+
80 per cent Work Done on Mumbai Bullet Train’s BKC Station
RAILWAYS & METRO RAIL

80 per cent Work Done on Mumbai Bullet Train’s BKC Station

The National High-Speed Rail Corporation of India Limited (NHSRCL) announced significant progress on the Mumbai–Ahmedabad bullet train project, with 80 per cent of excavation completed at the Bandra Kurla Complex (BKC) station site in Mumbai.

The 21-kilometre-long underground and undersea tunnel connecting BKC to Shilphata in Thane district includes 16 kilometres being excavated using Tunnel Boring Machines and the remaining 5 kilometres via the New Austrian Tunnelling Method.

The NHSRCL, which is implementing the 508-kilometre Mumbai–Ahmedabad high-speed rail corridor, stated that base slab casting has already begun at both ends of the BKC station, which lies around 30 metres (100 feet) below ground level.

Base slab casting is also complete at Vikhroli (56 metres deep) and the Sawli shaft (39 metres deep), both critical for launching the tunnel boring machines and facilitating underground works.

Meanwhile, construction of elevated stations at Thane, Virar, and Boisar in Maharashtra is progressing rapidly, with approximately 44 kilometres of piers cast to date. In Palghar district, excavation of seven mountain tunnels is underway, alongside the construction of bridges across the Vaitarna, Ulhas, and Jagani rivers.

The total project cost is estimated at Rs 1.08 trillion (Rs 1.08 lakh crore). As per the funding structure, the Government of India will contribute Rs 100 billion (Rs 10,000 crore), while the states of Gujarat and Maharashtra will each provide Rs 50 billion (Rs 5,000 crore). The balance will be funded by Japan through a soft loan at an interest rate of 0.1 per cent. 

The National High-Speed Rail Corporation of India Limited (NHSRCL) announced significant progress on the Mumbai–Ahmedabad bullet train project, with 80 per cent of excavation completed at the Bandra Kurla Complex (BKC) station site in Mumbai.The 21-kilometre-long underground and undersea tunnel connecting BKC to Shilphata in Thane district includes 16 kilometres being excavated using Tunnel Boring Machines and the remaining 5 kilometres via the New Austrian Tunnelling Method.The NHSRCL, which is implementing the 508-kilometre Mumbai–Ahmedabad high-speed rail corridor, stated that base slab casting has already begun at both ends of the BKC station, which lies around 30 metres (100 feet) below ground level.Base slab casting is also complete at Vikhroli (56 metres deep) and the Sawli shaft (39 metres deep), both critical for launching the tunnel boring machines and facilitating underground works.Meanwhile, construction of elevated stations at Thane, Virar, and Boisar in Maharashtra is progressing rapidly, with approximately 44 kilometres of piers cast to date. In Palghar district, excavation of seven mountain tunnels is underway, alongside the construction of bridges across the Vaitarna, Ulhas, and Jagani rivers.The total project cost is estimated at Rs 1.08 trillion (Rs 1.08 lakh crore). As per the funding structure, the Government of India will contribute Rs 100 billion (Rs 10,000 crore), while the states of Gujarat and Maharashtra will each provide Rs 50 billion (Rs 5,000 crore). The balance will be funded by Japan through a soft loan at an interest rate of 0.1 per cent. 

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App