Himachal Deploys 15,000 Personnel And 1,600 Machines To Restore Roads
ROADS & HIGHWAYS

Himachal Deploys 15,000 Personnel And 1,600 Machines To Restore Roads

Himachal Pradesh Public Works Department (PWD) minister Vikramaditya Singh said the state government had deployed around 15,000 personnel and 1,600 machines to restore road connectivity disrupted by heavy monsoon rains. He said restoration work was underway round the clock and the number of blocked roads had fallen significantly since Tuesday. The minister reported that about 104 roads had been closed on Tuesday and that a morning report showed the figure had come down to about 60.

He said remaining roads had already been reopened and that another 30 to 35 roads were expected to be restored by the evening. The PWD has mobilised extensive manpower and equipment, including nearly 1,600 machines such as JCBs, bulldozers and robotic equipment, stationed at different locations across the state. Singh said additional machinery had been hired and would be deployed wherever required to ensure there was no shortage of resources.

The minister warned that the ongoing monsoon season could bring cloudbursts, flash floods and landslides without warning, causing damage to infrastructure, houses and orchards and urged local residents to take precautions and avoid unnecessary travel during adverse weather. He asked people to inform the administration immediately of any dangerous developments so that timely intervention could be arranged. Singh chaired a nearly three hour online review meeting with senior officials to assess preparedness and streamline restoration efforts.

Officials were directed to reopen and restore all blocked roads within 24 hours wherever possible, with special attention to remote and vulnerable hill districts such as Mandi, Chamba, Kangra, Kullu and Shimla. The minister underlined the importance of maintaining road connectivity with apple season approaching so horticulturists and farmers would not suffer losses or face transport disruption. He added that the government remained committed to ensuring uninterrupted connectivity during the monsoon while protecting the interests of residents and producers across the state.

Himachal Pradesh Public Works Department (PWD) minister Vikramaditya Singh said the state government had deployed around 15,000 personnel and 1,600 machines to restore road connectivity disrupted by heavy monsoon rains. He said restoration work was underway round the clock and the number of blocked roads had fallen significantly since Tuesday. The minister reported that about 104 roads had been closed on Tuesday and that a morning report showed the figure had come down to about 60. He said remaining roads had already been reopened and that another 30 to 35 roads were expected to be restored by the evening. The PWD has mobilised extensive manpower and equipment, including nearly 1,600 machines such as JCBs, bulldozers and robotic equipment, stationed at different locations across the state. Singh said additional machinery had been hired and would be deployed wherever required to ensure there was no shortage of resources. The minister warned that the ongoing monsoon season could bring cloudbursts, flash floods and landslides without warning, causing damage to infrastructure, houses and orchards and urged local residents to take precautions and avoid unnecessary travel during adverse weather. He asked people to inform the administration immediately of any dangerous developments so that timely intervention could be arranged. Singh chaired a nearly three hour online review meeting with senior officials to assess preparedness and streamline restoration efforts. Officials were directed to reopen and restore all blocked roads within 24 hours wherever possible, with special attention to remote and vulnerable hill districts such as Mandi, Chamba, Kangra, Kullu and Shimla. The minister underlined the importance of maintaining road connectivity with apple season approaching so horticulturists and farmers would not suffer losses or face transport disruption. He added that the government remained committed to ensuring uninterrupted connectivity during the monsoon while protecting the interests of residents and producers across the state.

Next Story
Real Estate

CREDAI-MCHI to Host 10th Design & Construction Conference

CREDAI-MCHI will host the 10th anniversary edition of its Design & Construction Conference on August 19, 2026, at the Jio World Convention Centre in Mumbai.The event is expected to bring together more than 500 procurement leaders, construction heads, architects, consultants and senior real estate decision-makers, alongside over 50 construction and ancillary brands.The conference will feature product launches, technology showcases, knowledge sessions, strategic business-to-business networking and recognition of procurement professionals contributing to the transformation of the construction..

Next Story
Infrastructure Energy

BorgWarner Wins Extension for High-Voltage Inverter Programmes

BorgWarner has secured a major extension of several high-volume high-voltage inverter programmes from a leading European automotive manufacturer.The contracts cover updated inverter designs for plug-in hybrid and 800V battery-electric vehicle applications. Production is scheduled to begin in 2029.Isabelle McKenzie, President and General Manager, BorgWarner PowerDrive Systems, said the programme extensions demonstrate the company’s position in power electronics and reflect the strength of its technology, in-house expertise and customer relationships.For plug-in hybrid vehicles, BorgWarner wil..

Next Story
Infrastructure Urban

Castrol India Q2 Profit Rises 43% to Rs 3.48 bn

Castrol India reported a 43 per cent year-on-year increase in profit after tax to Rs 3.48 billion for the quarter ended June 30, 2026, supported by growth across its consumer, industrial and institutional businesses.Revenue from operations increased 25 per cent to Rs 18.71 billion during the second quarter of 2026, compared with Rs 14.97 billion in the corresponding period of 2025. EBITDA rose 41 per cent to Rs 4.94 billion from Rs 3.50 billion.Sequentially, revenue increased from Rs 15.45 billion in the first quarter of 2026, while EBITDA rose from Rs 3.29 billion. Profit after tax increased ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement