Govt wraps up 281 central infrastructure projects in FY24
RAILWAYS & METRO RAIL

Govt wraps up 281 central infrastructure projects in FY24

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade.

The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost.

By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years.

The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March.

The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported.

A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively.

Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns.

Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

According to government data released, in FY24, work on 281 central government projects costing over Rs 1.50 billion was completed, compared to 329 projects completed in the previous year. It was noted that this completion rate was the second-highest in nearly a decade. The data also revealed that the proportion of delayed projects increased to 41.6% in March from 41.2% in the previous month. Similarly, the ratio of cost overruns rose to 18.65% compared to 18.19% in the previous month. This increase was attributed to the anticipated cost of 1,873 projects amounting to Rs 31.9 trillion, which was Rs 5 trillion higher than the original cost. By the end of March, 779 projects were delayed, with 51% of them being delayed for over two years, averaging 36.04 months or nearly three years. The government release indicated that three projects (two road projects and one telecom project) were added, while 32 projects (seven roads, 23 in petroleum, and two in the power sector) were completed in March. The release also pointed out a concerning observation that many project agencies were not reporting revised cost estimates and commissioning schedules for numerous projects, hinting that time/cost overrun figures might be underreported. A sectoral analysis revealed that Railways and water resources had the highest cost overruns, with the anticipated costs of all projects monitored by the ministry exceeding the original cost by 54% and 197%, respectively. Of the 249 projects monitored under Railways, 149 were facing cost overruns, while the ratio was 9 out of 41 for water resources. Additionally, nearly a fifth of road projects, which constituted the highest number of ongoing projects, were experiencing cost overruns. Concerning time overruns, 109 out of 249 railway projects and nearly 40% of road projects were delayed.

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?