In FY2019-20, we are working towards a 35 per cent growth in turnover
ROADS & HIGHWAYS

In FY2019-20, we are working towards a 35 per cent growth in turnover

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....

Name one major challenge faced in FY2018-19. How did the company tackle it?
The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.

Name one you consider the biggest contributor to the company’s growth in FY2018-19.
Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.

What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?
RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. 

What are your plans for the company’s growth in FY2019-20? 
In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20. 

Rail Vikas Nigam
Net Sales EBITDA Reported PAT
FY19 (Rs Billion) 100.68 8.03 7.05
Growth over FY18 (%) 32.52 32.30 23.83

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....Name one major challenge faced in FY2018-19. How did the company tackle it?The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.Name one you consider the biggest contributor to the company’s growth in FY2018-19.Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. What are your plans for the company’s growth in FY2019-20? In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20.  .tg {border-collapse:collapse;border-spacing:0;} .tg td{font-family:Arial, sans-serif;font-size:14px;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg th{font-family:Arial, sans-serif;font-size:14px;font-weight:normal;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg .tg-eohl{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:right;vertical-align:top} .tg .tg-v56s{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-5agr{color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-39dc{color:#343434;border-color:inherit;text-align:right;vertical-align:top} Rail Vikas Nigam Net Sales EBITDA Reported PAT FY19 (Rs Billion) 100.68 8.03 7.05 Growth over FY18 (%) 32.52 32.30 23.83

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India’s first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India’s infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central–Gandhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India’s busiest business corridors. This upgrade, effective from 11 May, raised the train’s seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai–Ahmedabad–Gandhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi’s ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river’s health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?