In its phase 2, Chennai Metro Rail to remove 6 stations
RAILWAYS & METRO RAIL

In its phase 2, Chennai Metro Rail to remove 6 stations

Six metro stations that were less than 750 metres from the next stop each were eliminated from phase two of the metro rail system. This move is projected to save over Rs 12 billion. The stations were intended to be elevated at St. Joseph's College and underground at Doveton Junction, Foreshore Estate, Natesan Park, Meenakshi College, and Thapal Village. By 2026, the 118.9 km phase-2, which will include 128 stations, including 48 subterranean ones, and cost an estimated Rs 618.43 billion, should be finished.

For simple access and emergency evacuation, metro stations are typically planned every 1 kilometre. Reasons for discarding stations include short distances and steep turns. According to L Girirajan, a spokeswoman for Chennai Metro Rail Ltd (CMRL), while the proposed station at Thapal Petti in Madhavaram would have featured a severe curve that could have been difficult to maintain, it was removed because it was so close to the nearest stations. Thapal Petti and Meenakshi College being eliminated will result at a savings of almost Rs 4.50 billion, he claimed.

The projects proposed at Foreshore Estate, Natesan Park, and Meenakshi College are on the 26.1-km Lighthouse-Poonamallee Bypass corridor-4, while those at Thapal Petti, Doveton, and St. Joseph's College are on the 45.8-km Madhavaram Milk Colony-Siruseri Sipcot corridor-3. The stations at Madhavaram Milk Colony and Murari Hospital are 980 and 684 metres, respectively, from the one at Thapal Petti, whilst the stations at Meenakshi College are 725 and 1,040 metres, respectively, from Kodambakkam and Power House. On the OMR, Semmencheri is 805m away and Sathyabhama University is 827m away from St. Joseph's College station.

Beside a school on Venkatanarayana Road, the Natesan Park station in T Nagar is about 632 metres from Panagal Park metro and 625 metres from Nandanam metro. Lighthouse station at Marina Beach is located 786 metres away from Foreshore Estate station, which is located 958 metres away from Kutchery Road, the following station.

Six metro stations that were less than 750 metres from the next stop each were eliminated from phase two of the metro rail system. This move is projected to save over Rs 12 billion. The stations were intended to be elevated at St. Joseph's College and underground at Doveton Junction, Foreshore Estate, Natesan Park, Meenakshi College, and Thapal Village. By 2026, the 118.9 km phase-2, which will include 128 stations, including 48 subterranean ones, and cost an estimated Rs 618.43 billion, should be finished. For simple access and emergency evacuation, metro stations are typically planned every 1 kilometre. Reasons for discarding stations include short distances and steep turns. According to L Girirajan, a spokeswoman for Chennai Metro Rail Ltd (CMRL), while the proposed station at Thapal Petti in Madhavaram would have featured a severe curve that could have been difficult to maintain, it was removed because it was so close to the nearest stations. Thapal Petti and Meenakshi College being eliminated will result at a savings of almost Rs 4.50 billion, he claimed. The projects proposed at Foreshore Estate, Natesan Park, and Meenakshi College are on the 26.1-km Lighthouse-Poonamallee Bypass corridor-4, while those at Thapal Petti, Doveton, and St. Joseph's College are on the 45.8-km Madhavaram Milk Colony-Siruseri Sipcot corridor-3. The stations at Madhavaram Milk Colony and Murari Hospital are 980 and 684 metres, respectively, from the one at Thapal Petti, whilst the stations at Meenakshi College are 725 and 1,040 metres, respectively, from Kodambakkam and Power House. On the OMR, Semmencheri is 805m away and Sathyabhama University is 827m away from St. Joseph's College station. Beside a school on Venkatanarayana Road, the Natesan Park station in T Nagar is about 632 metres from Panagal Park metro and 625 metres from Nandanam metro. Lighthouse station at Marina Beach is located 786 metres away from Foreshore Estate station, which is located 958 metres away from Kutchery Road, the following station.

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?