Govt wraps up 281 central infrastructure projects in FY24
RAILWAYS & METRO RAIL

Govt wraps up 281 central infrastructure projects in FY24

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade.

The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost.

By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years.

The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March.

The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported.

A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively.

Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns.

Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade. The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost. By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years. The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March. The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported. A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively. Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns. Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?