45% Work Complete on Murkongselek–Pasighat Rail Line
RAILWAYS & METRO RAIL

45% Work Complete on Murkongselek–Pasighat Rail Line

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration.

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.

Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.

Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.

Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.

An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration. Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion. Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support. Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards. Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh. An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Next Story
Real Estate

Mahindra Lifespaces Bags Rs 12.5 billion Redevelopment in Mulund

Mahindra Lifespace Developers (MLDL), the real estate and infrastructure development arm of the Mahindra Group, has been appointed as the preferred developer for the redevelopment of a premium housing society in Mulund (West), Mumbai. The project will be developed across a 3.08-acre land parcel, with an estimated development value of approximately Rs 12.5 billion. Strategically located, the site enjoys proximity to major connectivity points—just 1.4 km from the upcoming Mumbai Metro Line 5 and 0.8 km from the Goregaon-Mulund Link Road. It also offers seamless access to the Eastern Expre..

Next Story
Infrastructure Urban

Snowman Adds Warehouses in Kolkata and Krishnapatnam

Snowman Logistics, India’s leading integrated temperature-controlled logistics company, has announced the commencement of operations at its two new state-of-the-art, owned cold storage facilities in Kolkata and Krishnapatnam. With these additions, the company’s total pallet capacity has reached 1,50,754, spanning 43 warehouses in 20 cities across the country. The newly operational Kolkata facility offers a storage capacity of 5,630 pallets, while the Krishnapatnam facility holds 3,927 pallets. These warehouses are equipped with advanced automation and infrastructure designed to enhanc..

Next Story
Resources

Noesis Enables IHCL Hotel Deal in Udupi–Manipal Corridor

NOESIS Capital Advisors, India’s leading hotel investment advisory firm, has successfully facilitated a landmark hospitality transaction in the Udupi–Manipal region of Karnataka. The deal involves the acquisition of a nearly completed, 130-key upscale hotel that will operate under one of the premium brands of IHCL, reinforcing NOESIS’ position as a preferred partner for strategic hospitality transactions across India. Strategically located on the Udupi–Manipal Highway, the 1.03-acre property will cater to business travellers, pilgrims and families visiting Manipal University. With..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?