HC denies Delhi-Amritsar-Katra Expressway Land Acquisition
ROADS & HIGHWAYS

HC denies Delhi-Amritsar-Katra Expressway Land Acquisition

The acquisition of land by the National Highway Authority of India (NHAI) for the construction of the Delhi-Amritsar-Katra Expressway will proceed as the Punjab and Haryana High Court has denied interim relief to stop the process. The court is currently hearing a plea from 126 petitioners, led by Darshan Singh, who claim that their residential houses and other structures are being demolished without proper compensation.

The proposed Delhi-Amritsar-Katra Expressway is a 669-kilometer, 4-lane access-controlled green field expressway with a budget of Rs 400 billion. It aims to reduce travel time between Delhi and Chandigarh to 2 hours and Delhi and Amritsar to 4 hours. Additionally, the expressway is planned to connect important Sikh religious sites, starting from Shri Harmandir Sahib Amritsar and culminating at the holy shrine of Mata Vaishno Devi in Katra.

Representing the NHAI, Senior Advocate Chetan Mittal, along with Advocate Abhilaksh Gaind, argued that only one residential house belonging to Darshan Singh is affected by the project, with the main structure of the house located outside the project's alignment. The NHAI's counsels also stated that a supplementary award has been passed for the boundary wall in question, and a table detailing the claims made by the petitioners regarding other structures such as tube-wells and bore-wells has been provided to the court.

The petitioners' counsel countered that their clients were unaware of any supplementary award and had not received compensation for the demolition. They also raised other arguments challenging the land acquisition itself. In response, the NHAI's counsels informed the court that the petition is misleading and does not align with the factual position. They emphasized the national importance of the project and its potential positive impact on Punjab and neighboring states.

After considering the arguments from both sides regarding interim relief, the High Court firmly declined to grant any interim stay to halt the project at this stage. Justices Lisa Gill and Ritu Tagore, the division bench overseeing the case, stated in their order that no grounds were found to support granting interim relief to hinder the project.

The acquisition of land by the National Highway Authority of India (NHAI) for the construction of the Delhi-Amritsar-Katra Expressway will proceed as the Punjab and Haryana High Court has denied interim relief to stop the process. The court is currently hearing a plea from 126 petitioners, led by Darshan Singh, who claim that their residential houses and other structures are being demolished without proper compensation. The proposed Delhi-Amritsar-Katra Expressway is a 669-kilometer, 4-lane access-controlled green field expressway with a budget of Rs 400 billion. It aims to reduce travel time between Delhi and Chandigarh to 2 hours and Delhi and Amritsar to 4 hours. Additionally, the expressway is planned to connect important Sikh religious sites, starting from Shri Harmandir Sahib Amritsar and culminating at the holy shrine of Mata Vaishno Devi in Katra. Representing the NHAI, Senior Advocate Chetan Mittal, along with Advocate Abhilaksh Gaind, argued that only one residential house belonging to Darshan Singh is affected by the project, with the main structure of the house located outside the project's alignment. The NHAI's counsels also stated that a supplementary award has been passed for the boundary wall in question, and a table detailing the claims made by the petitioners regarding other structures such as tube-wells and bore-wells has been provided to the court. The petitioners' counsel countered that their clients were unaware of any supplementary award and had not received compensation for the demolition. They also raised other arguments challenging the land acquisition itself. In response, the NHAI's counsels informed the court that the petition is misleading and does not align with the factual position. They emphasized the national importance of the project and its potential positive impact on Punjab and neighboring states. After considering the arguments from both sides regarding interim relief, the High Court firmly declined to grant any interim stay to halt the project at this stage. Justices Lisa Gill and Ritu Tagore, the division bench overseeing the case, stated in their order that no grounds were found to support granting interim relief to hinder the project.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App