45% Work Complete on Murkongselek–Pasighat Rail Line
RAILWAYS & METRO RAIL

45% Work Complete on Murkongselek–Pasighat Rail Line

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration.

Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion.

Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support.

Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards.

Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh.

An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

The Murkongselek–Pasighat new line project, a key initiative by Northeast Frontier Railway (NFR) to enhance rail connectivity between Assam and Arunachal Pradesh, has achieved 45% physical progress as of March 31, 2025. The project, estimated at Rs 12.52 billion, is expected to play a crucial role in regional transportation and economic integration. Spanning 26.15 km, the project is being executed in two phases. In Phase I (Murkongselek to Sille – 15.60 km), earthwork is nearly complete, with 13.75 lakh cubic meters done out of a total 14.16 lakh cubic meters. Work on 18 major and 35 minor bridges is advancing steadily. Ballast supply and track linking are set to begin soon, and the Murkongselek station building is nearing completion. Phase II (Sille to Pasighat – 10.55 km) has seen 3.55 lakh cubic meters of earthwork completed out of 6.85 lakh cubic meters. Bridge construction and casting are in progress, while land acquisition for a key road overbridge at Pasighat Yard is being expedited with local support. Despite extended monsoon seasons and local disruptions, construction has continued at a steady pace. The NFR’s General Manager (Construction) recently inspected the site and emphasized timely completion while maintaining quality standards. Once completed, the new railway line is expected to boost tourism, enhance national integration, and open up access to remote border areas of Arunachal Pradesh. An NFR spokesperson reiterated Indian Railways’ commitment to executing this strategic infrastructure project, overcoming both environmental and logistical challenges.

Next Story
Infrastructure Energy

BGR Tech–Collabrah Wins Rs 530.5 Mn Project from Oil India

BGR Tech, in partnership with Collabrah India, has secured a Rs 530.5 million contract from Oil India (OIL) for the deployment of six Surface Production Facilities (SPFs) across OIL’s operational zones in Assam. The three-year project includes a Framework Agreement, allowing for the provision of additional units if required. The collaboration leverages BGR Tech’s engineering expertise and Collabrah’s execution capabilities to support OIL India’s production expansion plans in line with the Ministry of Petroleum & Natural Gas’s vision for domestic energy growth. Following this win, BG..

Next Story
Infrastructure Energy

Rosatom Showcases Nuclear Energy Solutions at POWERGEN India 2025

Representatives of Rosatom participated in the international forum POWERGEN India & Indian Utility Week 2025, held in New Delhi from September 2–4. As part of the event, a panel discussion titled “Reinventing Atomic Energy for a Net Zero Future” featured industry leaders from Rosatom, the Council on Energy, Environment and Water (CEEW), NTPC Ltd, and other energy experts.Ekaterina Astashina, Rosatom’s Business Development Manager for South Asia, highlighted the importance of nuclear energy in achieving decarbonisation goals and shared Rosatom’s experience in India.“Through the ..

Next Story
Building Material

Assam Govt Defends Land Allotment to Cement Firm in Dima Hasao

The Assam government has informed the Gauhati High Court that the allotment of 3,000 bighas of land in Dima Hasao district to Mahabal Cement for setting up a cement factory was carried out in accordance with the “due process of law.”Appearing before the court, Advocate General Devajit Saikia submitted a report prepared by a three-member committee, which examined the land allotment, its suitability and potential implications.Saikia clarified that the cement company, part of the Trivikram Consortium, had sought 6,000 bighas, of which 3,000 bighas were allotted by the autonomous council in tw..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?