Humtso Elumyo PMGSY Road Project Faces Prolonged Delay
ROADS & HIGHWAYS

Humtso Elumyo PMGSY Road Project Faces Prolonged Delay

Representatives of the Humtso Village Youth Organisation (HVYO), the Humtso Village Council, the contractor's representative and Er Chandemo Tungoe, sub-divisional officer (SDO), Public Works Department (PWD), held discussions on the progress of the Humtso-Elumyo village road construction under the Pradhan Mantri Gram Sadak Yojana (PMGSY).

The project was sanctioned under PMGSY-III in March 2024 with an 18-month period and has recorded limited progress, currently operating in its second extension period. Attendees reviewed the work completed to date and the outstanding tasks affecting timely delivery.

Completed works included earth cutting, installation of Hume pipe culverts, construction of protection walls and excavation of side drains, while full depth reclamation (FDR), plain cement concrete (PCC) and bituminous surfacing have not yet commenced. The department indicated that efforts were under way to facilitate completion by March 2027 and the contractor's representative signalled that work might resume at the earliest opportunity. The meeting examined project scheduling, resource mobilisation and technical requirements necessary to advance the remaining activities.

Prolonged delay has reportedly been attributed to incessant rainfall, shortages and breakdowns of machinery and other operational difficulties that have impeded progress. Local residents have continued to await a properly constructed road to support regular travel, access to services and improved connectivity between the villages. The Humtso Village Youth Organisation appealed to the contractor and the executing authorities to resume construction promptly and to target completion ahead of the forthcoming Christmas celebrations.

The organisation expressed appreciation to stakeholders for acknowledging its concerns and offered continued cooperation to ensure better road connectivity for the people of Humtso and Elumyo. The discussion underscored the importance of coordinated action by the PWD and the contractor to prevent further delays and of transparent updates on timelines and task completion. Continued monitoring and operational readiness were urged to restore momentum and deliver the infrastructure sought by the community.

Representatives of the Humtso Village Youth Organisation (HVYO), the Humtso Village Council, the contractor's representative and Er Chandemo Tungoe, sub-divisional officer (SDO), Public Works Department (PWD), held discussions on the progress of the Humtso-Elumyo village road construction under the Pradhan Mantri Gram Sadak Yojana (PMGSY). The project was sanctioned under PMGSY-III in March 2024 with an 18-month period and has recorded limited progress, currently operating in its second extension period. Attendees reviewed the work completed to date and the outstanding tasks affecting timely delivery. Completed works included earth cutting, installation of Hume pipe culverts, construction of protection walls and excavation of side drains, while full depth reclamation (FDR), plain cement concrete (PCC) and bituminous surfacing have not yet commenced. The department indicated that efforts were under way to facilitate completion by March 2027 and the contractor's representative signalled that work might resume at the earliest opportunity. The meeting examined project scheduling, resource mobilisation and technical requirements necessary to advance the remaining activities. Prolonged delay has reportedly been attributed to incessant rainfall, shortages and breakdowns of machinery and other operational difficulties that have impeded progress. Local residents have continued to await a properly constructed road to support regular travel, access to services and improved connectivity between the villages. The Humtso Village Youth Organisation appealed to the contractor and the executing authorities to resume construction promptly and to target completion ahead of the forthcoming Christmas celebrations. The organisation expressed appreciation to stakeholders for acknowledging its concerns and offered continued cooperation to ensure better road connectivity for the people of Humtso and Elumyo. The discussion underscored the importance of coordinated action by the PWD and the contractor to prevent further delays and of transparent updates on timelines and task completion. Continued monitoring and operational readiness were urged to restore momentum and deliver the infrastructure sought by the community.

Related Stories

Gold Stories

Next Story
Real Estate

IHCL signs 140-key Taj resort in Meghalaya

The Indian Hotels Company (IHCL) has signed an agreement to develop a 140-key Taj resort at Barapani in Meghalaya. The conversion project, being undertaken in partnership with Umiam Hotels, will be located on the banks of Umiam Lake.Suma Venkatesh, Executive Vice-President – Real Estate and Development, IHCL, said the project would strengthen the company's presence in the Northeast and complement its existing portfolio by supporting a travel circuit connecting Guwahati, Barapani and Shillong.The resort will include an all-day dining restaurant, a specialty restaurant, a bar, a café and a lo..

Next Story
Real Estate

IHCL signs 140-key Taj resort in Meghalaya

The Indian Hotels Company (IHCL) has signed an agreement to develop a 140-key Taj resort at Barapani in Meghalaya. The conversion project, being undertaken in partnership with Umiam Hotels, will be located on the banks of Umiam Lake.Suma Venkatesh, Executive Vice-President – Real Estate and Development, IHCL, said the project would strengthen the company's presence in the Northeast and complement its existing portfolio by supporting a travel circuit connecting Guwahati, Barapani and Shillong.The resort will include an all-day dining restaurant, a specialty restaurant, a bar, a café and a lo..

Next Story
Real Estate

Haworth showcases India-made workplace solutions at ORGATEC India 2026

Haworth will showcase its workplace solutions at ORGATEC India 2026, scheduled from 19 to 21 November at the Jio World Convention Centre, Mumbai. Under the theme ‘Future of Workspaces. Build for Those Who Build India’, the company will present its approach to workplace design, manufacturing in India and product longevity.At the centre of its showcase will be ‘Workplace Through the Senses’, an experiential display exploring how colour, lighting, acoustics and materials influence comfort, focus, collaboration and employee wellbeing. The booth will bring together solutions from Haworth, B..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code