More than 80 per cent of issues pertained to the state governments
ROADS & HIGHWAYS

More than 80 per cent of issues pertained to the state governments

Arun Goyal, Former Secretary to Government of India and Ex-Head of the Project Monitoring Group (PMG), had a long stint in the Group from October 2015 to February 2019.The group was tasked with fast-tracking, setting up and implementing large public, private and public-private partnership (PPP) projects by resolving a variety of issues. The group mainly dealt with projects with anticipated investment above Rs 10 billion (Rs 5 billion in case of projects with FDI). “The issues uploaded by project proponents on PMG’s portal were resolved through regular review,” says Goyal. “The review was carried through inter-ministerial subgroups and state-level meetings with respective chief secretaries or senior level-officers at state capitals or through video conference.Project proponents were also invited for these review meetings. During my three-and-a-half-year stint at PMG, more than 3,400 issues pertaining to over 720 projects were resolved under the mechanism.” Goyal shares more on solutions to avoid time and cost overruns, in conversation with SERAPHINA D’SOUZA...

  • “I observed that issues leading to time or cost overruns pertained to both the Centre and state governments. Central Government issues included environment, forest and wildlife clearances; eco-sensitive zone clearances; sanction of debt funds and working capital by banks or financial institutions; approval for private railways siding construction; and permission for road crossing of pipelines, transmission lines, railway lines and shifting of utilities. State government issues included land acquisition issues such as government notifications or disbursement of compensation and mutation; removalof encroachments and handing over possession of land; formulation of relief and rehabilitation plans; issue of certificate under the Forest Rights Act; tree-cutting permissions; grant of right of way (RoW) permissions; consent to establish and operate from the State Pollution Control Board; and transfer of government land.
  • I found that most of the issues on our portal pertained to the Central Government’s linear projects such as highways and rail lines, transmission lines and pipelines. Very few issues pertaining to the Central Government were pending on PMG’s portal at a particular time. In the Central Government, rigorous and digital monitoring mechanisms ensured issues were addressed quickly. More than 80 per cent of issues pertained to the state governments. As projects are executed on ground in different states, response varied from state to state. Some states were also slow in responding to issues owing to political reasons.
  • I have observed that once there is cost and time overrun in a public project, project execution tends to get further delayed. In a delayed project, decision-making involves deviations from the terms and conditions of the tender and, at times, the financial implications may be huge. In such circumstances, public-sector executives and civil servants tend be cautious and sometimes the procedures involved are also lengthy.
  • There is another important difference in project execution between the private sector and public sector. A public-sector employee has to follow all procedures of tendering, etc, without consideration of the time and amount already invested into the project. On the other hand, a private-sector executive is able to factor in opportunity and the cost involved because of the amount and time already invested and need not follow all procedures.
  • Overall, I feel there has to be a sense of urgency amongstate-level officials, particularly at the district level, to proactively resolve and expedite local-level issues. This is particularly important for linear projects because, sometimes, a long, linear project with huge investment may get stalled because of issues involved in a small patch of land.”

    Arun Goyal, Former Secretary to Government of India and Ex-Head of the Project Monitoring Group (PMG), had a long stint in the Group from October 2015 to February 2019.The group was tasked with fast-tracking, setting up and implementing large public, private and public-private partnership (PPP) projects by resolving a variety of issues. The group mainly dealt with projects with anticipated investment above Rs 10 billion (Rs 5 billion in case of projects with FDI). “The issues uploaded by project proponents on PMG’s portal were resolved through regular review,” says Goyal. “The review was carried through inter-ministerial subgroups and state-level meetings with respective chief secretaries or senior level-officers at state capitals or through video conference.Project proponents were also invited for these review meetings. During my three-and-a-half-year stint at PMG, more than 3,400 issues pertaining to over 720 projects were resolved under the mechanism.” Goyal shares more on solutions to avoid time and cost overruns, in conversation with SERAPHINA D’SOUZA... “I observed that issues leading to time or cost overruns pertained to both the Centre and state governments. Central Government issues included environment, forest and wildlife clearances; eco-sensitive zone clearances; sanction of debt funds and working capital by banks or financial institutions; approval for private railways siding construction; and permission for road crossing of pipelines, transmission lines, railway lines and shifting of utilities. State government issues included land acquisition issues such as government notifications or disbursement of compensation and mutation; removalof encroachments and handing over possession of land; formulation of relief and rehabilitation plans; issue of certificate under the Forest Rights Act; tree-cutting permissions; grant of right of way (RoW) permissions; consent to establish and operate from the State Pollution Control Board; and transfer of government land. I found that most of the issues on our portal pertained to the Central Government’s linear projects such as highways and rail lines, transmission lines and pipelines. Very few issues pertaining to the Central Government were pending on PMG’s portal at a particular time. In the Central Government, rigorous and digital monitoring mechanisms ensured issues were addressed quickly. More than 80 per cent of issues pertained to the state governments. As projects are executed on ground in different states, response varied from state to state. Some states were also slow in responding to issues owing to political reasons. I have observed that once there is cost and time overrun in a public project, project execution tends to get further delayed. In a delayed project, decision-making involves deviations from the terms and conditions of the tender and, at times, the financial implications may be huge. In such circumstances, public-sector executives and civil servants tend be cautious and sometimes the procedures involved are also lengthy. There is another important difference in project execution between the private sector and public sector. A public-sector employee has to follow all procedures of tendering, etc, without consideration of the time and amount already invested into the project. On the other hand, a private-sector executive is able to factor in opportunity and the cost involved because of the amount and time already invested and need not follow all procedures. Overall, I feel there has to be a sense of urgency amongstate-level officials, particularly at the district level, to proactively resolve and expedite local-level issues. This is particularly important for linear projects because, sometimes, a long, linear project with huge investment may get stalled because of issues involved in a small patch of land.”

    Next Story
    Real Estate

    Integrated Waterproofing Strategies

    Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

    Next Story
    Infrastructure Urban

    GROHE Showcases Water-Led Design At Milan

    GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

    Next Story
    Infrastructure Transport

    Rahee Group Expands Rail Manufacturing Capacity

    Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    Advertisement

    Advertisement

    -->