Govt wraps up 281 central infrastructure projects in FY24
RAILWAYS & METRO RAIL

Govt wraps up 281 central infrastructure projects in FY24

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade.

The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost.

By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years.

The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March.

The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported.

A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively.

Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns.

Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade. The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost. By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years. The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March. The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported. A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively. Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns. Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement