Highway Construction Pace Seen Slowing to 27 Km a Day in FY26
ROADS & HIGHWAYS

Highway Construction Pace Seen Slowing to 27 Km a Day in FY26

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.

The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.

Historical data shows the sector’s fluctuations:
  • FY18: A record 9,829 km constructed and 17,065 km awarded.
  • FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.
  • FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.
  • FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.
  • FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.
For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.
Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.

News source: Business World

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.Historical data shows the sector’s fluctuations:FY18: A record 9,829 km constructed and 17,065 km awarded.FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.News source: Business World

Next Story
Infrastructure Transport

Ashoka Bags Rs 5 Billion Rail Electrification Contract

Ashoka Buildcon Ltd. has secured a Letter of Acceptance (LoA) worth approximately Rs 5 billion from the North Western Railway, Jaipur, for a major upgrade of the electric traction system in the Jaipur Division. The contract, with a duration of 24 months, involves the design, supply, erection, testing, and commissioning of a 2×25 kV traction system to replace the current 1×25 kV network. The project also includes modifications to the overhead equipment to enable train speeds of up to 160 km/h across specified sections of the division.In a separate development, Servotech Power Systems Ltd. has..

Next Story
Infrastructure Transport

Mumbai–Ahmedabad Bullet Train Stations Near Completion

The Ministry of Railways has announced that construction work on the bullet train stations along the Mumbai–Ahmedabad High-Speed Rail (MAHSR) corridor is nearing completion. The modern, eco-friendly stations are being designed with a blend of cutting-edge technology and local cultural identity to offer passengers seamless connectivity and elevated comfort.In a recent post on social media platform X, the Ministry stated: “The #BulletTrain stations on the Mumbai–Ahmedabad corridor in Gujarat are nearing completion. With modern design, cultural identity, seamless connectivity and eco-friend..

Next Story
Infrastructure Transport

Satish Kumar Gets 1-Year Extension as Railway Board CEO

The Indian government has extended the tenure of Satish Kumar, Chairman and Chief Executive Officer (CEO) of the Railway Board, for an additional year, marking the first such extension for the post in five years. The Appointments Committee of the Cabinet approved the reappointment of Kumar, a retired Indian Railway Management Service officer, effective from 1 September 2025, on a contractual basis under existing terms.Kumar, who assumed charge in September 2024, became the first Dalit to lead the national transporter, having previously served as Member (Traction and Rolling Stock) of the Railw..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?