Highway Construction Pace Seen Slowing to 27 Km a Day in FY26
ROADS & HIGHWAYS

Highway Construction Pace Seen Slowing to 27 Km a Day in FY26

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.

The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.

Historical data shows the sector’s fluctuations:
  • FY18: A record 9,829 km constructed and 17,065 km awarded.
  • FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.
  • FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.
  • FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.
  • FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.
For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.
Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.

News source: Business World

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.Historical data shows the sector’s fluctuations:FY18: A record 9,829 km constructed and 17,065 km awarded.FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.News source: Business World

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement