Driverless metro train reaches Chennai for Namma Metro
RAILWAYS & METRO RAIL

Driverless metro train reaches Chennai for Namma Metro

After a prolonged delay, the inaugural train from China destined for Namma Metro's Yellow Line (RV Road-Bommsandra) finally arrived at Chennai port.

The driverless train prototype, featuring communication-based train control (CBTC), is anticipated to reach the Hebbagodi depot near Electronics City by February 18.

BMRCL's Chief Public Relations Officer, BL Yeshwanth Chavan, informed TOI, stating, "Typically, customs clearance takes 3-4 days, following which the coaches will be transported to Bengaluru. At the depot, assembly will take place, followed by a series of tests before the train undergoes dynamic testing on the tracks."

"As this is a new train, we need to conduct 14 comprehensive tests for the main lines. Subsequently, signaling tests will be carried out. A total of 37 tests must be completed before seeking approval from the Commissioner of Metro Railway Safety. Compliance with rules mandates technical approvals from Research Designs and Standards Organisations (RDSO), Chief Commissioner of Railway Safety, and the Railway Board at different stages," Chavan explained.

He emphasised that the entire testing process, involving technical experts from China Railway Rolling Stock Corporation (CRRC), will take a minimum of 4-5 months. Authorisation from CMRS will follow after the completion of these tests. Additionally, CRRC has delivered two train car body shells to its local manufacturing partner, Titagarh Rail System Limited, with the expectation of delivering these two trains in May.

After a prolonged delay, the inaugural train from China destined for Namma Metro's Yellow Line (RV Road-Bommsandra) finally arrived at Chennai port. The driverless train prototype, featuring communication-based train control (CBTC), is anticipated to reach the Hebbagodi depot near Electronics City by February 18. BMRCL's Chief Public Relations Officer, BL Yeshwanth Chavan, informed TOI, stating, Typically, customs clearance takes 3-4 days, following which the coaches will be transported to Bengaluru. At the depot, assembly will take place, followed by a series of tests before the train undergoes dynamic testing on the tracks. As this is a new train, we need to conduct 14 comprehensive tests for the main lines. Subsequently, signaling tests will be carried out. A total of 37 tests must be completed before seeking approval from the Commissioner of Metro Railway Safety. Compliance with rules mandates technical approvals from Research Designs and Standards Organisations (RDSO), Chief Commissioner of Railway Safety, and the Railway Board at different stages, Chavan explained. He emphasised that the entire testing process, involving technical experts from China Railway Rolling Stock Corporation (CRRC), will take a minimum of 4-5 months. Authorisation from CMRS will follow after the completion of these tests. Additionally, CRRC has delivered two train car body shells to its local manufacturing partner, Titagarh Rail System Limited, with the expectation of delivering these two trains in May.

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement