Hindon Bridge expected to be completed by April 2026
ROADS & HIGHWAYS

Hindon Bridge expected to be completed by April 2026

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.

Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.

The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.

Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

Next Story
Infrastructure Transport

RAHSTA 2026 to Host Certified Highway Construction Masterclass

RAHSTA 2026 will organise the Certified Highway Construction Masterclass, a specialised two-day corporate training programme for highway construction professionals, on July 8–9, 2026, at the Jio World Convention Centre.The Masterclass will be delivered by RASTA – Center for Road Technology and supported by Construction World and FIRST Construction Council.Designed as an industry-led refresher programme, the Masterclass aims to help engineering and project teams stay updated with the latest advancements in highway construction, pavement technologies, sustainable materials, intelligent compa..

Next Story
Infrastructure Urban

Grand Mercure Mysuru Turns 10; BHVL to Invest Rs 1,000 Crore in Karnataka

Brigade Hotel Ventures Limited (BHVL) has marked the 10th anniversary of its flagship property, Grand Mercure Mysuru, by announcing a major investment plan of around Rs 1,000 crore in Karnataka over the next five years. The company said the investment will be directed towards new hospitality projects as well as modernisation of existing assets, aligning with the evolving demand for experiential tourism.The announcement comes as BHVL reiterated its focus on strengthening Mysuru’s position as a prominent global tourism destination by supporting the local micro-economy and adopting sustainable ..

Next Story
Infrastructure Urban

Ottobock and Celcius Set Up Prosthetics Warehouse in India

Celcius Logistics, a domestic third-party logistics (3PL) company specialising in end-to-end cold-chain solutions, has partnered with Ottobock India, the Indian arm of Germany-based Ottobock, to establish a dedicated prosthetics warehouse and logistics distribution hub in India. As part of the collaboration, a technology-enabled facility has been launched in Thane to streamline storage and nationwide movement of prosthetic and assistive devices.The dedicated warehouse is expected to strengthen the medical supply chain by reducing turnaround time and improving access to prosthetic products acro..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement