Most 2D Software to construct Bogibeel Bridge
ROADS & HIGHWAYS

Most 2D Software to construct Bogibeel Bridge

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997.

For the Bogibeel Bridge, the initial plan was to use Pot-PTFE bearing with metallic pins and guide bearings. However, the size of the bearing required for taking the anticipated load could not be accommodated in the pier cap. Hence, spherical bearings with a four support system as per European bearing standard EN- 1337 have been used. A total of 164 such bearings have been used to construct the bridge. Each span is supported by four spherical bearings.

Most 2D software
At the Bogibeel project, the HCC team used ‘Most 2D’ automatic nesting software to generate efficient two-dimensional cutting plans for fabricating the steel superstructure. The nesting technology was based on advanced cutting algorithms specifically designed to optimise the cutting layouts in shearing. The software generates high-utilisation layouts, significantly reducing waste, and maximises productivity.

Corrosion protection measures
The superstructure of Bogibeel Bridge has been constructed using special grade copper-bearing steel plates to reduce corrosion. The average annual relative humidity in Bogibeel is 90 per cent, which goes up to 96-97 per cent. To further reduce corrosion from excessive humidity, a complex corrosion protection system specific to different components of the bridge has been implemented during construction.

As part of its corrosion protection measures, for various purposes based on the requirement, the team used aluminium metal spraying, hot zinc spray, metal spray zinc coating, inorganic zinc silicate, primers, and hot-dip galvanising, among others.

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997. For the Bogibeel Bridge, the initial plan was to use Pot-PTFE bearing with metallic pins and guide bearings. However, the size of the bearing required for taking the anticipated load could not be accommodated in the pier cap. Hence, spherical bearings with a four support system as per European bearing standard EN- 1337 have been used. A total of 164 such bearings have been used to construct the bridge. Each span is supported by four spherical bearings. Most 2D software At the Bogibeel project, the HCC team used ‘Most 2D’ automatic nesting software to generate efficient two-dimensional cutting plans for fabricating the steel superstructure. The nesting technology was based on advanced cutting algorithms specifically designed to optimise the cutting layouts in shearing. The software generates high-utilisation layouts, significantly reducing waste, and maximises productivity. Corrosion protection measures The superstructure of Bogibeel Bridge has been constructed using special grade copper-bearing steel plates to reduce corrosion. The average annual relative humidity in Bogibeel is 90 per cent, which goes up to 96-97 per cent. To further reduce corrosion from excessive humidity, a complex corrosion protection system specific to different components of the bridge has been implemented during construction. As part of its corrosion protection measures, for various purposes based on the requirement, the team used aluminium metal spraying, hot zinc spray, metal spray zinc coating, inorganic zinc silicate, primers, and hot-dip galvanising, among others.

Next Story
Resources

Jyoti Structures Launches Heat Safety Drive Across Sites

Jyoti Structures (JSL) has strengthened heat safety measures across its project sites and manufacturing facilities as temperatures rise across India. The company has implemented a Summer Safety Plan covering all transmission line projects to address risks related to heat stress, dehydration and worker fatigue.The initiative includes rescheduling work away from peak afternoon temperatures, provision of drinking water, ORS and lemon-salt solutions, and installation of rest shelters near work areas. Daily toolbox talks, worker health monitoring, first-aid preparedness, emergency transport arrange..

Next Story
Real Estate

MHADA Declares 82 Buildings Most Dangerous in Central and South Mumbai

The Maharashtra Housing and Area Development Authority (MHADA) has declared 82 buildings as most dangerous across Central and South Mumbai and has appealed to residents to vacate immediately. The list, prepared after structural assessments by the authority, identifies buildings judged to pose imminent risk to occupants and to passersby. Local civic bodies have been asked to coordinate evacuations and to make arrangements for temporary shelter and rehabilitation for displaced households. Officials said the authority prioritised buildings with visible structural distress, severe cracking, tiltin..

Next Story
Infrastructure Transport

Damage Reported At Halwara Airport Terminal After First Rains

Severe damage was reported at the terminal of Halwara Airport during the first major rain spell of the season, prompting immediate concern among aviation and local authorities. Images from the site showed water ingress and visible deterioration of the terminal interior, affecting passenger areas and ancillary services. The airport authority suspended certain operations temporarily to assess structural safety and ensure passenger wellbeing. Preliminary inspections have prioritised electrical systems and roof seals to prevent further water ingress. State aviation officials ordered a formal inqui..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->