In FY2019-20, we are working towards a 35 per cent growth in turnover
ROADS & HIGHWAYS

In FY2019-20, we are working towards a 35 per cent growth in turnover

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....

Name one major challenge faced in FY2018-19. How did the company tackle it?
The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.

Name one you consider the biggest contributor to the company’s growth in FY2018-19.
Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.

What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?
RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. 

What are your plans for the company’s growth in FY2019-20? 
In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20. 

Rail Vikas Nigam
Net Sales EBITDA Reported PAT
FY19 (Rs Billion) 100.68 8.03 7.05
Growth over FY18 (%) 32.52 32.30 23.83

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....Name one major challenge faced in FY2018-19. How did the company tackle it?The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.Name one you consider the biggest contributor to the company’s growth in FY2018-19.Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. What are your plans for the company’s growth in FY2019-20? In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20.  .tg {border-collapse:collapse;border-spacing:0;} .tg td{font-family:Arial, sans-serif;font-size:14px;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg th{font-family:Arial, sans-serif;font-size:14px;font-weight:normal;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg .tg-eohl{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:right;vertical-align:top} .tg .tg-v56s{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-5agr{color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-39dc{color:#343434;border-color:inherit;text-align:right;vertical-align:top} Rail Vikas Nigam Net Sales EBITDA Reported PAT FY19 (Rs Billion) 100.68 8.03 7.05 Growth over FY18 (%) 32.52 32.30 23.83

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement