45% Work Complete on Murkongselek–Pasighat Rail Line
RAILWAYS & METRO RAIL

45% Work Complete on Murkongselek–Pasighat Rail Line

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration.

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.

Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.

Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.

Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.

An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration. Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion. Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support. Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards. Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh. An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement