Gorakhpur Link Expressway to be operational soon
ROADS & HIGHWAYS

Gorakhpur Link Expressway to be operational soon

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs.

More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi.

While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM).

The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh.

The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson.

The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway.

Also Read
Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint 
Dalmia Cement to sell stake in firm Sarvapriya Healthcare

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs. More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi. While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM). The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh. The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson. The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway. Also Read Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint  Dalmia Cement to sell stake in firm Sarvapriya Healthcare

Next Story
Real Estate

Heena Lalwani Buys Rs 1.13 Billion Juhu Apartment

Heena Lalwani, promoter of Aatman Innovations Private Limited, has purchased a luxury apartment worth Rs 1.13 billion in Mumbai’s upscale Juhu locality, according to property registration documents accessed by Zapkey.com.The 9,862 sq ft apartment, located on the 10th floor of Lodha Developers’ Avalon Tower, was acquired at Rs 115,000 per sq ft and comes with five car parking spaces. The deal, registered on 18 August 2025, also included the payment of Rs 68 million in stamp duty and a Rs 30,000 registration fee.Lodha Developers did not respond to queries regarding the transaction, while the..

Next Story
Real Estate

Godrej Buys KPHB Land for Rs 7 Billion in E-Auction

An acre of prime land in Kukatpally Housing Board (KPHB), Hyderabad, was auctioned for Rs 7 billion, with the Telangana Housing Board generating Rs 5.47 billion from the sale of 7.8 acres through e-auction on 20 August 2025.The auction notification was issued last month, attracting bids from Godrej Properties, Aurobindo Realty, Prestige Estates, and Ashoka Builders, according to Board vice-chairman V.P. Gautham. With an offset price of Rs 4 billion per acre, the three-hour auction saw 46 bid increases, before Godrej Properties acquired the land.Revenue generated from the auction will be utilis..

Next Story
Real Estate

HMDA to Auction 93 Prime Plots in September

The Hyderabad Metropolitan Development Authority (HMDA) is preparing to conduct a three-day auction of prime open plots across Hyderabad, Rangareddy, and Medchal-Malkajgiri districts this September.According to official reports, the e-auction will take place on 17, 18, and 19 September, offering 93 plots. Of these, 70 are located in the Bachupally HMDA layout, with the remainder spread across Turkayamjal, Kokapet, Poppalguda, Chandanagar, Bairagiguda, Gandi Maisamma, Suraram, Medipally, and Bachupally village.The highest upset price has been fixed at Rs 175,000 per square yard for a land parce..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?