Expansion of Virar Dahanu railway to begin
RAILWAYS & METRO RAIL

Expansion of Virar Dahanu railway to begin

The Mumbai Railway Vikas Corporation's (MRVC) plans to increase railway line capacity between Virar and Dahanu on the western line have not yet taken off, despite receiving Stage 1 (in principle) forest clearance (FC) in February 2022 since the Bombay High Court is yet to grant permission for the project to clear approximately 24.5 hectares of mangroves in Palghar district. In the matter, a writ petition is still pending before the HC.

However, the ministry of environment, forests, and climate change's regional empowered committee (REC) has permitted MRVC to begin work on two hectares of the railway line outside of the protected mangrove patches while recommending Stage II clearance, the final level of FC required for any project. Officials claim that the HC's pending permission is all that stands in the way of the construction of the project, which is scheduled to be finished by 2025, now that the Maharashtra Coastal Zone Management Authority has granted the project CRZ clearance in November 2022.

The third and fourth railway lines will be laid parallel to the existing double line corridor for approximately 63 km between Virar and Dahanu as part of Phase III of the Mumbai Urban Transport Project. According to official records, the project will result in the removal of 25,438 trees, including 24,302 mangroves. Compensatory forestation has been proposed for 54 hectares of degraded land in three Palghar villages nearby to make up for the loss. Within one year of receiving Stage II clearance, a total of 200 trees will be transplanted from the two or three hectares of land outside the mangrove area, where work will be done without the HC's approval.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Mumbai Railway Vikas Corporation's (MRVC) plans to increase railway line capacity between Virar and Dahanu on the western line have not yet taken off, despite receiving Stage 1 (in principle) forest clearance (FC) in February 2022 since the Bombay High Court is yet to grant permission for the project to clear approximately 24.5 hectares of mangroves in Palghar district. In the matter, a writ petition is still pending before the HC. However, the ministry of environment, forests, and climate change's regional empowered committee (REC) has permitted MRVC to begin work on two hectares of the railway line outside of the protected mangrove patches while recommending Stage II clearance, the final level of FC required for any project. Officials claim that the HC's pending permission is all that stands in the way of the construction of the project, which is scheduled to be finished by 2025, now that the Maharashtra Coastal Zone Management Authority has granted the project CRZ clearance in November 2022. The third and fourth railway lines will be laid parallel to the existing double line corridor for approximately 63 km between Virar and Dahanu as part of Phase III of the Mumbai Urban Transport Project. According to official records, the project will result in the removal of 25,438 trees, including 24,302 mangroves. Compensatory forestation has been proposed for 54 hectares of degraded land in three Palghar villages nearby to make up for the loss. Within one year of receiving Stage II clearance, a total of 200 trees will be transplanted from the two or three hectares of land outside the mangrove area, where work will be done without the HC's approval.

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement