Hindon Bridge expected to be completed by April 2026
ROADS & HIGHWAYS

Hindon Bridge expected to be completed by April 2026

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.

Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.

The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.

Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

The completion of the Hindon Bridge, a critical infrastructure project aimed at improving connectivity between Noida and Greater Noida, has been postponed to April 2026. The project involves constructing a road over two kilometers long, which will link the Noida Expressway to Greater Noida’s LG Chowk via the Hindon Bridge. However, the project has encountered major delays due to ongoing land acquisition challenges.Spanning 290 meters over the Hindon River, the bridge has only reached 30% of its construction progress. Initially launched by the Chief Minister of Uttar Pradesh in January 2019, the project was intended to be completed within 18 months. However, due to land acquisition issues, especially on the side of the Noida Authority, construction was halted for an extended period.The Uttar Pradesh State Bridge Corporation (UPSBCL), the body overseeing the bridge’s construction, has officially requested an 18-month extension to finalize the remaining work. The delay also affects the construction of approach roads on both sides of the bridge, which are being developed by the Noida and Greater Noida authorities. These approach roads, each around one kilometre long, are expected to be completed alongside the bridge. Work on the bridge was paused for two and a half years because of the land acquisition issues, but construction resumed in November 2023. The approach roads began earlier this year as part of the project’s revival.Once completed, the Hindon Bridge is expected to cut travel time between Noida and Greater Noida, along with key locations such as the district collectorate, Surajpur, and Ghaziabad, by approximately 16 kilometres. This improvement is expected to relieve traffic congestion, particularly at Pari Chowk, which is currently a major bottleneck for commuters. The delay highlights the difficulties faced by large-scale infrastructure projects, especially when dealing with land management. Ultimately, the Hindon Bridge is anticipated to significantly enhance regional connectivity and help manage increasing traffic demands in the area.                                                                                                                         

Next Story
Infrastructure Urban

Recycling Leaders Push for Policy Reforms in India

As India prepares for the largest recycling-focused event in its history, industry leaders are making a strong case for policy reforms to unlock the country’s circular economy potential. Ahead of the Bharat Recycling Show (BRS) 2025, co-located with Plastics Recycling Show (PRS) India, a high-level panel discussion in Mumbai spotlighted the urgent need for regulatory clarity, digital innovation, and integration of the informal sector.Held under the theme “Unlocking Circular Value: Regulatory and Market Trends in Recycling”, the panel brought together prominent voices from across the recy..

Next Story
Infrastructure Energy

Environmental Hearing Set for 1000 MW Naying Hydro Project

The environmental public hearing for the 1,000 MW Naying hydroelectric project will take place on November 12 at Yapik community hall in Shi-Yomi district, Arunachal Pradesh, officials confirmed. The run-of-the-river project on the Siyom (Yomgo) river is being developed by the North Eastern Electric Power Corporation (NEEPCO). Construction, including a concrete dam, underground powerhouse, and tunnel, is expected to commence around 2028, with commissioning planned by 2032. The project aims to generate approximately 4,966.77 GWh of electricity. The Naying project received Central Electricity ..

Next Story
Infrastructure Energy

India Achieves 490 MWh Energy Storage Capacity by June 2025

India’s cumulative energy storage capacity reached 490 MWh by June 2025, according to data released by the Central Electricity Authority (CEA). Of this, more than 85 per cent is associated with renewable energy projects, primarily solar and wind, reflecting the country’s accelerated shift towards grid stability and clean energy integration. The CEA report highlights that 16 energy storage systems are currently operational across 10 states, with major installations in Rajasthan, Gujarat, Karnataka, and Maharashtra. These include both standalone and co-located battery systems deployed by le..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?