HC orders authorities to complete two major roads in Shillong
ROADS & HIGHWAYS

HC orders authorities to complete two major roads in Shillong

On February 24, the Meghalaya high court ordered the concerned authorities to provide timelines for the completion of two important roads in Shillong and the surrounding areas to alleviate traffic congestion.

Shillong-Western Bypass and Shillong-Diengpasoh road are the two roads.

The division bench stated in its order issued while hearing a Public Interest Litigation (PIL) filed by the High Court of Meghalaya Bar Association that all authorities must put their heads together and indicate the timelines for completion with milestones, if possible.

The state first passes the buck to the National Highways Authority of India (NHAI) and the National Highways and Infrastructure Development Corporation Limited (NHIDCL), according to the court.

Although the National Highways Authority of India Act, 1956 contains a mechanism for the acquisition of land, settlement of disputes, and payment of compensation – complete with arbitration – it appears that both the NHAI and the NHIDCL have washed their hands in respect of the land acquisition.

The state has informed the petitioner that the acquisition process for the Shillong Western Bypass has begun, although the petitioner has submitted that no detailed project report (DPR) has been prepared for the purpose.

The state also claims that a third of the construction on the Shillong-Diengpasoh road has already been completed.

Both roads are critical for relieving Shillong and the surrounding areas of daily traffic congestion and toxic fumes.

Image Source

Also read: NHAI to offer land along National Highways for realty development

On February 24, the Meghalaya high court ordered the concerned authorities to provide timelines for the completion of two important roads in Shillong and the surrounding areas to alleviate traffic congestion. Shillong-Western Bypass and Shillong-Diengpasoh road are the two roads. The division bench stated in its order issued while hearing a Public Interest Litigation (PIL) filed by the High Court of Meghalaya Bar Association that all authorities must put their heads together and indicate the timelines for completion with milestones, if possible. The state first passes the buck to the National Highways Authority of India (NHAI) and the National Highways and Infrastructure Development Corporation Limited (NHIDCL), according to the court. Although the National Highways Authority of India Act, 1956 contains a mechanism for the acquisition of land, settlement of disputes, and payment of compensation – complete with arbitration – it appears that both the NHAI and the NHIDCL have washed their hands in respect of the land acquisition. The state has informed the petitioner that the acquisition process for the Shillong Western Bypass has begun, although the petitioner has submitted that no detailed project report (DPR) has been prepared for the purpose. The state also claims that a third of the construction on the Shillong-Diengpasoh road has already been completed. Both roads are critical for relieving Shillong and the surrounding areas of daily traffic congestion and toxic fumes. Image Source Also read: NHAI to offer land along National Highways for realty development

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code