Projects in Railways, Roads, Power, Urban Development facing a lag
RAILWAYS & METRO RAIL

Projects in Railways, Roads, Power, Urban Development facing a lag

Of a total of 371 projects – each amounting to Rs 10 billion or more – delayed across four sectors, the railways takes the lead with 174 delayed projects, followed by road transport and highways at 127 projects; power at 56; and urban development at 14 projects. 

The September 2018 Flash Report clearly indicates these numbers with time and cost overruns compared to the original schedule. The report also analyses sectoral delays with projects amounting to Rs 1.50 billion and above. 

In case of the railways, the total original cost of implementation of 375 projects when sanctioned was Rs 4,783.59 billion but this subsequently increased to Rs 7,253.43 billion, implying a staggering cost overrun of 51.6 per cent.

The expenditure incurred on these projects till September 2018 is Rs 1,723.61 billion, which is 23.8 per cent of the anticipated project cost. Some major projects that faced delay and cost overruns included the Western Dedicated Freight Corridor. The project, worth Rs 165 billion, which commenced in 2007 is now facing an additional cost overrun of Rs 345 billion. The current project cost is around Rs 511 billion. Similarly, the Eastern Dedicated Freight Corridor Project, which was inaugurated with much fanfare in 2006, is facing an additional cost overrun of Rs 165 billion from its original cost of Rs 115.89 billion. The total cost of the project is Rs 281.81 billion.

Over the years, the power sector witnessed an overall cost overrun of 21.3 per cent to Rs 3,725.25 billion as against the original cost of Rs 3,072.23 billion for 105 projects. The expenditure incurred on these projects till September 2018 is Rs 2,345.28 billion, which is 63 per cent of the anticipated project cost. By far, the power sector has seen the maximum cost incurred on projects (percentage-wise) as against other sectors.

In the roads sector, out of 574 projects, two projects are ahead of schedule, 81 projects are on schedule and 90 projects are delayed. Surprisingly, 368 projects do not have fixed dates of commissioning and 33 projects were sanctioned without any commissioning date but subsequently dates of completion were finalised. The total original cost of implementation of 574 projects when sanctioned was around Rs 3,869.25 billion, but this was increased to Rs 4,011.59 billion implying a cost overrun of 3.7 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,326.43 billion, which is 33 per cent of the anticipated cost of the projects.

Urban development, too, was privy to project delays and cost overruns. The total original cost of implementation of 61 projects, when sanctioned, was Rs 1, 717.44 billion, but this was subsequently increased to Rs 1,794.53 billion, implying a cost overrun of 4.5 per cent. 

The expenditure incurred on these projects till September 2018 is Rs 736 billion, which is 41 per cent of the anticipated cost of the projects.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Of a total of 371 projects – each amounting to Rs 10 billion or more – delayed across four sectors, the railways takes the lead with 174 delayed projects, followed by road transport and highways at 127 projects; power at 56; and urban development at 14 projects.  The September 2018 Flash Report clearly indicates these numbers with time and cost overruns compared to the original schedule. The report also analyses sectoral delays with projects amounting to Rs 1.50 billion and above.  In case of the railways, the total original cost of implementation of 375 projects when sanctioned was Rs 4,783.59 billion but this subsequently increased to Rs 7,253.43 billion, implying a staggering cost overrun of 51.6 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,723.61 billion, which is 23.8 per cent of the anticipated project cost. Some major projects that faced delay and cost overruns included the Western Dedicated Freight Corridor. The project, worth Rs 165 billion, which commenced in 2007 is now facing an additional cost overrun of Rs 345 billion. The current project cost is around Rs 511 billion. Similarly, the Eastern Dedicated Freight Corridor Project, which was inaugurated with much fanfare in 2006, is facing an additional cost overrun of Rs 165 billion from its original cost of Rs 115.89 billion. The total cost of the project is Rs 281.81 billion. Over the years, the power sector witnessed an overall cost overrun of 21.3 per cent to Rs 3,725.25 billion as against the original cost of Rs 3,072.23 billion for 105 projects. The expenditure incurred on these projects till September 2018 is Rs 2,345.28 billion, which is 63 per cent of the anticipated project cost. By far, the power sector has seen the maximum cost incurred on projects (percentage-wise) as against other sectors. In the roads sector, out of 574 projects, two projects are ahead of schedule, 81 projects are on schedule and 90 projects are delayed. Surprisingly, 368 projects do not have fixed dates of commissioning and 33 projects were sanctioned without any commissioning date but subsequently dates of completion were finalised. The total original cost of implementation of 574 projects when sanctioned was around Rs 3,869.25 billion, but this was increased to Rs 4,011.59 billion implying a cost overrun of 3.7 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,326.43 billion, which is 33 per cent of the anticipated cost of the projects. Urban development, too, was privy to project delays and cost overruns. The total original cost of implementation of 61 projects, when sanctioned, was Rs 1, 717.44 billion, but this was subsequently increased to Rs 1,794.53 billion, implying a cost overrun of 4.5 per cent.  The expenditure incurred on these projects till September 2018 is Rs 736 billion, which is 41 per cent of the anticipated cost of the projects. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Next Story
Infrastructure Urban

DDA Approves Rs 87.2 Billion Budget for 2025-26

The Delhi Development Authority (DDA) has approved a budget of Rs 87.2 billion for the financial year 2025-26, with a strong emphasis on civic infrastructure development, green space rejuvenation, housing, and sports facilities, according to an official statement. Chaired by Lieutenant Governor V.K. Saxena, the budget meeting highlighted several large-scale projects, including the revitalisation of the Yamuna floodplain, creation of expansive parks, and upgraded civic amenities. Out of the total outlay, Rs 41.4 billion has been earmarked for capital expenditure, covering new roads, infrastruc..

Next Story
Infrastructure Energy

Vi Taps Cisco to Power Next-Gen Network

Telecom operator Vodafone Idea (Vi) has joined hands with US-based tech major Cisco Systems to revamp its transport network infrastructure across India. The strategic partnership aims to enhance network performance, scalability, and user experience for both retail and enterprise customers. As part of the agreement, Vi will deploy Cisco’s advanced Multiprotocol Label Switching (MPLS) technology to create a high-capacity, software-driven transport network. This will significantly improve the telecom player’s ability to manage surging data traffic and support data-heavy digital services such..

Next Story
Building Material

GPT Infra Commissions New Steel Girder Plant Near Kolkata

GPT Infraprojects announced the successful commissioning of its steel girder and components manufacturing facility in West Bengal on April 24, 2025. Located in Village Majinan, Hooghly district—about 60 km from Kolkata—the plant begins operations with an initial capacity of 10,000 metric tonnes per annum (MTPA). The company stated that the facility is in the process of securing RDSO (Research Designs and Standards Organisation) approval for manufacturing steel bridge girders. Once approved, this unit is expected to become a key asset for the company’s steel bridge segment, catering to c..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?