Projects in Railways, Roads, Power, Urban Development facing a lag
RAILWAYS & METRO RAIL

Projects in Railways, Roads, Power, Urban Development facing a lag

Of a total of 371 projects – each amounting to Rs 10 billion or more – delayed across four sectors, the railways takes the lead with 174 delayed projects, followed by road transport and highways at 127 projects; power at 56; and urban development at 14 projects. 

The September 2018 Flash Report clearly indicates these numbers with time and cost overruns compared to the original schedule. The report also analyses sectoral delays with projects amounting to Rs 1.50 billion and above. 

In case of the railways, the total original cost of implementation of 375 projects when sanctioned was Rs 4,783.59 billion but this subsequently increased to Rs 7,253.43 billion, implying a staggering cost overrun of 51.6 per cent.

The expenditure incurred on these projects till September 2018 is Rs 1,723.61 billion, which is 23.8 per cent of the anticipated project cost. Some major projects that faced delay and cost overruns included the Western Dedicated Freight Corridor. The project, worth Rs 165 billion, which commenced in 2007 is now facing an additional cost overrun of Rs 345 billion. The current project cost is around Rs 511 billion. Similarly, the Eastern Dedicated Freight Corridor Project, which was inaugurated with much fanfare in 2006, is facing an additional cost overrun of Rs 165 billion from its original cost of Rs 115.89 billion. The total cost of the project is Rs 281.81 billion.

Over the years, the power sector witnessed an overall cost overrun of 21.3 per cent to Rs 3,725.25 billion as against the original cost of Rs 3,072.23 billion for 105 projects. The expenditure incurred on these projects till September 2018 is Rs 2,345.28 billion, which is 63 per cent of the anticipated project cost. By far, the power sector has seen the maximum cost incurred on projects (percentage-wise) as against other sectors.

In the roads sector, out of 574 projects, two projects are ahead of schedule, 81 projects are on schedule and 90 projects are delayed. Surprisingly, 368 projects do not have fixed dates of commissioning and 33 projects were sanctioned without any commissioning date but subsequently dates of completion were finalised. The total original cost of implementation of 574 projects when sanctioned was around Rs 3,869.25 billion, but this was increased to Rs 4,011.59 billion implying a cost overrun of 3.7 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,326.43 billion, which is 33 per cent of the anticipated cost of the projects.

Urban development, too, was privy to project delays and cost overruns. The total original cost of implementation of 61 projects, when sanctioned, was Rs 1, 717.44 billion, but this was subsequently increased to Rs 1,794.53 billion, implying a cost overrun of 4.5 per cent. 

The expenditure incurred on these projects till September 2018 is Rs 736 billion, which is 41 per cent of the anticipated cost of the projects.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Of a total of 371 projects – each amounting to Rs 10 billion or more – delayed across four sectors, the railways takes the lead with 174 delayed projects, followed by road transport and highways at 127 projects; power at 56; and urban development at 14 projects.  The September 2018 Flash Report clearly indicates these numbers with time and cost overruns compared to the original schedule. The report also analyses sectoral delays with projects amounting to Rs 1.50 billion and above.  In case of the railways, the total original cost of implementation of 375 projects when sanctioned was Rs 4,783.59 billion but this subsequently increased to Rs 7,253.43 billion, implying a staggering cost overrun of 51.6 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,723.61 billion, which is 23.8 per cent of the anticipated project cost. Some major projects that faced delay and cost overruns included the Western Dedicated Freight Corridor. The project, worth Rs 165 billion, which commenced in 2007 is now facing an additional cost overrun of Rs 345 billion. The current project cost is around Rs 511 billion. Similarly, the Eastern Dedicated Freight Corridor Project, which was inaugurated with much fanfare in 2006, is facing an additional cost overrun of Rs 165 billion from its original cost of Rs 115.89 billion. The total cost of the project is Rs 281.81 billion. Over the years, the power sector witnessed an overall cost overrun of 21.3 per cent to Rs 3,725.25 billion as against the original cost of Rs 3,072.23 billion for 105 projects. The expenditure incurred on these projects till September 2018 is Rs 2,345.28 billion, which is 63 per cent of the anticipated project cost. By far, the power sector has seen the maximum cost incurred on projects (percentage-wise) as against other sectors. In the roads sector, out of 574 projects, two projects are ahead of schedule, 81 projects are on schedule and 90 projects are delayed. Surprisingly, 368 projects do not have fixed dates of commissioning and 33 projects were sanctioned without any commissioning date but subsequently dates of completion were finalised. The total original cost of implementation of 574 projects when sanctioned was around Rs 3,869.25 billion, but this was increased to Rs 4,011.59 billion implying a cost overrun of 3.7 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,326.43 billion, which is 33 per cent of the anticipated cost of the projects. Urban development, too, was privy to project delays and cost overruns. The total original cost of implementation of 61 projects, when sanctioned, was Rs 1, 717.44 billion, but this was subsequently increased to Rs 1,794.53 billion, implying a cost overrun of 4.5 per cent.  The expenditure incurred on these projects till September 2018 is Rs 736 billion, which is 41 per cent of the anticipated cost of the projects. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Next Story
Real Estate

Platinum Corp Launches Bespoke Presidential Suites

Platinum Corp has launched Platinum Stellar: Bespoke Presidential Suites, a luxury residential project on Main Avenue in Santacruz, Mumbai. The project has been positioned as a boutique, design-led development for high-net-worth individuals, business owners and legacy residents from the Bandra-Khar-Santacruz belt.The project has been developed in collaboration with celebrity interior designer Sussanne Khan and follows a design-first approach inspired by Art Deco architecture. It incorporates refined detailing, spacious layouts, premium material palettes and arrival experiences planned to creat..

Next Story
Infrastructure Transport

Adani Airport City Plans Rs 200 Bn Investment

Adani Airport City Limited (AACL), a wholly owned subsidiary of Adani Airport Holdings Limited (AAHL), has announced a programme to develop integrated airport cities across its airport network. The first phase will involve an investment of more than Rs 20,000 crore and cover around 22 million sq ft across Mumbai, Navi Mumbai, Ahmedabad, Lucknow, Jaipur and Guwahati.The development spans over 655 acres across six airports in five states. Nearly 440 acres are located in Mumbai and Navi Mumbai, which will receive close to 70 per cent of the planned investment. The focus reflects the Mumbai Metrop..

Next Story
Infrastructure Urban

Vedanta contributes Rs 627.22 billion to exchequer

Vedanta Limited contributed Rs 627.22 billion to the exchequer in FY26, according to its 11th Tax Transparency Report. The contribution accounted for 36 per cent of the company’s consolidated revenue from operations and reflected its focus on transparent governance, fiscal discipline and nation-building.The FY26 contribution marked a 13.3 per cent increase over the previous year. Vedanta’s cumulative contribution to the exchequer over the past decade reached Rs 4.83 trillion. The company said the Group ranks among India’s top three private-sector contributors to the national exchequer.Th..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement