Gorakhpur Link Expressway to be operational soon
ROADS & HIGHWAYS

Gorakhpur Link Expressway to be operational soon

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs.

More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi.

While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM).

The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh.

The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson.

The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway.

Also Read
Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint 
Dalmia Cement to sell stake in firm Sarvapriya Healthcare

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs. More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi. While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM). The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh. The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson. The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway. Also Read Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint  Dalmia Cement to sell stake in firm Sarvapriya Healthcare

Next Story
Real Estate

BXB Estates Sets AED 110 Million Jumeirah Golf Estates Record

BXB Estates has completed an AED 110 million residential transaction at Jumeirah Golf Estates, setting a new sales record for the prestigious Dubai residential community.Negotiated by Alfie Tabrez, Managing Partner of BXB Estates, the deal surpassed the previous record of AED 58 million for a completed ready villa in the development.The six-bedroom residence offers 21,714 sq ft of built-up space on a 15,873-sq-ft plot. It features nine bathrooms, four living lounges, a home office, bar lounge, private cinema and rooftop terrace.The property also includes a dedicated wellness area comprising a ..

Next Story
Infrastructure Urban

SECR Floats Rs 6,019 Mn EPC Tender For Paradol Nagpur Link

South East Central Railway (SECR) has invited bids for an Engineering, Procurement and Construction (EPC) contract to build a new broad gauge single line between Paradol Takeoff Point and Nagpur Road Station in Chhattisgarh. The contract carries an estimated cost of Rs 6,019.0 mn and requires an earnest money deposit of Rs 120.4 mn. The work is framed as an EPC assignment intended to strengthen regional rail infrastructure. The tender, issued under number CAO-C-BSP-26-27-15, specifies a completion period of 730 days and a bid validity of 180 days. Two pre-bid meetings are scheduled for 24 Augu..

Next Story
Infrastructure Transport

Indian Railways Reports Nine Per Cent Rise In July Freight Loading

Indian Railways handled 141.3 million tonnes (141.3 mn t) of freight in July, marking a rise of nine per cent year on year. Freight loading maintained a positive trajectory across the network compared with the same month last year. Passenger traffic also increased in July, contributing to higher overall network utilisation. The July outcome continued a pattern of steady monthly gains, reflecting gradual improvement in industrial and logistics activity. The growth in freight volumes reflected stronger demand across multiple sectors and improvements in logistics and train turnarounds. Enhanced r..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement