Sinhagad Road Flyover’s 2.12-km Stretch to Open in Pune Next Month
ROADS & HIGHWAYS

Sinhagad Road Flyover’s 2.12-km Stretch to Open in Pune Next Month

The much-anticipated flyover on Sinhagad Road is set to open for the public soon, as the Pune Municipal Corporation (PMC) has nearly completed work on the 2.2 km long lane from Vithalwadi to Funtime Theatre. Work on the opposite lane, a 1.54 km stretch from Indian Hume Pipe to Inamdar Chowk, is expected to be completed by June.

Phase-1 of the project, a 520-metre-long flyover at Rajaram Bridge Chowk on Sinhagad Road, was completed in August last year. This followed criticism from the opposition, which accused the civic administration of delaying the inauguration due to the unavailability of ministers. At that point, the focus shifted to completing the largest part of the flyover in Phase-2, which would help commuters bypass five traffic signals on the congested road. The project is estimated to cost Rs 1.18 billion, with an additional Rs 270 million allocated for the metro pillars.

Phase-2 of the project includes a 2.12 km flyover on one side from Vithalwadi to Fun Time Theatre, and a 1.54 km flyover from Indian Hume Pipe to Inamdar Chowk. According to Yuvraj Deshmukh, the Chief Engineer of PMC, the work on the 2.12 km lane is complete, except for signages and other minor tasks, and it is expected to be opened by next week. However, the work on the opposite 1.54 km stretch will only be completed by June. Municipal Commissioner Rajendra Bhosale inspected the 2.12 km long flyover to check its progress.

The flyover is expected to help motorists avoid traffic signals at Vitthalwadi, Hingne Khurd, Anandnagar, Bramha Hotel, and Goel Ganga Chowk while traveling from Vithalwadi to Fun Time Theatre on Sinhagad Road. The other lane will help bypass traffic signals at Bramha Hotel, Anandnagar, and Hingne Khurd.

The primary objective of the flyover is to alleviate traffic congestion at the Rajaram Bridge junction and ease traffic flow on Sinhagad Road. It will also make it easier for pedestrians to cross the road and improve travel to Swargate, while reducing fuel consumption for vehicles that otherwise get stuck in traffic jams.

The delay in the project occurred when it was decided to accommodate the construction of metro station pillars for the proposed metro route from Khadakwasla to Hadapsar via Swargate. The foundation for the pillars at Manik Baug and Hingane Khurd has already been completed, which added an additional Rs 27 crore to the project cost, as stated by officials.

The project had sparked controversy, as it lies on the planned route for the Pune Metro. Union Minister Nitin Gadkari, who laid the foundation stone for the project three years ago, had suggested exploring the possibility of a two-storey bridge, with the Metro on the top and a vehicle bridge on the first floor, similar to structures in Karve Road and Nagpur. Metro work is expected to begin once the flyover is completed, pending approval from the state government.

News source: The Indian Express

The much-anticipated flyover on Sinhagad Road is set to open for the public soon, as the Pune Municipal Corporation (PMC) has nearly completed work on the 2.2 km long lane from Vithalwadi to Funtime Theatre. Work on the opposite lane, a 1.54 km stretch from Indian Hume Pipe to Inamdar Chowk, is expected to be completed by June. Phase-1 of the project, a 520-metre-long flyover at Rajaram Bridge Chowk on Sinhagad Road, was completed in August last year. This followed criticism from the opposition, which accused the civic administration of delaying the inauguration due to the unavailability of ministers. At that point, the focus shifted to completing the largest part of the flyover in Phase-2, which would help commuters bypass five traffic signals on the congested road. The project is estimated to cost Rs 1.18 billion, with an additional Rs 270 million allocated for the metro pillars. Phase-2 of the project includes a 2.12 km flyover on one side from Vithalwadi to Fun Time Theatre, and a 1.54 km flyover from Indian Hume Pipe to Inamdar Chowk. According to Yuvraj Deshmukh, the Chief Engineer of PMC, the work on the 2.12 km lane is complete, except for signages and other minor tasks, and it is expected to be opened by next week. However, the work on the opposite 1.54 km stretch will only be completed by June. Municipal Commissioner Rajendra Bhosale inspected the 2.12 km long flyover to check its progress. The flyover is expected to help motorists avoid traffic signals at Vitthalwadi, Hingne Khurd, Anandnagar, Bramha Hotel, and Goel Ganga Chowk while traveling from Vithalwadi to Fun Time Theatre on Sinhagad Road. The other lane will help bypass traffic signals at Bramha Hotel, Anandnagar, and Hingne Khurd. The primary objective of the flyover is to alleviate traffic congestion at the Rajaram Bridge junction and ease traffic flow on Sinhagad Road. It will also make it easier for pedestrians to cross the road and improve travel to Swargate, while reducing fuel consumption for vehicles that otherwise get stuck in traffic jams. The delay in the project occurred when it was decided to accommodate the construction of metro station pillars for the proposed metro route from Khadakwasla to Hadapsar via Swargate. The foundation for the pillars at Manik Baug and Hingane Khurd has already been completed, which added an additional Rs 27 crore to the project cost, as stated by officials. The project had sparked controversy, as it lies on the planned route for the Pune Metro. Union Minister Nitin Gadkari, who laid the foundation stone for the project three years ago, had suggested exploring the possibility of a two-storey bridge, with the Metro on the top and a vehicle bridge on the first floor, similar to structures in Karve Road and Nagpur. Metro work is expected to begin once the flyover is completed, pending approval from the state government. News source: The Indian Express

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code