Hindon Bridge expected to be completed by April 2026
ROADS & HIGHWAYS

Hindon Bridge expected to be completed by April 2026

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.

Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.

The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.

Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->