HCC completes first tunnel for Mumbai Metro-III project
RAILWAYS & METRO RAIL

HCC completes first tunnel for Mumbai Metro-III project

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. 

As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. 

MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.

Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.

As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. 

The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India’s first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India’s infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central–Gandhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India’s busiest business corridors. This upgrade, effective from 11 May, raised the train’s seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai–Ahmedabad–Gandhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi’s ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river’s health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?