Mumbai Metro 7A Viaduct Error May Require Rs 2.5bn Rebuild
RAILWAYS & METRO RAIL

Mumbai Metro 7A Viaduct Error May Require Rs 2.5bn Rebuild

An engineering planning error on the Mumbai Metro Line 7A could require demolition and reconstruction of almost one kilometre of an elevated viaduct in Vile Parle East after the height of overhead electric wires exceeded the clearance permitted by the Airports Authority of India in the airport funnel zone. The mismatch, of about two point five metres, has halted work on the stretch despite most civil construction being complete. The authority estimated that if no technical remedy is found, work valued at Rs two point five billion (bn) may have to be redone, adding to delays.

The short extension was originally scheduled to open in 2021 and has missed several deadlines, and officials indicated it is unlikely to open in the financial year 2026-27. The project is a three point four-kilometre extension of Metro Line 7 from Andheri East to Chhatrapati Shivaji Maharaj International Airport and will connect with the underground Metro Line 3 to provide a direct link for commuters. The elevated section affected includes the Airport Colony station, viaduct and ramp.

MMRDA officials said the problem relates to the additional height required for the overhead electric equipment to operate the metro, which was not factored into the original design when no-objection certificates were issued in 2022. Construction on the Vile Parle East stretch advanced after permissions were granted, and the issue was flagged in 2025, prompting a pause and requests for revised clearance from the Airports Authority of India. The civil consultant consortium of Systra, CEG and SMCIPL holds differing positions, with the consultant denying responsibility and the authority yet to permit the extra height.

MMRDA data showed that by February 2026 the entire elevated viaduct was complete and 95 per cent of the elevated ramp had been constructed, with the Airport Colony station substantially finished. The alignment comprises approximately two point five kilometres of underground track and 940 metres of elevated alignment. A questionnaire sent to the Mumbai Metropolitan Region Development Authority on August 19 elicited no response.

An engineering planning error on the Mumbai Metro Line 7A could require demolition and reconstruction of almost one kilometre of an elevated viaduct in Vile Parle East after the height of overhead electric wires exceeded the clearance permitted by the Airports Authority of India in the airport funnel zone. The mismatch, of about two point five metres, has halted work on the stretch despite most civil construction being complete. The authority estimated that if no technical remedy is found, work valued at Rs two point five billion (bn) may have to be redone, adding to delays. The short extension was originally scheduled to open in 2021 and has missed several deadlines, and officials indicated it is unlikely to open in the financial year 2026-27. The project is a three point four-kilometre extension of Metro Line 7 from Andheri East to Chhatrapati Shivaji Maharaj International Airport and will connect with the underground Metro Line 3 to provide a direct link for commuters. The elevated section affected includes the Airport Colony station, viaduct and ramp. MMRDA officials said the problem relates to the additional height required for the overhead electric equipment to operate the metro, which was not factored into the original design when no-objection certificates were issued in 2022. Construction on the Vile Parle East stretch advanced after permissions were granted, and the issue was flagged in 2025, prompting a pause and requests for revised clearance from the Airports Authority of India. The civil consultant consortium of Systra, CEG and SMCIPL holds differing positions, with the consultant denying responsibility and the authority yet to permit the extra height. MMRDA data showed that by February 2026 the entire elevated viaduct was complete and 95 per cent of the elevated ramp had been constructed, with the Airport Colony station substantially finished. The alignment comprises approximately two point five kilometres of underground track and 940 metres of elevated alignment. A questionnaire sent to the Mumbai Metropolitan Region Development Authority on August 19 elicited no response.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code