Mumbai Metro 7A Viaduct Error May Require Rs 2.5bn Rebuild
RAILWAYS & METRO RAIL

Mumbai Metro 7A Viaduct Error May Require Rs 2.5bn Rebuild

An engineering planning error on the Mumbai Metro Line 7A could require demolition and reconstruction of almost one kilometre of an elevated viaduct in Vile Parle East after the height of overhead electric wires exceeded the clearance permitted by the Airports Authority of India in the airport funnel zone. The mismatch, of about two point five metres, has halted work on the stretch despite most civil construction being complete. The authority estimated that if no technical remedy is found, work valued at Rs two point five billion (bn) may have to be redone, adding to delays.

The short extension was originally scheduled to open in 2021 and has missed several deadlines, and officials indicated it is unlikely to open in the financial year 2026-27. The project is a three point four-kilometre extension of Metro Line 7 from Andheri East to Chhatrapati Shivaji Maharaj International Airport and will connect with the underground Metro Line 3 to provide a direct link for commuters. The elevated section affected includes the Airport Colony station, viaduct and ramp.

MMRDA officials said the problem relates to the additional height required for the overhead electric equipment to operate the metro, which was not factored into the original design when no-objection certificates were issued in 2022. Construction on the Vile Parle East stretch advanced after permissions were granted, and the issue was flagged in 2025, prompting a pause and requests for revised clearance from the Airports Authority of India. The civil consultant consortium of Systra, CEG and SMCIPL holds differing positions, with the consultant denying responsibility and the authority yet to permit the extra height.

MMRDA data showed that by February 2026 the entire elevated viaduct was complete and 95 per cent of the elevated ramp had been constructed, with the Airport Colony station substantially finished. The alignment comprises approximately two point five kilometres of underground track and 940 metres of elevated alignment. A questionnaire sent to the Mumbai Metropolitan Region Development Authority on August 19 elicited no response.

An engineering planning error on the Mumbai Metro Line 7A could require demolition and reconstruction of almost one kilometre of an elevated viaduct in Vile Parle East after the height of overhead electric wires exceeded the clearance permitted by the Airports Authority of India in the airport funnel zone. The mismatch, of about two point five metres, has halted work on the stretch despite most civil construction being complete. The authority estimated that if no technical remedy is found, work valued at Rs two point five billion (bn) may have to be redone, adding to delays. The short extension was originally scheduled to open in 2021 and has missed several deadlines, and officials indicated it is unlikely to open in the financial year 2026-27. The project is a three point four-kilometre extension of Metro Line 7 from Andheri East to Chhatrapati Shivaji Maharaj International Airport and will connect with the underground Metro Line 3 to provide a direct link for commuters. The elevated section affected includes the Airport Colony station, viaduct and ramp. MMRDA officials said the problem relates to the additional height required for the overhead electric equipment to operate the metro, which was not factored into the original design when no-objection certificates were issued in 2022. Construction on the Vile Parle East stretch advanced after permissions were granted, and the issue was flagged in 2025, prompting a pause and requests for revised clearance from the Airports Authority of India. The civil consultant consortium of Systra, CEG and SMCIPL holds differing positions, with the consultant denying responsibility and the authority yet to permit the extra height. MMRDA data showed that by February 2026 the entire elevated viaduct was complete and 95 per cent of the elevated ramp had been constructed, with the Airport Colony station substantially finished. The alignment comprises approximately two point five kilometres of underground track and 940 metres of elevated alignment. A questionnaire sent to the Mumbai Metropolitan Region Development Authority on August 19 elicited no response.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

MMRDA Targets Completion of Projects by December 2028

The Mumbai Metropolitan Region Development Authority (MMRDA) is targeting the completion of all its ongoing infrastructure projects by December 2028, a year ahead of its December 2029 deadline, Metropolitan Commissioner Dr Sanjay Mukherjee has said.Speaking at the sixth edition of the Real Estate & Infrastructure Investors' Summit (REIIS) 2026 in Mumbai, Mukherjee said the authority was developing an integrated network of roads, tunnels, sea links and Metro corridors under its broader vision of “Mumbai in 59 Minutes”.The objective is to improve east-west and north-south connectivity an..

Next Story
Building Material

High-Performance Façades Gain Ground in Indian Buildings

High-performance façades are gaining greater importance in Indian architecture as developers and architects increasingly focus on energy efficiency, thermal comfort and building performance, according to Shankar Fenestrations & Glasses.The company said modern façade systems are increasingly being considered as part of a building's overall performance strategy rather than being used primarily as aesthetic elements.High-performance glass, curtain wall systems and structural glazing can contribute to thermal regulation, solar control, daylight management and indoor comfort. Their growing ad..

Next Story
Technology

SPML Infra's 104.4 kWh BESS Battery Pack Clears Global Tests

SPML Infra has announced that its proprietary 104.4 kWh Battery Energy Storage System (BESS) battery pack has completed key international safety, performance and transportation testing and certification requirements, marking a step towards its commercial deployment.Developed under the company's own intellectual property, the battery pack has completed requirements under UL9540A, IEC 62619, IEC 63056, IEC 60730, IEC 61000-6-2, IEC 61000-6-4 and UN38.3 standards.The testing covers areas including thermal runaway safety, battery performance, system functional safety, electromagnetic compatibility..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code