45% Work Complete on Murkongselek–Pasighat Rail Line
RAILWAYS & METRO RAIL

45% Work Complete on Murkongselek–Pasighat Rail Line

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration.

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.

Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.

Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.

Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.

An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration. Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion. Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support. Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards. Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh. An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Next Story
Infrastructure Energy

L&T to Build India’s Largest Green Hydrogen Plant for IOCL

The plant will be developed on a build-own-operate (BOO) model and will supply 10,000 tonnes of green hydrogen annually to IOCL for a period of 25 years. It will operate entirely on renewable energy, aligning with IOCL’s decarbonisation goals and India’s broader net-zero ambitions.Green hydrogen at the plant will be produced using high-pressure alkaline electrolysers manufactured at L&T Electrolysers Ltd’s facility in Hazira, Gujarat. This initiative further showcases L&T’s commitment to localised, self-reliant clean-tech solutions under the Aatmanirbhar Bharat mission.LTEG’s..

Next Story
Infrastructure Urban

Bansal Wire Q1 Profit Rises 24.6% to Rs 393 Mn

Bansal Wire Industries, India’s largest stainless steel wire manufacturer and second-largest steel wire maker by volume, reported a 24.6 per cent year-on-year rise in net profit to Rs 393 million for the quarter ended June 30, 2025 (Q1 FY26).During the quarter, revenue rose 14.9 per cent YoY to Rs 9,390 million, while EBITDA increased by 19.6 per cent YoY to Rs 745 million, reflecting the company's strong operational performance and focus on value-added segments.According to Pranav Bansal, MD & CEO of Bansal Wire Industries, the company has started FY26 on a strong note, building on the ..

Next Story
Infrastructure Urban

Lemon Tree Opens Keys Lite Hotel in Banswara, Rajasthan

Lemon Tree Hotels has launched its latest property, Keys Lite by Lemon Tree Hotels, Banswara, further expanding its footprint in Rajasthan. This marks the group’s 11th operational hotel in the state and continues its focus on providing quality stays in emerging travel destinations.The newly launched managed hotel features 54 well-appointed rooms, a multi-cuisine restaurant – Keys Café, a fitness centre, and spacious banquet and conference facilities, catering to both leisure and business travellers.Located in southern Rajasthan, Banswara is known as the “City of Hundred Islands” for t..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?