+
6th Open Web Girder Launched for Mumbai-Ahmedabad Bullet Train
RAILWAYS & METRO RAIL

6th Open Web Girder Launched for Mumbai-Ahmedabad Bullet Train

M G Contractors Pvt. Ltd. (MGCPL) has successfully launched the sixth open web girder (OWG) bridge for the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR) project. 
The 100-meter-long steel bridge for GAD-12, part of MAHSR’s Package P1(B), was installed over the Western Railways’ Baroda-Surat line and the Western Dedicated Freight Corridor (WDFC) in Gujarat. The launch site, located between Sayan and Kim near Surat, lies between MAHSR’s chainage KM 285+927m and KM 286+007m. 

Standing 12.5 meters tall and 14.3 meters wide, the 2,000 MT bridge was positioned using rollers and hydraulic jacks. A temporary launching nose was attached to assist in the process, which was completed in two days using traffic and power blocks to minimise disruptions to regular train services. 

The bridge and launching nose were pre-assembled at a height of 14.5 meters on temporary trestles and pulled into place using two semi-automatic jacks, each with a 250-ton capacity. 

MGCPL was awarded the Rs 5.49 billion contract for Package P1(B) by the National High-Speed Rail Corporation (NHSRCL) in September 2021. The package involves launching four PSC bridges and seven steel truss bridges within the 237.1 km civil Package C-4 (Vadodara-Zaroli), currently under construction by Larsen & Toubro. 

A total of 70,865 MT of steel will be used to fabricate 28 bridges for India’s first bullet train. So far, three OWG bridges have been launched under Package P1(B) and three under Package P1(C), marking significant progress in the project. 

(themetrorailguy)      

M G Contractors Pvt. Ltd. (MGCPL) has successfully launched the sixth open web girder (OWG) bridge for the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR) project. The 100-meter-long steel bridge for GAD-12, part of MAHSR’s Package P1(B), was installed over the Western Railways’ Baroda-Surat line and the Western Dedicated Freight Corridor (WDFC) in Gujarat. The launch site, located between Sayan and Kim near Surat, lies between MAHSR’s chainage KM 285+927m and KM 286+007m. Standing 12.5 meters tall and 14.3 meters wide, the 2,000 MT bridge was positioned using rollers and hydraulic jacks. A temporary launching nose was attached to assist in the process, which was completed in two days using traffic and power blocks to minimise disruptions to regular train services. The bridge and launching nose were pre-assembled at a height of 14.5 meters on temporary trestles and pulled into place using two semi-automatic jacks, each with a 250-ton capacity. MGCPL was awarded the Rs 5.49 billion contract for Package P1(B) by the National High-Speed Rail Corporation (NHSRCL) in September 2021. The package involves launching four PSC bridges and seven steel truss bridges within the 237.1 km civil Package C-4 (Vadodara-Zaroli), currently under construction by Larsen & Toubro. A total of 70,865 MT of steel will be used to fabricate 28 bridges for India’s first bullet train. So far, three OWG bridges have been launched under Package P1(B) and three under Package P1(C), marking significant progress in the project. (themetrorailguy)      

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code