Mumbai-Pune Missing Link Project 96% Done, New Completion by September
ROADS & HIGHWAYS

Mumbai-Pune Missing Link Project 96% Done, New Completion by September

The much-anticipated “missing link” road project between Mumbai and Pune is reportedly 96 pre cent complete, with the Maharashtra State Road Development Corporation (MSRDC) targeting its opening by September 2025.

The project features several significant engineering components, including a 1.75 km tunnel, an 840-meter viaduct, a 650-meter cable-stayed bridge over Tiger Valley, and an 8.9 km tunnel that passes 170 feet below Lonavala Lake. Among these, the cable-stayed bridge, which rises 180 meters above Khandala Valley, is considered one of the most challenging sections. MSRDC officials indicated that completing this part is particularly difficult, especially with the monsoon season approaching.

Upon completion, the 13 km stretch is expected to reduce the distance between Mumbai and Pune by 5.7 km and cut travel time by approximately 30 minutes. The new road will allow vehicles to travel at speeds of up to 120 km/h. In addition to saving time, the project aims to enhance safety by rerouting the expressway away from areas prone to landslides and falling rocks, which frequently cause accidents and traffic congestion during the rainy season. The MSRDC’s goal is to transform the Mumbai-Pune Expressway into a “zero-fatality corridor.”

Despite facing multiple delays, the Rs 66-billion project has progressed steadily. Initially scheduled to open in March 2024, the deadline was postponed first to January, then March 2025, and is now set for September 2025. MSRDC representatives acknowledged that construction near Lonavala has been particularly challenging but assured that work is proceeding cautiously to avoid disrupting traffic on the current expressway, which remains one of India’s busiest highways.

Currently, the tunnels and the first viaduct have been completed. These completed structures are being used by workers to access the site for the construction of the second viaduct, which is still underway across the valley. Officials have emphasized maintaining safety and consistent progress as they approach the final stages of the project.


News source: Pune Pulse

The much-anticipated “missing link” road project between Mumbai and Pune is reportedly 96 pre cent complete, with the Maharashtra State Road Development Corporation (MSRDC) targeting its opening by September 2025.The project features several significant engineering components, including a 1.75 km tunnel, an 840-meter viaduct, a 650-meter cable-stayed bridge over Tiger Valley, and an 8.9 km tunnel that passes 170 feet below Lonavala Lake. Among these, the cable-stayed bridge, which rises 180 meters above Khandala Valley, is considered one of the most challenging sections. MSRDC officials indicated that completing this part is particularly difficult, especially with the monsoon season approaching.Upon completion, the 13 km stretch is expected to reduce the distance between Mumbai and Pune by 5.7 km and cut travel time by approximately 30 minutes. The new road will allow vehicles to travel at speeds of up to 120 km/h. In addition to saving time, the project aims to enhance safety by rerouting the expressway away from areas prone to landslides and falling rocks, which frequently cause accidents and traffic congestion during the rainy season. The MSRDC’s goal is to transform the Mumbai-Pune Expressway into a “zero-fatality corridor.”Despite facing multiple delays, the Rs 66-billion project has progressed steadily. Initially scheduled to open in March 2024, the deadline was postponed first to January, then March 2025, and is now set for September 2025. MSRDC representatives acknowledged that construction near Lonavala has been particularly challenging but assured that work is proceeding cautiously to avoid disrupting traffic on the current expressway, which remains one of India’s busiest highways.Currently, the tunnels and the first viaduct have been completed. These completed structures are being used by workers to access the site for the construction of the second viaduct, which is still underway across the valley. Officials have emphasized maintaining safety and consistent progress as they approach the final stages of the project.News source: Pune Pulse

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement