45% Work Complete on Murkongselek–Pasighat Rail Line
RAILWAYS & METRO RAIL

45% Work Complete on Murkongselek–Pasighat Rail Line

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration.

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.

Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.

Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.

Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.

An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration. Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion. Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support. Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards. Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh. An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Next Story
Equipment

Schwing Stetter India Unveils New Innovations at Excon 2025

Schwing Stetter India unveiled more than 20 new machines at Excon 2025, marking one of its most significant showcases and introducing several India-first technologies to the construction equipment sector. The company launched the country’s first 56-metre boom pump designed and manufactured in India, the first fully electric truck mixer, the first CNG mixer variant and the first hybrid boom pump. Executives said the launch portfolio was engineered to support India’s move toward faster, greener and more vertically oriented infrastructure through advanced engineering, clean-energy solutions a..

Next Story
Infrastructure Energy

SEPC Resolves Hindustan Copper Dispute, Wins Rs 725 Mn Order

Engineering, procurement and construction firm SEPC Ltd has recently settled a dispute with Hindustan Copper Ltd (HCL) and secured a mining infrastructure order valued at Rs 725 million from the state-owned company. SEPC informed the stock exchanges that it has executed a settlement deed with HCL, bringing closure to all inter-se claims and counterclaims arising from arbitration proceedings. As part of the settlement, SEPC will receive Rs 304.5 million as full and final payment, marking the resolution of all pending disputes between the two entities. The company also stated that Hindustan Co..

Next Story
Infrastructure Energy

20% Ethanol Blending Cuts India’s CO2 Emissions by 73.6 Mn Tonnes

Union Road Transport and Highways Minister Nitin Gadkari recently said that India has reduced carbon dioxide emissions by 73.6 million metric tonnes due to the adoption of 20 per cent ethanol blending in petrol. He made the statement while replying to supplementary questions during the Question Hour in the Lok Sabha. Describing ethanol as a green fuel, the minister said it plays a key role in reducing pollution while also supporting higher incomes for farmers. He underlined that ethanol blending contributes both to environmental sustainability and rural economic growth. Nitin Gadkari also po..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App