Gorakhpur Link Expressway to be operational soon
ROADS & HIGHWAYS

Gorakhpur Link Expressway to be operational soon

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs.

More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi.

While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM).

The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh.

The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson.

The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway.

Also Read
Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint 
Dalmia Cement to sell stake in firm Sarvapriya Healthcare

The 92-kilometre-long Gorakhpur Link Expressway, which connects the city to the Purvanchal Expressway, will be opened to the public soon. Chief Minister Yogi Adityanath set a December deadline for the completion of the Gorakhpur Link Expressway in February. The project, which began in February 2020, will cost Rs 5,877 crore, including land costs. More than 62% of the construction work has been completed thus far. Once completed, the motorway will ensure smooth vehicular traffic movement from Gorakhpur to Lucknow, Agra, and Delhi. While clearing and grubbing work has been completed, civil work on the main carriageway is currently underway, including granular sub-base (GSB), wet mix macadam (WMM), and dense bituminous macadam (DBM). The four-lane (expandable to six lanes) expressway begins at Jaitpur on NH-27 in Gorakhpur district and links with the Purvanchal Expressway near Salarpur in Azamgarh district. The access-controlled expressway spans across four districts — Gorakhpur, Sant Kabir Nagar, Ambedkar Nagar, and Azamgarh. The nodal agency, Uttar Pradesh Expressway Development Authority (UPEIDA), is carrying out this project in the engineering, procurement, and construction (EPC) mode. For implementation, the project has been divided into two packages. While one company is working on the project's 47-kilometer-long package-1, another is working on package-2, which is 43.03 kilometres long. Two toll plazas, three ramp plazas, seven flyovers, 16 vehicular underpasses, 50 light vehicular underpasses, 35 pedestrian underpasses, seven major bridges, 27 minor bridges, and 389 culverts are also being built as part of the motorway. A separate link road will connect the Gorakhpur Link Expressway to Varanasi, according to a UPEIDA spokesperson. The motorway is expected to serve as an industrial corridor, connecting various manufacturing units. Keeping this in mind, the latest budget includes a Rs 200 crore allocation for the Industrial Corridor along the Gorakhpur-link Expressway. Also Read Rs 120 bn project development in Gorakhpur in 1 st year CM’s 2 nd-stint  Dalmia Cement to sell stake in firm Sarvapriya Healthcare

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement