Humtso Elumyo PMGSY Road Project Faces Prolonged Delay
ROADS & HIGHWAYS

Humtso Elumyo PMGSY Road Project Faces Prolonged Delay

Representatives of the Humtso Village Youth Organisation (HVYO), the Humtso Village Council, the contractor's representative and Er Chandemo Tungoe, sub-divisional officer (SDO), Public Works Department (PWD), held discussions on the progress of the Humtso-Elumyo village road construction under the Pradhan Mantri Gram Sadak Yojana (PMGSY).

The project was sanctioned under PMGSY-III in March 2024 with an 18-month period and has recorded limited progress, currently operating in its second extension period. Attendees reviewed the work completed to date and the outstanding tasks affecting timely delivery.

Completed works included earth cutting, installation of Hume pipe culverts, construction of protection walls and excavation of side drains, while full depth reclamation (FDR), plain cement concrete (PCC) and bituminous surfacing have not yet commenced. The department indicated that efforts were under way to facilitate completion by March 2027 and the contractor's representative signalled that work might resume at the earliest opportunity. The meeting examined project scheduling, resource mobilisation and technical requirements necessary to advance the remaining activities.

Prolonged delay has reportedly been attributed to incessant rainfall, shortages and breakdowns of machinery and other operational difficulties that have impeded progress. Local residents have continued to await a properly constructed road to support regular travel, access to services and improved connectivity between the villages. The Humtso Village Youth Organisation appealed to the contractor and the executing authorities to resume construction promptly and to target completion ahead of the forthcoming Christmas celebrations.

The organisation expressed appreciation to stakeholders for acknowledging its concerns and offered continued cooperation to ensure better road connectivity for the people of Humtso and Elumyo. The discussion underscored the importance of coordinated action by the PWD and the contractor to prevent further delays and of transparent updates on timelines and task completion. Continued monitoring and operational readiness were urged to restore momentum and deliver the infrastructure sought by the community.

Representatives of the Humtso Village Youth Organisation (HVYO), the Humtso Village Council, the contractor's representative and Er Chandemo Tungoe, sub-divisional officer (SDO), Public Works Department (PWD), held discussions on the progress of the Humtso-Elumyo village road construction under the Pradhan Mantri Gram Sadak Yojana (PMGSY). The project was sanctioned under PMGSY-III in March 2024 with an 18-month period and has recorded limited progress, currently operating in its second extension period. Attendees reviewed the work completed to date and the outstanding tasks affecting timely delivery. Completed works included earth cutting, installation of Hume pipe culverts, construction of protection walls and excavation of side drains, while full depth reclamation (FDR), plain cement concrete (PCC) and bituminous surfacing have not yet commenced. The department indicated that efforts were under way to facilitate completion by March 2027 and the contractor's representative signalled that work might resume at the earliest opportunity. The meeting examined project scheduling, resource mobilisation and technical requirements necessary to advance the remaining activities. Prolonged delay has reportedly been attributed to incessant rainfall, shortages and breakdowns of machinery and other operational difficulties that have impeded progress. Local residents have continued to await a properly constructed road to support regular travel, access to services and improved connectivity between the villages. The Humtso Village Youth Organisation appealed to the contractor and the executing authorities to resume construction promptly and to target completion ahead of the forthcoming Christmas celebrations. The organisation expressed appreciation to stakeholders for acknowledging its concerns and offered continued cooperation to ensure better road connectivity for the people of Humtso and Elumyo. The discussion underscored the importance of coordinated action by the PWD and the contractor to prevent further delays and of transparent updates on timelines and task completion. Continued monitoring and operational readiness were urged to restore momentum and deliver the infrastructure sought by the community.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

CJI Surya Kant Calls for Preventive Justice to Avoid Infrastructure Disputes

Kant has urged the infrastructure ecosystem to design contractual and institutional frameworks that identify and address concerns early through communication and dispute-avoidance mechanisms.Chief Justice of India Surya Kant has urged India’s infrastructure ecosystem to move from retrospective justice to preventive justice, as the country undertakes projects at an unprecedented scale. Speaking at global engineering body FIDIC’s Global Infrastructure Conference 2026 in New Delhi, Kant said the true measure of a justice system’s success lies in ensuring mechanisms around infrastructure pro..

Next Story
Infrastructure Urban

Madhya Pradesh Secures Rs 530 Billion in Investment Proposals

Rupee (Rs) 530 billion (bn) in investment proposals were received by Madhya Pradesh on the third day of Chief Minister Mohan Yadav's visit to the United Arab Emirates, with major interest in green energy, artificial intelligence, data centres and advanced manufacturing. The delegation held engagements in Dubai and Sharjah to promote projects and secure commitments from global investors. State officials said the proposals represent a significant pipeline for industrial expansion and technology infrastructure. Rana Holdings Limited proposed a portfolio including a 2,000 MW solar energy project a..

Next Story
Infrastructure Energy

Shakti Pumps Wins Rs 2,359.2 Mn Maharashtra Order for 10,000 Solar Pumps

Shakti Pumps (India) has secured an order from Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) to supply and install 10,000 solar water pumping systems across the state. The contract is valued at Rs 2,359.2 million (mn) including GST, covering pumps with capacities of three horsepower, five horsepower and seven point five horsepower. The award has been made under Maharashtra's Magel Tyala Saur Krushi Pump Yojana and is intended to expand off grid irrigation options for farmers. The firm will undertake end to end responsibilities, including designing and manufacturing the pumps..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code