45% Work Complete on Murkongselek–Pasighat Rail Line
RAILWAYS & METRO RAIL

45% Work Complete on Murkongselek–Pasighat Rail Line

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration.

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.

Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.

Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.

Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.

An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration. Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion. Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support. Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards. Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh. An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Next Story
Infrastructure Transport

Chembur Metro to Boost East Mumbai Links

MMRDA is advancing eastern Mumbai’s urban mobility network, with the upcoming Chembur Metro Station set to emerge as a key interchange and the Mumbai Monorail preparing for relaunch.Dr Sanjay Mukherjee, Metropolitan Commissioner, MMRDA, conducted a site visit to Chembur Metro Station along with Kanhuraj Bagate, Managing Director, MMMOCL. He also visited the nearby VN Purav Monorail Station to review system preparedness and ease of interconnectivity.Once operational, the interchange is expected to offer commuters across the eastern suburbs quicker access, smoother transfers and seamless conne..

Next Story
Equipment

Herrenknecht TBMs Drive Thane–Borivali Tunnel Progress

Herrenknecht India has supplied two of the four tunnel boring machines (TBMs) required for the 11-km Thane–Borivali Twin Tunnel Project being developed by the Mumbai Metropolitan Region Development Authority (MMRDA). The project is expected to reduce travel time between Thane and Borivali from 60–90 minutes to around 15 minutes while easing congestion across the Mumbai Metropolitan Region.The first two Single Shield TBMs, named Nayak and Arjuna, feature 13.34-m cutterhead diameters and are designed for hard-rock excavation. They will be deployed to tunnel through the challenging geological..

Next Story
Resources

KBL Launches Smart Skid Mounted Fire Pump Set

Kirloskar Brothers (KBL) has launched its Smart Skid Mounted Fire Pump Set, an integrated fire protection solution designed to improve operational efficiency, remote monitoring and installation flexibility. The system was inaugurated by Ms Madhuritai Misal, Hon. Minister of State for Urban Development, Government of Maharashtra.The Smart Skid Mounted Fire Pump Set is a factory-tested, pre-packaged solution that combines FM/UL-certified motor and engine pump sets with IoT-enabled remote monitoring. Designed to deliver a flow rate of 170 m³/hr at a head of 100 metres, the system aims to provide..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->