Driverless metro train reaches Chennai for Namma Metro
RAILWAYS & METRO RAIL

Driverless metro train reaches Chennai for Namma Metro

After a prolonged delay, the inaugural train from China destined for Namma Metro's Yellow Line (RV Road-Bommsandra) finally arrived at Chennai port.

The driverless train prototype, featuring communication-based train control (CBTC), is anticipated to reach the Hebbagodi depot near Electronics City by February 18.

BMRCL's Chief Public Relations Officer, BL Yeshwanth Chavan, informed TOI, stating, "Typically, customs clearance takes 3-4 days, following which the coaches will be transported to Bengaluru. At the depot, assembly will take place, followed by a series of tests before the train undergoes dynamic testing on the tracks."

"As this is a new train, we need to conduct 14 comprehensive tests for the main lines. Subsequently, signaling tests will be carried out. A total of 37 tests must be completed before seeking approval from the Commissioner of Metro Railway Safety. Compliance with rules mandates technical approvals from Research Designs and Standards Organisations (RDSO), Chief Commissioner of Railway Safety, and the Railway Board at different stages," Chavan explained.

He emphasised that the entire testing process, involving technical experts from China Railway Rolling Stock Corporation (CRRC), will take a minimum of 4-5 months. Authorisation from CMRS will follow after the completion of these tests. Additionally, CRRC has delivered two train car body shells to its local manufacturing partner, Titagarh Rail System Limited, with the expectation of delivering these two trains in May.

After a prolonged delay, the inaugural train from China destined for Namma Metro's Yellow Line (RV Road-Bommsandra) finally arrived at Chennai port. The driverless train prototype, featuring communication-based train control (CBTC), is anticipated to reach the Hebbagodi depot near Electronics City by February 18. BMRCL's Chief Public Relations Officer, BL Yeshwanth Chavan, informed TOI, stating, Typically, customs clearance takes 3-4 days, following which the coaches will be transported to Bengaluru. At the depot, assembly will take place, followed by a series of tests before the train undergoes dynamic testing on the tracks. As this is a new train, we need to conduct 14 comprehensive tests for the main lines. Subsequently, signaling tests will be carried out. A total of 37 tests must be completed before seeking approval from the Commissioner of Metro Railway Safety. Compliance with rules mandates technical approvals from Research Designs and Standards Organisations (RDSO), Chief Commissioner of Railway Safety, and the Railway Board at different stages, Chavan explained. He emphasised that the entire testing process, involving technical experts from China Railway Rolling Stock Corporation (CRRC), will take a minimum of 4-5 months. Authorisation from CMRS will follow after the completion of these tests. Additionally, CRRC has delivered two train car body shells to its local manufacturing partner, Titagarh Rail System Limited, with the expectation of delivering these two trains in May.

Next Story
Infrastructure Urban

India Expands Semiconductor Training To 500 Institutions

Under the Chips to Startups programme of the India Semiconductor Mission, the Union minister responsible for Railways, Information and Broadcasting, and Electronics and IT reported notable progress in talent development. He indicated that over the past four years substantial steps have been taken towards a 10-year target of training 85,000 engineers in semiconductor design. World-class EDA tools have been deployed in 315 academic institutions across the country to provide students with practical exposure to chip design. These EDA tools are supported by leading global firms and are accessible t..

Next Story
Infrastructure Urban

Delhi Institutions Support India Semiconductor Mission

The Government of India has prioritised talent development through training, upskilling and workforce development under the Chips to Startups initiative of the India Semiconductor Mission, with officials noting progress in four years towards a 10-year target of training 85,000 engineers in semiconductor design. Electronic design automation tools provided by Synopsys, Cadence, Siemens, Renesas, Ansys and AMD have been deployed in 315 academic institutions, enabling students to gain practical chip design experience. Chips have been fabricated and tested at the Semiconductor Laboratory, Mohali, a..

Next Story
Infrastructure Urban

NHA Announces Winners Of NHCX Hackathon At IIT Hyderabad

The National Health Authority (NHA) has concluded the NHCX Hackathon under the Ayushman Bharat Digital Mission (ABDM) to stimulate innovation around the National Health Claims Exchange (NHCX). The winning teams presented their solutions at the NHCX Innovation Meet held at IIT Hyderabad during a two-day event in March 2026 that also served as the hackathon grand finale. The hackathon itself ran from 22 to 28 February 2026 and aimed to accelerate paperless, transparent claims processing across India. The event was organised with a range of ecosystem partners, including the Insurance Regulatory a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement