Highway Construction Pace Seen Slowing to 27 Km a Day in FY26
ROADS & HIGHWAYS

Highway Construction Pace Seen Slowing to 27 Km a Day in FY26

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.

The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.

Historical data shows the sector’s fluctuations:
  • FY18: A record 9,829 km constructed and 17,065 km awarded.
  • FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.
  • FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.
  • FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.
  • FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.
For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.
Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.

News source: Business World

India’s national highway construction is set to moderate further in FY26, with the average pace expected to decline to 27 km a day from a peak of 37 km in FY21, according to a report by CareEdge Ratings. The slowdown highlights execution hurdles and weaker project awarding activity despite strong demand for infrastructure development.The CareEdge Ratings report noted that construction activity is projected to contract by 7–10 per cent in FY26. Lower awarding of projects, pending approvals for Hybrid Annuity Model (HAM) projects, and execution challenges have weighed on the sector. Meanwhile, competition for NH-HAM bids has intensified, exerting additional pressure on developers.Historical data shows the sector’s fluctuations:FY18: A record 9,829 km constructed and 17,065 km awarded.FY19: Project awards fell sharply to 5,493 km, though construction rose to 10,885 km.FY21: Peak performance with 10,467 km awarded and 13,435 km built, averaging 37 km per day.FY22: Construction slowed to 10,457 km (29 km/day) despite awards rising to 12,731 km.FY24: 12,349 km constructed, averaging 34 km/day, while project awards slipped to 8,581 km.For FY26, construction is projected at 9,900 km, translating to 27 km a day, reflecting the sector’s difficulty in sustaining earlier momentum.Despite the moderation, industry watchers believe long-term demand for highways remains intact, with government initiatives under the Bharatmala Pariyojana and Gati Shakti framework expected to provide future impetus.News source: Business World

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->