80 per cent Work Done on Mumbai Bullet Train’s BKC Station
RAILWAYS & METRO RAIL

80 per cent Work Done on Mumbai Bullet Train’s BKC Station

The National High-Speed Rail Corporation of India Limited (NHSRCL) announced significant progress on the Mumbai–Ahmedabad bullet train project, with 80 per cent of excavation completed at the Bandra Kurla Complex (BKC) station site in Mumbai.

The 21-kilometre-long underground and undersea tunnel connecting BKC to Shilphata in Thane district includes 16 kilometres being excavated using Tunnel Boring Machines and the remaining 5 kilometres via the New Austrian Tunnelling Method.

The NHSRCL, which is implementing the 508-kilometre Mumbai–Ahmedabad high-speed rail corridor, stated that base slab casting has already begun at both ends of the BKC station, which lies around 30 metres (100 feet) below ground level.

Base slab casting is also complete at Vikhroli (56 metres deep) and the Sawli shaft (39 metres deep), both critical for launching the tunnel boring machines and facilitating underground works.

Meanwhile, construction of elevated stations at Thane, Virar, and Boisar in Maharashtra is progressing rapidly, with approximately 44 kilometres of piers cast to date. In Palghar district, excavation of seven mountain tunnels is underway, alongside the construction of bridges across the Vaitarna, Ulhas, and Jagani rivers.

The total project cost is estimated at Rs 1.08 trillion (Rs 1.08 lakh crore). As per the funding structure, the Government of India will contribute Rs 100 billion (Rs 10,000 crore), while the states of Gujarat and Maharashtra will each provide Rs 50 billion (Rs 5,000 crore). The balance will be funded by Japan through a soft loan at an interest rate of 0.1 per cent. 

The National High-Speed Rail Corporation of India Limited (NHSRCL) announced significant progress on the Mumbai–Ahmedabad bullet train project, with 80 per cent of excavation completed at the Bandra Kurla Complex (BKC) station site in Mumbai.The 21-kilometre-long underground and undersea tunnel connecting BKC to Shilphata in Thane district includes 16 kilometres being excavated using Tunnel Boring Machines and the remaining 5 kilometres via the New Austrian Tunnelling Method.The NHSRCL, which is implementing the 508-kilometre Mumbai–Ahmedabad high-speed rail corridor, stated that base slab casting has already begun at both ends of the BKC station, which lies around 30 metres (100 feet) below ground level.Base slab casting is also complete at Vikhroli (56 metres deep) and the Sawli shaft (39 metres deep), both critical for launching the tunnel boring machines and facilitating underground works.Meanwhile, construction of elevated stations at Thane, Virar, and Boisar in Maharashtra is progressing rapidly, with approximately 44 kilometres of piers cast to date. In Palghar district, excavation of seven mountain tunnels is underway, alongside the construction of bridges across the Vaitarna, Ulhas, and Jagani rivers.The total project cost is estimated at Rs 1.08 trillion (Rs 1.08 lakh crore). As per the funding structure, the Government of India will contribute Rs 100 billion (Rs 10,000 crore), while the states of Gujarat and Maharashtra will each provide Rs 50 billion (Rs 5,000 crore). The balance will be funded by Japan through a soft loan at an interest rate of 0.1 per cent. 

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement