Govt wraps up 281 central infrastructure projects in FY24
RAILWAYS & METRO RAIL

Govt wraps up 281 central infrastructure projects in FY24

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade.

The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost.

By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years.

The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March.

The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported.

A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively.

Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns.

Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade. The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost. By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years. The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March. The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported. A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively. Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns. Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

Next Story
Infrastructure Urban

Hindware Opens Rs 1.7 Billion Plastics Plant In Roorkee

Hindware has inaugurated its third manufacturing facility at Roorkee, Uttarakhand, to produce a broad range of CPVC, UPVC, SWR and PVC pipes and fittings, as well as overhead water storage tanks under the Truflo brand. Built with an investment of about Rs 1.7 billion, the plant opens with an annual capacity of 12,500 tonnes, taking the company’s total capacity—including its existing Sangareddy site—to 80,500 tonnes. Strategically located to serve northern and western India, the new unit is expected to sharpen Truflo’s distribution efficiency while creating roughly 200 direct an..

Next Story
Infrastructure Energy

Hartek Wins Rs 1.38 Billion Substation Deal from POWERGRID

Engineering, procurement, and construction (EPC) firm Hartek Group has secured a contract worth Rs 1.38 billion from state-owned POWERGRID for the development of a 400 kilovolt (kV) substation in Karnataka.In a statement issued on Wednesday, the company said the project will be delivered under the Tariff-Based Competitive Bidding (TBCB) route and will involve the design, engineering, procurement, construction, and commissioning of an Air Insulated Switchgear (AIS) substation.The comprehensive scope includes testing at the manufacturer’s works, supply, unloading, storage, erection, and commis..

Next Story
Infrastructure Energy

SJVN Signs Power Supply Deals for 1.5 GW Green Projects

State-run SJVN Ltd has signed multiple power purchase agreements to supply over 1,492 MW of renewable energy from its hydroelectric projects in Nepal and Himachal Pradesh, marking a major step in India’s clean energy transition.The company signed a Power Sale Agreement (PSA) with Uttar Pradesh Power Corporation Ltd (UPPCL) for the supply of electricity from its 900 MW Arun-III Hydro Electric Project in Nepal. The cross-border project is being developed in Sankhuwasabha district by SJVN’s wholly owned subsidiary, SJVN Arun-3 Power Development Company (SAPDC), and is expected to be commi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?