45% Work Complete on Murkongselek–Pasighat Rail Line
RAILWAYS & METRO RAIL

45% Work Complete on Murkongselek–Pasighat Rail Line

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration.

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.

Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.

Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.

Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.

An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration. Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion. Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support. Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards. Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh. An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App