Aizawl Gets Rail Link After 25 Years in the Making
RAILWAYS & METRO RAIL

Aizawl Gets Rail Link After 25 Years in the Making

Mizoram’s capital, Aizawl, has been formally connected to the Indian Railway network with the commissioning of the 51.38-kilometre Bairabi–Sairang railway line, marking a landmark moment in the state’s integration with national infrastructure. First conceptualised in 1999, the project has now materialised into a strategic corridor set to enhance transport and economic opportunities in the region.

During a recent meeting in New Delhi, Mizoram Chief Minister Lalduhoma received an assurance from Prime Minister Narendra Modi that he would inaugurate the Bairabi–Sairang rail line and Sairang railway station at the earliest opportunity, according to an official statement. The Chief Minister’s Office shared on X: “Chief Minister Shri @Lal_Duhoma met Hon'ble Prime Minister Shri @narendramodi in New Delhi today and discussed key development issues of Mizoram.”

The project faced numerous challenges due to the difficult hilly terrain and adverse weather conditions. It was officially commissioned in June 2025 by the Commissioner of Railway Safety. The first surveys were initiated in 2006 by the Northeast Frontier Railway, and detailed investigations were carried out by RITES in 2008, with the final report submitted in 2011. Recognising its strategic value, the UPA government declared the project a “National Project” in 2008–09, and Prime Minister Modi laid its foundation stone in November 2014.

Land acquisition was finalised by 2015, and full-scale construction commenced in the same year. The rail line is expected to reduce travel time between Guwahati and Aizawl from 18 hours by road to under 12 hours by train, with an estimated ticket fare of Rs 450. This development is poised to greatly benefit commuters, traders, students, and tourists through improved affordability and speed.

The project involved extraordinary engineering feats. According to Chief Engineer Vinod Kumar, the alignment crosses rugged terrain, deep valleys, and gorges. Frequent disruptions on the Guwahati–Silchar highway made transporting materials particularly difficult.

The Bairabi–Sairang section features:

  • 48 tunnels covering a total of 12.85 kilometres
  • 55 major and 87 minor bridges
  • 5 road overbridges and 9 underbridges
  • One exceptional bridge (No. 196) that stands 104 metres tall—42 metres higher than Delhi’s Qutub Minar

With its commissioning, Mizoram takes a significant leap in infrastructure connectivity with the rest of India. The line now awaits its formal inauguration by Prime Minister Modi. 

Mizoram’s capital, Aizawl, has been formally connected to the Indian Railway network with the commissioning of the 51.38-kilometre Bairabi–Sairang railway line, marking a landmark moment in the state’s integration with national infrastructure. First conceptualised in 1999, the project has now materialised into a strategic corridor set to enhance transport and economic opportunities in the region.During a recent meeting in New Delhi, Mizoram Chief Minister Lalduhoma received an assurance from Prime Minister Narendra Modi that he would inaugurate the Bairabi–Sairang rail line and Sairang railway station at the earliest opportunity, according to an official statement. The Chief Minister’s Office shared on X: “Chief Minister Shri @Lal_Duhoma met Hon'ble Prime Minister Shri @narendramodi in New Delhi today and discussed key development issues of Mizoram.”The project faced numerous challenges due to the difficult hilly terrain and adverse weather conditions. It was officially commissioned in June 2025 by the Commissioner of Railway Safety. The first surveys were initiated in 2006 by the Northeast Frontier Railway, and detailed investigations were carried out by RITES in 2008, with the final report submitted in 2011. Recognising its strategic value, the UPA government declared the project a “National Project” in 2008–09, and Prime Minister Modi laid its foundation stone in November 2014.Land acquisition was finalised by 2015, and full-scale construction commenced in the same year. The rail line is expected to reduce travel time between Guwahati and Aizawl from 18 hours by road to under 12 hours by train, with an estimated ticket fare of Rs 450. This development is poised to greatly benefit commuters, traders, students, and tourists through improved affordability and speed.The project involved extraordinary engineering feats. According to Chief Engineer Vinod Kumar, the alignment crosses rugged terrain, deep valleys, and gorges. Frequent disruptions on the Guwahati–Silchar highway made transporting materials particularly difficult.The Bairabi–Sairang section features:48 tunnels covering a total of 12.85 kilometres55 major and 87 minor bridges5 road overbridges and 9 underbridgesOne exceptional bridge (No. 196) that stands 104 metres tall—42 metres higher than Delhi’s Qutub MinarWith its commissioning, Mizoram takes a significant leap in infrastructure connectivity with the rest of India. The line now awaits its formal inauguration by Prime Minister Modi. 

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement