Construction of diaphragm wall for underground airport tunnel begins
RAILWAYS & METRO RAIL

Construction of diaphragm wall for underground airport tunnel begins

As part of Package ANVS-RVNL-1682, Afcons Infrastructure started building the diaphragm wall (D-wall) for the underground airport tunnel of Kolkata Metro Line 6 (Orange Line). The Airport Station will be the northern terminal of Kolkata Metro's 29.87-kilometer Line-6, which connects Kavi Subhash New Garia to Biman Bandar. It will also be a stop on the 6.87-kilometer Line-4 (Noapara – Airport). Line 4 will be extended to New Barrackpore in the north.

The station box, which includes four lines and a facility for train stabling, is currently being constructed by ITD Cementation. The Airports Authority of India's land will be traversed by an underground cut-and-cover tunnel that will be constructed by Afcons and measure approximately 950 meters in length.

The Rs were given to Afcons in January 2021. Package ANVS-RVNL-1682 is a civil construction contract worth 532.65 crore that must be finished in 36 months. The Sub CBD-2 Station and Biman Bandar will be connected by this civil package of 3.519 kilometers, most of which will be elevated. Under this, underground sections and a viaduct will be built, two new stations will be built at Chinar Park (formerly Rabindra Tirtha) and VIP Road (Haldiram).

As part of Package ANVS-RVNL-1682, Afcons Infrastructure started building the diaphragm wall (D-wall) for the underground airport tunnel of Kolkata Metro Line 6 (Orange Line). The Airport Station will be the northern terminal of Kolkata Metro's 29.87-kilometer Line-6, which connects Kavi Subhash New Garia to Biman Bandar. It will also be a stop on the 6.87-kilometer Line-4 (Noapara – Airport). Line 4 will be extended to New Barrackpore in the north. The station box, which includes four lines and a facility for train stabling, is currently being constructed by ITD Cementation. The Airports Authority of India's land will be traversed by an underground cut-and-cover tunnel that will be constructed by Afcons and measure approximately 950 meters in length. The Rs were given to Afcons in January 2021. Package ANVS-RVNL-1682 is a civil construction contract worth 532.65 crore that must be finished in 36 months. The Sub CBD-2 Station and Biman Bandar will be connected by this civil package of 3.519 kilometers, most of which will be elevated. Under this, underground sections and a viaduct will be built, two new stations will be built at Chinar Park (formerly Rabindra Tirtha) and VIP Road (Haldiram).

Next Story
Real Estate

Loomcraft Enters South India with Kerala Store Launch

Loomcraft has launched its exclusive store in Kerala, marking its entry into South India and a key step in its nationwide expansion strategy. The move targets a region driven by tourism and premium real estate demand, where outdoor spaces play a central role in hospitality and residential experiences.Kerala’s growing base of luxury resorts, boutique hotels, villas and gated communities has created strong demand for specialised outdoor furniture. However, the region has remained underserved, with buyers relying on imports or generic products not suited to humid, coastal and monsoon-heavy cond..

Next Story
Building Material

Mild Steel Prices Seen Rising to Rs 61,000 Per Tonne

Mild steel prices in India, currently around Rs 58,000 per tonne, are expected to rise to nearly Rs 61,000 per tonne in April, indicating an increase of about Rs 3,000 per tonne. The anticipated rise reflects structural pressures driven by geopolitical tensions, energy constraints and limited raw material availability.Ongoing global conflict has disrupted energy markets, leading to LNG shortages that are affecting domestic steel production. Small and mid-sized manufacturers, particularly those dependent on gas-based processes, are witnessing production cuts due to constrained energy supply, re..

Next Story
Infrastructure Urban

Vedanta Expands Transgender Workforce to 75 Employees

Vedanta has strengthened its commitment to workplace inclusion by employing 75 transgender individuals across its businesses, including Vedanta Aluminium, Hindustan Zinc, Sesa Goa, FACOR and Cairn Oil & Gas. The initiative reflects sustained hiring efforts since 2022 to build equitable opportunities across operations, corporate and technical roles.Transgender employees are engaged in functions such as operations, finance, logistics, HR, CSR, healthcare and security, with provisions for internal mobility to support career progression. The company has implemented structured policies, includi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement