of the delays and issued a formal penalty notice on 11 July. The contractor was originally awarded the repair work on 19 December 2024, with a stipulated completion date of 15 September 2025. However, progress has been far from satisfactory, the official said.
The repair work covered key master sector roads, including those dividing Sectors 30/31, 33/34, 57 (Part I and II), 49/50, 69/70, 70/75, 70/70A, 25/28, and 24/26. In its notice, the GMDA highlighted that the contractor failed to meet milestones agreed upon in the original contract, despite repeated reminders and follow-ups.
The delay has compounded public inconvenience, especially after recent rains severely damaged newly re-laid roads. “If timely repairs had been undertaken, the surface wouldn’t have folded or deteriorated to this extent,” the official added.
Residents have voiced frustration over the worsening condition of roads. Pankaj Yadav, a lawyer from Sector 22, said, “I had informed GMDA about the poor condition of Major Sushil Aima Road shortly after it was re-laid. The authority must act strictly in such cases.”
Large potholes and unsafe driving conditions continue to plague residents, intensifying demands for stricter accountability and faster completion of public infrastructure works.

The Gurugram Metropolitan Development Authority (GMDA) has imposed a penalty of Rs 9.9 million on a contractor based in Hisar for delays in the special repair of nine major sector roads across the city. Officials stated that this is the second such penalty, with a previous fine exceeding Rs 10 million already levied against the same contractor for delays in repairing 13 other critical roads, including Major Sushil Aima Road in Palam Vihar and roads in Sector 9 and 9A.A senior GMDA official confirmed that the authority took serious note of the delays and issued a formal penalty notice on 11 July. The contractor was originally awarded the repair work on 19 December 2024, with a stipulated completion date of 15 September 2025. However, progress has been far from satisfactory, the official said.The repair work covered key master sector roads, including those dividing Sectors 30/31, 33/34, 57 (Part I and II), 49/50, 69/70, 70/75, 70/70A, 25/28, and 24/26. In its notice, the GMDA highlighted that the contractor failed to meet milestones agreed upon in the original contract, despite repeated reminders and follow-ups.The delay has compounded public inconvenience, especially after recent rains severely damaged newly re-laid roads. “If timely repairs had been undertaken, the surface wouldn’t have folded or deteriorated to this extent,” the official added.Residents have voiced frustration over the worsening condition of roads. Pankaj Yadav, a lawyer from Sector 22, said, “I had informed GMDA about the poor condition of Major Sushil Aima Road shortly after it was re-laid. The authority must act strictly in such cases.”Large potholes and unsafe driving conditions continue to plague residents, intensifying demands for stricter accountability and faster completion of public infrastructure works. 

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement