Humtso Elumyo PMGSY Road Project Faces Prolonged Delay
ROADS & HIGHWAYS

Humtso Elumyo PMGSY Road Project Faces Prolonged Delay

Representatives of the Humtso Village Youth Organisation (HVYO), the Humtso Village Council, the contractor's representative and Er Chandemo Tungoe, sub-divisional officer (SDO), Public Works Department (PWD), held discussions on the progress of the Humtso-Elumyo village road construction under the Pradhan Mantri Gram Sadak Yojana (PMGSY).

The project was sanctioned under PMGSY-III in March 2024 with an 18-month period and has recorded limited progress, currently operating in its second extension period. Attendees reviewed the work completed to date and the outstanding tasks affecting timely delivery.

Completed works included earth cutting, installation of Hume pipe culverts, construction of protection walls and excavation of side drains, while full depth reclamation (FDR), plain cement concrete (PCC) and bituminous surfacing have not yet commenced. The department indicated that efforts were under way to facilitate completion by March 2027 and the contractor's representative signalled that work might resume at the earliest opportunity. The meeting examined project scheduling, resource mobilisation and technical requirements necessary to advance the remaining activities.

Prolonged delay has reportedly been attributed to incessant rainfall, shortages and breakdowns of machinery and other operational difficulties that have impeded progress. Local residents have continued to await a properly constructed road to support regular travel, access to services and improved connectivity between the villages. The Humtso Village Youth Organisation appealed to the contractor and the executing authorities to resume construction promptly and to target completion ahead of the forthcoming Christmas celebrations.

The organisation expressed appreciation to stakeholders for acknowledging its concerns and offered continued cooperation to ensure better road connectivity for the people of Humtso and Elumyo. The discussion underscored the importance of coordinated action by the PWD and the contractor to prevent further delays and of transparent updates on timelines and task completion. Continued monitoring and operational readiness were urged to restore momentum and deliver the infrastructure sought by the community.

Representatives of the Humtso Village Youth Organisation (HVYO), the Humtso Village Council, the contractor's representative and Er Chandemo Tungoe, sub-divisional officer (SDO), Public Works Department (PWD), held discussions on the progress of the Humtso-Elumyo village road construction under the Pradhan Mantri Gram Sadak Yojana (PMGSY). The project was sanctioned under PMGSY-III in March 2024 with an 18-month period and has recorded limited progress, currently operating in its second extension period. Attendees reviewed the work completed to date and the outstanding tasks affecting timely delivery. Completed works included earth cutting, installation of Hume pipe culverts, construction of protection walls and excavation of side drains, while full depth reclamation (FDR), plain cement concrete (PCC) and bituminous surfacing have not yet commenced. The department indicated that efforts were under way to facilitate completion by March 2027 and the contractor's representative signalled that work might resume at the earliest opportunity. The meeting examined project scheduling, resource mobilisation and technical requirements necessary to advance the remaining activities. Prolonged delay has reportedly been attributed to incessant rainfall, shortages and breakdowns of machinery and other operational difficulties that have impeded progress. Local residents have continued to await a properly constructed road to support regular travel, access to services and improved connectivity between the villages. The Humtso Village Youth Organisation appealed to the contractor and the executing authorities to resume construction promptly and to target completion ahead of the forthcoming Christmas celebrations. The organisation expressed appreciation to stakeholders for acknowledging its concerns and offered continued cooperation to ensure better road connectivity for the people of Humtso and Elumyo. The discussion underscored the importance of coordinated action by the PWD and the contractor to prevent further delays and of transparent updates on timelines and task completion. Continued monitoring and operational readiness were urged to restore momentum and deliver the infrastructure sought by the community.

Related Stories

Gold Stories

Next Story
Real Estate

Mindspace REIT earns IGBC Green Landscape Gold Rating

Mindspace Business Parks REIT’s Mindspace Airoli East business park in Navi Mumbai has received the IGBC Green Landscape Gold Rating from the Indian Green Building Council (IGBC). Mindspace REIT said it is the first REIT in India to receive the distinction.The certification evaluates the design, management and ecological performance of landscaped areas, including biodiversity, resource efficiency and sustainability practices.Mindspace Airoli East has more than 60 per cent native and adaptive green cover and more than 30 per cent vegetation supporting local birds and insects. Smart landscape ..

Next Story
Real Estate

Vertical integration gives us control over cost and delivery: Renny Strips

At bauma CONEXPO India 2026, Renny Strips showcased its green steel proposition, with a focus on lower-emission manufacturing, vertical integration and customised structural steel solutions. Managing Director Binny Gupta spoke to Kavita Parab about the company’s sustainability initiatives, including its 22MW solar plant, and its plans to expand capacity and support India’s infrastructure growth.What was Renny Strips’ focus at Bauma CONEXPO India 2026?We focused on showcasing our green steel proposition and explaining its benefits to customers, particularly in European markets. Our steel ..

Next Story
Infrastructure Energy

Beyond Energy-Efficiency

Walk through any major Indian business district today and you will see slick, glass-clad towers shimmering under the tropical sun. Most of these structures proudly display plaque certifications: Platinum, Gold, or 5-Star ratings. They promise lower carbon footprints, reduced electricity bills and a sustainable future.Yet, behind these polished green plaques, the electricity meter tells a different story. Many of these certified structures consume massive amounts of energy to remain operational. This gap, between what a certificate says and what a building actually does, is where this critique ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code