MEIL makes major breakthrough in Zojila La tunnel project
ROADS & HIGHWAYS

MEIL makes major breakthrough in Zojila La tunnel project

Hyderabad-based Megha Engineering and Infrastructures Limited (MEIL) completed the excavation of the second tube of Tunnel-1 on Monday, bringing the strategic Zoji La tunnel one step closer to providing all-weather road connectivity between Jammu and Kashmir and Ladakh.

T-1 has two tubes, each with a length of 448 m and 472 m, according to officials. On November 4, the first tube was day-lighted, and the second tube was day-lighted today. Officials claim that the difficult task was completed ahead of schedule. Tunnelling this stretch was difficult because water kept seeping in.

The Zoji La project is 32 km long and is divided into two sections. Two twin-tube tunnels, five bridges, and two snow galleries will be part of the highway. Part 1 of the project, which spans 18 km and includes major bridges and twin tunnels, connects Sonamarg and Taltal. Officials have stated that the next twin tubes, each measuring two km in length, will achieve day-lighting in April 2022. The Zoji La project was awarded to MEIL, a leading infrastructure company, in 2020.

The Zoji La Tunnel is a 14.2 km long road tunnel under the Zoji La pass in the Himalayas that connects Sonmarg and Drass town in the Kargil district of the Indian Union Territory of Ladakh. It is currently under construction and is expected to be completed in about five to seven years after construction began in 2018. The tunnel, along with the 6.5 km long Z-Morh Tunnel, will ensure year-round road connectivity between Srinagar and Kargil, which has been closed for about seven months due to heavy snowfall on the Zoji La pass on the Srinagar-Kargil-Leh highway. Zoji La is 15 km from Sonamarg and serves as a vital link between Ladakh's Drass and Kargil. Due to heavy snowfall and snow avalanches, it is closed for six to seven months during the winter.

Image Source

Hyderabad-based Megha Engineering and Infrastructures Limited (MEIL) completed the excavation of the second tube of Tunnel-1 on Monday, bringing the strategic Zoji La tunnel one step closer to providing all-weather road connectivity between Jammu and Kashmir and Ladakh. T-1 has two tubes, each with a length of 448 m and 472 m, according to officials. On November 4, the first tube was day-lighted, and the second tube was day-lighted today. Officials claim that the difficult task was completed ahead of schedule. Tunnelling this stretch was difficult because water kept seeping in. The Zoji La project is 32 km long and is divided into two sections. Two twin-tube tunnels, five bridges, and two snow galleries will be part of the highway. Part 1 of the project, which spans 18 km and includes major bridges and twin tunnels, connects Sonamarg and Taltal. Officials have stated that the next twin tubes, each measuring two km in length, will achieve day-lighting in April 2022. The Zoji La project was awarded to MEIL, a leading infrastructure company, in 2020. The Zoji La Tunnel is a 14.2 km long road tunnel under the Zoji La pass in the Himalayas that connects Sonmarg and Drass town in the Kargil district of the Indian Union Territory of Ladakh. It is currently under construction and is expected to be completed in about five to seven years after construction began in 2018. The tunnel, along with the 6.5 km long Z-Morh Tunnel, will ensure year-round road connectivity between Srinagar and Kargil, which has been closed for about seven months due to heavy snowfall on the Zoji La pass on the Srinagar-Kargil-Leh highway. Zoji La is 15 km from Sonamarg and serves as a vital link between Ladakh's Drass and Kargil. Due to heavy snowfall and snow avalanches, it is closed for six to seven months during the winter. Image Source

Related Stories

Gold Stories

Next Story
Infrastructure Urban

KONE Opens India's First Digital Experience Centre in Pune

KONE, a global elevator and escalator manufacturer, has inaugurated its first Digital Experience Centre (DEC) in India, located in Pune. The facility aims to showcase how artificial intelligence (AI), connectivity and data-driven technologies can enhance customer experiences and improve building operations.The centre was inaugurated by Jussi Herlin, Executive Vice Chair, KONE Corporation; Philippe Delorme, President and CEO, KONE; and Nandan Nilekani, Co-founder and Chairman of the Board, Infosys.Designed as an interactive customer environment, the facility demonstrates digital solutions cover..

Next Story
Infrastructure Urban

CII GreenCo Launches Circularity Guidelines for Indian Industry

The Confederation of Indian Industry (CII) GreenCo Council has launched the CII GreenCo Circularity Guidelines – Pilot Version at the 17th CII GreenCo Waste & Resource Management Summit 2026 in Chennai. The initiative aims to strengthen resource efficiency, waste reduction and circular economy practices across Indian manufacturing and process industries.The guidelines introduce a structured framework with circularity indices covering raw materials, consumables, packaging and other resource inputs. These indicators will help industries assess existing practices, identify opportunities to ..

Next Story
Infrastructure Energy

Global Electronics Association Launches IPC-1783-CO2E Standard

The Global Electronics Association has introduced IPC-1783-CO2E, a new international standard aimed at improving consistency, transparency and comparability in product carbon footprint reporting across the electronics manufacturing industry.The standard, titled International Standard for Data Collection and Reporting of CO2 Equivalent (CO2e) Emissions for the Electronics Manufacturing Supply Chain, provides industry-specific guidance for collecting, estimating and reporting carbon emissions data.With increasing regulatory requirements and customer expectations, electronics manufacturers face c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code