MEIL makes major breakthrough in Zojila La tunnel project
ROADS & HIGHWAYS

MEIL makes major breakthrough in Zojila La tunnel project

Hyderabad-based Megha Engineering and Infrastructures Limited (MEIL) completed the excavation of the second tube of Tunnel-1 on Monday, bringing the strategic Zoji La tunnel one step closer to providing all-weather road connectivity between Jammu and Kashmir and Ladakh.

T-1 has two tubes, each with a length of 448 m and 472 m, according to officials. On November 4, the first tube was day-lighted, and the second tube was day-lighted today. Officials claim that the difficult task was completed ahead of schedule. Tunnelling this stretch was difficult because water kept seeping in.

The Zoji La project is 32 km long and is divided into two sections. Two twin-tube tunnels, five bridges, and two snow galleries will be part of the highway. Part 1 of the project, which spans 18 km and includes major bridges and twin tunnels, connects Sonamarg and Taltal. Officials have stated that the next twin tubes, each measuring two km in length, will achieve day-lighting in April 2022. The Zoji La project was awarded to MEIL, a leading infrastructure company, in 2020.

The Zoji La Tunnel is a 14.2 km long road tunnel under the Zoji La pass in the Himalayas that connects Sonmarg and Drass town in the Kargil district of the Indian Union Territory of Ladakh. It is currently under construction and is expected to be completed in about five to seven years after construction began in 2018. The tunnel, along with the 6.5 km long Z-Morh Tunnel, will ensure year-round road connectivity between Srinagar and Kargil, which has been closed for about seven months due to heavy snowfall on the Zoji La pass on the Srinagar-Kargil-Leh highway. Zoji La is 15 km from Sonamarg and serves as a vital link between Ladakh's Drass and Kargil. Due to heavy snowfall and snow avalanches, it is closed for six to seven months during the winter.

Image Source

Hyderabad-based Megha Engineering and Infrastructures Limited (MEIL) completed the excavation of the second tube of Tunnel-1 on Monday, bringing the strategic Zoji La tunnel one step closer to providing all-weather road connectivity between Jammu and Kashmir and Ladakh. T-1 has two tubes, each with a length of 448 m and 472 m, according to officials. On November 4, the first tube was day-lighted, and the second tube was day-lighted today. Officials claim that the difficult task was completed ahead of schedule. Tunnelling this stretch was difficult because water kept seeping in. The Zoji La project is 32 km long and is divided into two sections. Two twin-tube tunnels, five bridges, and two snow galleries will be part of the highway. Part 1 of the project, which spans 18 km and includes major bridges and twin tunnels, connects Sonamarg and Taltal. Officials have stated that the next twin tubes, each measuring two km in length, will achieve day-lighting in April 2022. The Zoji La project was awarded to MEIL, a leading infrastructure company, in 2020. The Zoji La Tunnel is a 14.2 km long road tunnel under the Zoji La pass in the Himalayas that connects Sonmarg and Drass town in the Kargil district of the Indian Union Territory of Ladakh. It is currently under construction and is expected to be completed in about five to seven years after construction began in 2018. The tunnel, along with the 6.5 km long Z-Morh Tunnel, will ensure year-round road connectivity between Srinagar and Kargil, which has been closed for about seven months due to heavy snowfall on the Zoji La pass on the Srinagar-Kargil-Leh highway. Zoji La is 15 km from Sonamarg and serves as a vital link between Ladakh's Drass and Kargil. Due to heavy snowfall and snow avalanches, it is closed for six to seven months during the winter. Image Source

Next Story
Infrastructure Energy

Vikram Solar Secures 200 MW Order From AB Energia

Vikram Solar added 1.44 per cent to Rs 362.45 after announcing a significant order win of 200 MW high-efficiency solar modules from AB Energia, a specialist in end-to-end EPC solutions for commercial and industrial (C&I) solar projects.The modules, rated at 590 Wp and above, will be deployed across Maharashtra, Madhya Pradesh, and Gujarat. Deliveries are scheduled to begin in September 2025 and continue into early 2026.Gyanesh Chaudhary, chairman and managing director of Vikram Solar, stated, “We are proud to continue our collaboration with partners who share our vision for accelerating ..

Next Story
Infrastructure Energy

India Pushes Green Hydrogen Innovation to Lead Global Market

India’s drive towards achieving Net Zero by 2070 has gained fresh momentum as Union Minister of State for New and Renewable Energy, Shripad Yesso Naik, called on scientists, startups, researchers, and industry leaders to position India as a global hub for green hydrogen innovation.He was speaking at the valedictory session of the first Green Hydrogen R&D Conference, organised under the National Green Hydrogen Mission by the Ministry of New and Renewable Energy (MNRE). The two-day event brought together experts to chart India’s course towards a clean, secure, and self-reliant energy fut..

Next Story
Infrastructure Energy

NARCL Sells Rs 37.63 Billion of Wind World Debt to Omkara ARC

The National Asset Reconstruction Company Limited (NARCL) has successfully sold Rs 37.63 billion of Wind World’s outstanding debt, marking a significant step in managing stressed assets within India’s renewable energy sector. The transaction forms part of wider efforts to resolve non-performing loans and bolster financial stability in the industry.Omkara ARC emerged as the anchor bidder in the deal, demonstrating strong investor interest in renewable energy debt. Anchor bidders play a vital role in ensuring successful debt resolution and attracting participation from other investors in suc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?