In FY2019-20, we are working towards a 35 per cent growth in turnover
ROADS & HIGHWAYS

In FY2019-20, we are working towards a 35 per cent growth in turnover

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....

Name one major challenge faced in FY2018-19. How did the company tackle it?
The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.

Name one you consider the biggest contributor to the company’s growth in FY2018-19.
Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.

What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?
RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. 

What are your plans for the company’s growth in FY2019-20? 
In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20. 

Rail Vikas Nigam
Net Sales EBITDA Reported PAT
FY19 (Rs Billion) 100.68 8.03 7.05
Growth over FY18 (%) 32.52 32.30 23.83

Rail Vikas Nigam (RVNL), a CPSE under the Ministry of Railways,was incorporated in 2003 to raise non-budgetary resources for implementation of rail capacity augmentation projects and their implementation on a fast-track basis. It is headed by Pradeep Gaur, Chairman & Managing Director, who is assisted by three functional directors and a CFO. RVNL has completed 8879.65 km of project length covering 360.01 km of new lines, 2932.35km of doubling, 1783.22 km of gauge conversion, 3762.07 km of railway electrification, 42 km of Metropolitan Transport Project (MTP), seven railway workshops, one cable-stayed bridge at Bardhhaman and four other specific works. Gaur shares more....Name one major challenge faced in FY2018-19. How did the company tackle it?The primary activity of RVNL is commissioning of rail infrastructure. Commissioning is directly related to release of funds by the Ministry of Railways. The problems faced owing to funds for commissioning of rail infrastructure were closely followed up with the Ministry of Railways/Ministry of Finance/IRFC and funds were arranged. In FY2018-19, the commissioning of new lines/gauge conversion/doubling (NL/GC/DL) increased by 61 per cent and railway electrification rose by 85 per cent.Name one you consider the biggest contributor to the company’s growth in FY2018-19.Our approach was based on the synergy of various verticals and employee satisfaction. All issues pertaining to project delivery, general progress of the company and employee satisfaction were closely looked into and timely action was taken to resolve them.What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?RVNL is executing some projects on a cost-sharing basis between the Ministry of Railways and respective state governments. Owing to a precarious financial position, the administrations at state level were not able to provide their share of funds. Consequently, RVNL slowed down work on these projects to reduce the liability of the company. What are your plans for the company’s growth in FY2019-20? In FY 2019-20, we are working towards a 35 per cent growth in turnover and a 50 per cent increase in commissioning of projects (NL/GC/DL) and railway electrification. At present, around 15 days are taken by the Ministry to reimburse all project expenditure incurred by our company. A joint procedure order is currently under modification to bring this time period down to three days. RVNL has already commissioned the Obulavaripalli-Krishnapatnam (125 km) new line, which is built on the PPP model. Another PPP project, the Haridaspur-Paradeep (82 km) new line, is being targeted for commissioning in FY 2019-20.  .tg {border-collapse:collapse;border-spacing:0;} .tg td{font-family:Arial, sans-serif;font-size:14px;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg th{font-family:Arial, sans-serif;font-size:14px;font-weight:normal;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg .tg-eohl{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:right;vertical-align:top} .tg .tg-v56s{font-weight:bold;background-color:#ffcb2f;color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-5agr{color:#343434;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-39dc{color:#343434;border-color:inherit;text-align:right;vertical-align:top} Rail Vikas Nigam Net Sales EBITDA Reported PAT FY19 (Rs Billion) 100.68 8.03 7.05 Growth over FY18 (%) 32.52 32.30 23.83

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement