Highway Construction Pace Seen Slowing to 27 Km a Day in FY26
ROADS & HIGHWAYS

Highway Construction Pace Seen Slowing to 27 Km a Day in FY26

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.

The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.

Historical data shows the sector’s fluctuations:
  • FY18: A record 9,829 km constructed and 17,065 km awarded.
  • FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.
  • FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.
  • FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.
  • FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.
For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.
Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.

News source: Business World

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.Historical data shows the sector’s fluctuations:FY18: A record 9,829 km constructed and 17,065 km awarded.FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.News source: Business World

Next Story
Real Estate

Birla Estates Tops Global GRESB 2025 Rankings

Birla Estates (BEPL), a wholly owned subsidiary of Aditya Birla Real Estate (formerly Century Textiles and Industries Limited), has been recognised as a Sector Leader in the 2025 GRESB Real Estate Assessment, securing top honours across multiple global and regional categories.Birla Estates’ Achievements in GRESB 2025:Global Sector Leader – ResidentialGlobal Sector Leader – Non-Listed ResidentialRegional Sector Leader – Asia – ResidentialRegional Sector Leader – Non-Listed – Asia – ResidentialThese distinctions reaffirm Birla Estates’ exceptional performance in Environmental, ..

Next Story
Infrastructure Transport

Progota India Secures RDSO Clearance for Kavach 4.0

Concord Control Systems, one of India’s leading manufacturers of embedded electronic and critical system solutions, announced that its associate company, Progota India, has received Technical Prototype Clearance from the Research Designs and Standards Organisation (RDSO) for Kavach 4.0, the latest version of Indian Railways’ indigenous Automatic Train Protection (ATP) system.With this clearance, Progota has been formally approved to execute its ongoing trial order from South Central Railway, marking a key milestone in India’s railway modernization journey. The approval also establishes P..

Next Story
Infrastructure Urban

MPS Interactive Systems Completes Full Acquisition of Liberate Group

MPS Interactive Systems (MPSi), a material subsidiary of MPS, has completed the acquisition of the remaining shareholding in the Liberate Group of Companies—comprising Liberate Learning, App-eLearn, and Liberate eLearning.With this transaction, MPSi now holds 100 per cent ownership of all entities within the Liberate Group, making them its wholly owned subsidiaries. The acquisition was executed in line with the valuation methodology defined in the original transaction documents.Commenting on the development, Rahul Arora, Chairman and CEO of MPS, said, “The corporate learning sector continu..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?