Chennai Metro: TBM Adyar Breaks Through
RAILWAYS & METRO RAIL

Chennai Metro: TBM Adyar Breaks Through

Larsen & Toubro’s (L&T) tunnel boring machine (TBM) Adyar (S-1326A) has achieved its first breakthrough at Adyar Junction for Package TU-02 on Chennai Metro Phase 2’s Line 3. This milestone marks the fourth breakthrough in the 12 km tunnel stretch between Kellys and Taramani Road Junction stations.

The 116.1 km Phase 2 project aims to improve connectivity across Chennai, with Line 3 spanning 45.8 km and 49 stations—20 elevated and 29 underground.

A Key Milestone for Chennai Metro TBM Adyar, a 100m-long Herrenknecht earth pressure balance (EPB) machine, began its assignment at Greenways Road Station in April 2023. Over 22 months, it navigated complex geological conditions, including constructing a 300m tunnel under the Adyar River, before breaking through at Adyar Junction.

L&T has deployed eight TBMs for twin tunnel construction under Package TU-02, which involves building 24 km of tunnels.

Project Background & Scope L&T secured Package TU-02 from Chennai Metro Rail Ltd. (CMRL) in May 2021 for Rs. 23.85 billion ($286 million), with a 42-month deadline. The contract covers:

Twin tunnel construction between Kellys and Taramani Road Junction Diaphragm walls and entry/exit structures for Chetpet, Royapettah Government Hospital, and Thiruvanmiyur stations Partial diaphragm wall construction at Greenways Road Station Chennai Metro’s Progress on Line 3 With TBM Adyar’s breakthrough, 10 tunnel breakthroughs have been completed on Line 3. Other notable breakthroughs include:

Siruvani (DZ1040) – Sterling Road (703m) – August 2024 Kaveri (S-1327A) – Adyar Junction (1,228m) – September 2024 Palar (DZ1041) – Sterling Road (700m) – October 2024

Pushing Forward As Chennai Metro Phase 2 progresses, each breakthrough brings the city closer to a seamless urban transit system. A CMRL official noted, “These milestones reflect the dedication of our teams in overcoming challenging tunneling conditions to enhance Chennai’s metro connectivity.”

With more breakthroughs expected in the coming months, Chennai Metro continues to shape the city's urban transport landscape.

Larsen & Toubro’s (L&T) tunnel boring machine (TBM) Adyar (S-1326A) has achieved its first breakthrough at Adyar Junction for Package TU-02 on Chennai Metro Phase 2’s Line 3. This milestone marks the fourth breakthrough in the 12 km tunnel stretch between Kellys and Taramani Road Junction stations. The 116.1 km Phase 2 project aims to improve connectivity across Chennai, with Line 3 spanning 45.8 km and 49 stations—20 elevated and 29 underground. A Key Milestone for Chennai Metro TBM Adyar, a 100m-long Herrenknecht earth pressure balance (EPB) machine, began its assignment at Greenways Road Station in April 2023. Over 22 months, it navigated complex geological conditions, including constructing a 300m tunnel under the Adyar River, before breaking through at Adyar Junction. L&T has deployed eight TBMs for twin tunnel construction under Package TU-02, which involves building 24 km of tunnels. Project Background & Scope L&T secured Package TU-02 from Chennai Metro Rail Ltd. (CMRL) in May 2021 for Rs. 23.85 billion ($286 million), with a 42-month deadline. The contract covers: Twin tunnel construction between Kellys and Taramani Road Junction Diaphragm walls and entry/exit structures for Chetpet, Royapettah Government Hospital, and Thiruvanmiyur stations Partial diaphragm wall construction at Greenways Road Station Chennai Metro’s Progress on Line 3 With TBM Adyar’s breakthrough, 10 tunnel breakthroughs have been completed on Line 3. Other notable breakthroughs include: Siruvani (DZ1040) – Sterling Road (703m) – August 2024 Kaveri (S-1327A) – Adyar Junction (1,228m) – September 2024 Palar (DZ1041) – Sterling Road (700m) – October 2024 Pushing Forward As Chennai Metro Phase 2 progresses, each breakthrough brings the city closer to a seamless urban transit system. A CMRL official noted, “These milestones reflect the dedication of our teams in overcoming challenging tunneling conditions to enhance Chennai’s metro connectivity.” With more breakthroughs expected in the coming months, Chennai Metro continues to shape the city's urban transport landscape.

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?