Chennai Metro: TBM Adyar Breaks Through
RAILWAYS & METRO RAIL

Chennai Metro: TBM Adyar Breaks Through

Larsen & Toubro’s (L&T) tunnel boring machine (TBM) Adyar (S-1326A) has achieved its first breakthrough at Adyar Junction for Package TU-02 on Chennai Metro Phase 2’s Line 3. This milestone marks the fourth breakthrough in the 12 km tunnel stretch between Kellys and Taramani Road Junction stations.

The 116.1 km Phase 2 project aims to improve connectivity across Chennai, with Line 3 spanning 45.8 km and 49 stations—20 elevated and 29 underground.

A Key Milestone for Chennai Metro TBM Adyar, a 100m-long Herrenknecht earth pressure balance (EPB) machine, began its assignment at Greenways Road Station in April 2023. Over 22 months, it navigated complex geological conditions, including constructing a 300m tunnel under the Adyar River, before breaking through at Adyar Junction.

L&T has deployed eight TBMs for twin tunnel construction under Package TU-02, which involves building 24 km of tunnels.

Project Background & Scope L&T secured Package TU-02 from Chennai Metro Rail Ltd. (CMRL) in May 2021 for Rs. 23.85 billion ($286 million), with a 42-month deadline. The contract covers:

Twin tunnel construction between Kellys and Taramani Road Junction Diaphragm walls and entry/exit structures for Chetpet, Royapettah Government Hospital, and Thiruvanmiyur stations Partial diaphragm wall construction at Greenways Road Station Chennai Metro’s Progress on Line 3 With TBM Adyar’s breakthrough, 10 tunnel breakthroughs have been completed on Line 3. Other notable breakthroughs include:

Siruvani (DZ1040) – Sterling Road (703m) – August 2024 Kaveri (S-1327A) – Adyar Junction (1,228m) – September 2024 Palar (DZ1041) – Sterling Road (700m) – October 2024

Pushing Forward As Chennai Metro Phase 2 progresses, each breakthrough brings the city closer to a seamless urban transit system. A CMRL official noted, “These milestones reflect the dedication of our teams in overcoming challenging tunneling conditions to enhance Chennai’s metro connectivity.”

With more breakthroughs expected in the coming months, Chennai Metro continues to shape the city's urban transport landscape.

Larsen & Toubro’s (L&T) tunnel boring machine (TBM) Adyar (S-1326A) has achieved its first breakthrough at Adyar Junction for Package TU-02 on Chennai Metro Phase 2’s Line 3. This milestone marks the fourth breakthrough in the 12 km tunnel stretch between Kellys and Taramani Road Junction stations. The 116.1 km Phase 2 project aims to improve connectivity across Chennai, with Line 3 spanning 45.8 km and 49 stations—20 elevated and 29 underground. A Key Milestone for Chennai Metro TBM Adyar, a 100m-long Herrenknecht earth pressure balance (EPB) machine, began its assignment at Greenways Road Station in April 2023. Over 22 months, it navigated complex geological conditions, including constructing a 300m tunnel under the Adyar River, before breaking through at Adyar Junction. L&T has deployed eight TBMs for twin tunnel construction under Package TU-02, which involves building 24 km of tunnels. Project Background & Scope L&T secured Package TU-02 from Chennai Metro Rail Ltd. (CMRL) in May 2021 for Rs. 23.85 billion ($286 million), with a 42-month deadline. The contract covers: Twin tunnel construction between Kellys and Taramani Road Junction Diaphragm walls and entry/exit structures for Chetpet, Royapettah Government Hospital, and Thiruvanmiyur stations Partial diaphragm wall construction at Greenways Road Station Chennai Metro’s Progress on Line 3 With TBM Adyar’s breakthrough, 10 tunnel breakthroughs have been completed on Line 3. Other notable breakthroughs include: Siruvani (DZ1040) – Sterling Road (703m) – August 2024 Kaveri (S-1327A) – Adyar Junction (1,228m) – September 2024 Palar (DZ1041) – Sterling Road (700m) – October 2024 Pushing Forward As Chennai Metro Phase 2 progresses, each breakthrough brings the city closer to a seamless urban transit system. A CMRL official noted, “These milestones reflect the dedication of our teams in overcoming challenging tunneling conditions to enhance Chennai’s metro connectivity.” With more breakthroughs expected in the coming months, Chennai Metro continues to shape the city's urban transport landscape.

Next Story
Infrastructure Urban

Titan Intech Strengthens UltraLED Push With Global LED Veteran

Titan Intech has announced the induction of global LED industry veteran Su Piow Ko to its Board of Directors, marking a strategic step in strengthening its UltraLED Displays roadmap and building globally competitive LED display solutions from India.The appointment aligns with Titan Intech’s ambition to position India as a hub for advanced, high-quality LED display manufacturing. With an increased focus on UltraLED Displays, the company aims to enhance technical governance, raise manufacturing standards and expand its presence across global markets.Su Piow Ko brings over three decades of inte..

Next Story
Infrastructure Urban

Dun & Bradstreet Flags New Growth Engines in India 2026 Outlook

Dun & Bradstreet has released its India 2026: D&B’s Perspective report, projecting a stable macroeconomic environment underpinned by fresh opportunities for productivity-led and inclusive growth. The report outlines how India’s next growth phase will be driven by digitised logistics, trusted data ecosystems, clean energy and rising city vitality.According to the outlook, India’s GDP growth is expected to reach around 6.6 per cent by FY2027, supported by resilient consumer demand and sustained public investment. Manufacturing is seen entering a new phase, moving beyond scale towar..

Next Story
Building Material

Sources Unlimited Introduces Vitamine Pendant Lamp by Melogranoblu

Sources Unlimited has launched the Vitamine Pendant Lamp by Melogranoblu in India, expanding its portfolio of curated international luxury lighting solutions. Designed and crafted in Italy, the Vitamine pendant reflects contemporary glass artistry, combining hand-blown craftsmanship with refined aesthetics and atmospheric illumination.The Vitamine Pendant Lamp is sculpted in hand-blown glass and is available in frosted, silver and black metallised finishes. Each finish offers a distinct visual identity while maintaining a cohesive and sophisticated design language. The lamp’s softly contoure..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App