In its phase 2, Chennai Metro Rail to remove 6 stations
In its phase 2, Chennai Metro Rail to remove 6 stations
RAILWAYS & METRO RAIL

In its phase 2, Chennai Metro Rail to remove 6 stations

Six metro stations that were less than 750 metres from the next stop each were eliminated from phase two of the metro rail system. This move is projected to save over Rs 12 billion. The stations were intended to be elevated at St. Joseph's College and underground at Doveton Junction, Foreshore Estate, Natesan Park, Meenakshi College, and Thapal Village. By 2026, the 118.9 km phase-2, which will include 128 stations, including 48 subterranean ones, and cost an estimated Rs 618.43 billion, should be finished.

For simple access and emergency evacuation, metro stations are typically planned every 1 kilometre. Reasons for discarding stations include short distances and steep turns. According to L Girirajan, a spokeswoman for Chennai Metro Rail Ltd (CMRL), while the proposed station at Thapal Petti in Madhavaram would have featured a severe curve that could have been difficult to maintain, it was removed because it was so close to the nearest stations. Thapal Petti and Meenakshi College being eliminated will result at a savings of almost Rs 4.50 billion, he claimed.

The projects proposed at Foreshore Estate, Natesan Park, and Meenakshi College are on the 26.1-km Lighthouse-Poonamallee Bypass corridor-4, while those at Thapal Petti, Doveton, and St. Joseph's College are on the 45.8-km Madhavaram Milk Colony-Siruseri Sipcot corridor-3. The stations at Madhavaram Milk Colony and Murari Hospital are 980 and 684 metres, respectively, from the one at Thapal Petti, whilst the stations at Meenakshi College are 725 and 1,040 metres, respectively, from Kodambakkam and Power House. On the OMR, Semmencheri is 805m away and Sathyabhama University is 827m away from St. Joseph's College station.

Beside a school on Venkatanarayana Road, the Natesan Park station in T Nagar is about 632 metres from Panagal Park metro and 625 metres from Nandanam metro. Lighthouse station at Marina Beach is located 786 metres away from Foreshore Estate station, which is located 958 metres away from Kutchery Road, the following station.

Six metro stations that were less than 750 metres from the next stop each were eliminated from phase two of the metro rail system. This move is projected to save over Rs 12 billion. The stations were intended to be elevated at St. Joseph's College and underground at Doveton Junction, Foreshore Estate, Natesan Park, Meenakshi College, and Thapal Village. By 2026, the 118.9 km phase-2, which will include 128 stations, including 48 subterranean ones, and cost an estimated Rs 618.43 billion, should be finished. For simple access and emergency evacuation, metro stations are typically planned every 1 kilometre. Reasons for discarding stations include short distances and steep turns. According to L Girirajan, a spokeswoman for Chennai Metro Rail Ltd (CMRL), while the proposed station at Thapal Petti in Madhavaram would have featured a severe curve that could have been difficult to maintain, it was removed because it was so close to the nearest stations. Thapal Petti and Meenakshi College being eliminated will result at a savings of almost Rs 4.50 billion, he claimed. The projects proposed at Foreshore Estate, Natesan Park, and Meenakshi College are on the 26.1-km Lighthouse-Poonamallee Bypass corridor-4, while those at Thapal Petti, Doveton, and St. Joseph's College are on the 45.8-km Madhavaram Milk Colony-Siruseri Sipcot corridor-3. The stations at Madhavaram Milk Colony and Murari Hospital are 980 and 684 metres, respectively, from the one at Thapal Petti, whilst the stations at Meenakshi College are 725 and 1,040 metres, respectively, from Kodambakkam and Power House. On the OMR, Semmencheri is 805m away and Sathyabhama University is 827m away from St. Joseph's College station. Beside a school on Venkatanarayana Road, the Natesan Park station in T Nagar is about 632 metres from Panagal Park metro and 625 metres from Nandanam metro. Lighthouse station at Marina Beach is located 786 metres away from Foreshore Estate station, which is located 958 metres away from Kutchery Road, the following station.

Next Story
Infrastructure Urban

Global Rare Earth Supply Chains Diversify Away from China

In response to the rising global demand for rare earths critical for producing everything from electric vehicles to wind turbines, supply chains are undergoing a significant realignment away from China. Historically dominant in rare earth production, China's recent policies and geopolitical tensions have prompted Western nations and other stakeholders to seek alternative sources and bolster local capabilities. Rare earth processing involves two essential stages: initial extraction and subsequent refining into individual oxide compounds used to manufacture magnets essential in various industri..

Next Story
Infrastructure Urban

Coal India, US Firm to Explore Argentine Lithium

State-run Coal India Ltd is collaborating with a US company to explore lithium blocks in Argentina, a critical step in securing supplies of the essential battery material, according to an Indian source with direct knowledge of the matter. This initiative is part of India's participation in the US-led Minerals Security Partnership (MSP), which New Delhi joined last year to ensure a steady supply of minerals necessary to meet its zero-carbon objectives. As part of the MSP, India was invited to engage in 20-25 critical minerals projects, with four already identified by the Indian government. Indi..

Next Story
Infrastructure Energy

India's Coal Consumption Set to Surge Amid Hydroelectricity Shortfall

Amid a significant drop in hydroelectricity production caused by inadequate rainfall, India is gearing up to increase its coal consumption to satisfy rising power demands, according to S&P Global Commodity Insights. This shortfall in hydroelectric power is anticipated to perpetuate India's reliance on coal imports. During the fiscal year 2023-24, India's coal production approached the 1 billion metric ton milestone, reflecting the government's strategy to lessen dependency on imported coal. Nonetheless, the country has already imported approximately 85 million metric tons of thermal coal in 20..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000

Join us Telegram