Chennai Metro Phase II Project Nears 40% Completion, Says Lok Sabha Reply
RAILWAYS & METRO RAIL

Chennai Metro Phase II Project Nears 40% Completion, Says Lok Sabha Reply

Nearly 40% of Chennai Metro Rail’s Phase II project has been completed, as revealed in a reply in the Lok Sabha. The Phase II project, spanning 118.9 km and costing Rs 63,246 crore, is designed to provide faster commuting options across the city. It consists of three corridors: Madhavaram to SIPCOT (Corridor 3), Light House to Poonamallee (Corridor 4), and Madhavaram to Sholinganallur (Corridor 5).

Minister of State for Housing and Urban Affairs, Tokhan Sahu, informed the Lok Sabha that Chennai Metro Rail Limited (CMRL), the Special Purpose Vehicle (SPV) for the project, reported physical progress at 40.41% and financial progress at 32.74%. The project will have 128 stations with both elevated and underground sections across the three corridors. The first stretch available for passenger services will be the 9 km elevated section from Poonamallee to Porur on Corridor 4. While the elevated sections are progressing well, only 19 km of the 50.5 km underground tunnelling has been completed.

The Poonamallee to Porur stretch is expected to be operational by December 2025, with work progressing on stations and tracks. An extension from Porur to Kodambakkam is also planned for a few months later.

Nearly 40% of Chennai Metro Rail’s Phase II project has been completed, as revealed in a reply in the Lok Sabha. The Phase II project, spanning 118.9 km and costing Rs 63,246 crore, is designed to provide faster commuting options across the city. It consists of three corridors: Madhavaram to SIPCOT (Corridor 3), Light House to Poonamallee (Corridor 4), and Madhavaram to Sholinganallur (Corridor 5).Minister of State for Housing and Urban Affairs, Tokhan Sahu, informed the Lok Sabha that Chennai Metro Rail Limited (CMRL), the Special Purpose Vehicle (SPV) for the project, reported physical progress at 40.41% and financial progress at 32.74%. The project will have 128 stations with both elevated and underground sections across the three corridors. The first stretch available for passenger services will be the 9 km elevated section from Poonamallee to Porur on Corridor 4. While the elevated sections are progressing well, only 19 km of the 50.5 km underground tunnelling has been completed.The Poonamallee to Porur stretch is expected to be operational by December 2025, with work progressing on stations and tracks. An extension from Porur to Kodambakkam is also planned for a few months later.

Next Story
Real Estate

Shriram Properties Launches ‘Codename: The One’ in Bengaluru

Shriram Properties (SPL), a leading real estate developer focused on the mid-market and mid-premium segments, has announced the launch of its latest residential project under the banner “Codename: The One” in Bengaluru’s Electronic City corridor. This feature-rich gated community will offer 340 spacious 2- and 3-BHK residences, with a total saleable area of approximately 5 lakh square feet and an estimated revenue potential of over Rs 3.5 billion. The project is expected to be developed over a span of more than three years.  Strategically located near the Bommasandra Metro stat..

Next Story
Resources

India Warehousing Show 2025 Closes with Strong Global Presence

The 14th edition of the India Warehousing Show (IWS) 2025 concluded successfully at Yashobhoomi (IICC), Dwarka, drawing participation from over 300 exhibitors across 15 countries and welcoming 15,000+ visitors. Recognised as India’s leading platform for warehousing and logistics excellence, IWS 2025 offered a comprehensive display of cutting-edge automation, sustainable warehousing solutions, and next-gen supply chain technologies. The show was inaugurated by Shri Pankaj Kumar, Joint Secretary – Logistics, DPIIT, Ministry of Commerce and Industry, Government of India. In his opening a..

Next Story
Equipment

MHIET Launches 450kW Gas Cogeneration System with H₂ Co-Firing

Mitsubishi Heavy Industries Engine & Turbocharger (MHIET), part of the Mitsubishi Heavy Industries Group, has launched a new 450kW gas cogeneration system, the SGP M450, jointly developed with Toho Gas Co.,. The system supports hydrogen co-firing at up to 15 vol per cent, with no loss in performance or reliability.  The system is currently available in the Japanese market, and has been developed from the existing GS6R2 city gas engine platform. Key modifications were made to the fuel gas and engine control systems to enable hydrogen co-firing.   Verified through de..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?