In its phase 2, Chennai Metro Rail to remove 6 stations
RAILWAYS & METRO RAIL

In its phase 2, Chennai Metro Rail to remove 6 stations

Six metro stations that were less than 750 metres from the next stop each were eliminated from phase two of the metro rail system. This move is projected to save over Rs 12 billion. The stations were intended to be elevated at St. Joseph's College and underground at Doveton Junction, Foreshore Estate, Natesan Park, Meenakshi College, and Thapal Village. By 2026, the 118.9 km phase-2, which will include 128 stations, including 48 subterranean ones, and cost an estimated Rs 618.43 billion, should be finished.

For simple access and emergency evacuation, metro stations are typically planned every 1 kilometre. Reasons for discarding stations include short distances and steep turns. According to L Girirajan, a spokeswoman for Chennai Metro Rail Ltd (CMRL), while the proposed station at Thapal Petti in Madhavaram would have featured a severe curve that could have been difficult to maintain, it was removed because it was so close to the nearest stations. Thapal Petti and Meenakshi College being eliminated will result at a savings of almost Rs 4.50 billion, he claimed.

The projects proposed at Foreshore Estate, Natesan Park, and Meenakshi College are on the 26.1-km Lighthouse-Poonamallee Bypass corridor-4, while those at Thapal Petti, Doveton, and St. Joseph's College are on the 45.8-km Madhavaram Milk Colony-Siruseri Sipcot corridor-3. The stations at Madhavaram Milk Colony and Murari Hospital are 980 and 684 metres, respectively, from the one at Thapal Petti, whilst the stations at Meenakshi College are 725 and 1,040 metres, respectively, from Kodambakkam and Power House. On the OMR, Semmencheri is 805m away and Sathyabhama University is 827m away from St. Joseph's College station.

Beside a school on Venkatanarayana Road, the Natesan Park station in T Nagar is about 632 metres from Panagal Park metro and 625 metres from Nandanam metro. Lighthouse station at Marina Beach is located 786 metres away from Foreshore Estate station, which is located 958 metres away from Kutchery Road, the following station.

Six metro stations that were less than 750 metres from the next stop each were eliminated from phase two of the metro rail system. This move is projected to save over Rs 12 billion. The stations were intended to be elevated at St. Joseph's College and underground at Doveton Junction, Foreshore Estate, Natesan Park, Meenakshi College, and Thapal Village. By 2026, the 118.9 km phase-2, which will include 128 stations, including 48 subterranean ones, and cost an estimated Rs 618.43 billion, should be finished. For simple access and emergency evacuation, metro stations are typically planned every 1 kilometre. Reasons for discarding stations include short distances and steep turns. According to L Girirajan, a spokeswoman for Chennai Metro Rail Ltd (CMRL), while the proposed station at Thapal Petti in Madhavaram would have featured a severe curve that could have been difficult to maintain, it was removed because it was so close to the nearest stations. Thapal Petti and Meenakshi College being eliminated will result at a savings of almost Rs 4.50 billion, he claimed. The projects proposed at Foreshore Estate, Natesan Park, and Meenakshi College are on the 26.1-km Lighthouse-Poonamallee Bypass corridor-4, while those at Thapal Petti, Doveton, and St. Joseph's College are on the 45.8-km Madhavaram Milk Colony-Siruseri Sipcot corridor-3. The stations at Madhavaram Milk Colony and Murari Hospital are 980 and 684 metres, respectively, from the one at Thapal Petti, whilst the stations at Meenakshi College are 725 and 1,040 metres, respectively, from Kodambakkam and Power House. On the OMR, Semmencheri is 805m away and Sathyabhama University is 827m away from St. Joseph's College station. Beside a school on Venkatanarayana Road, the Natesan Park station in T Nagar is about 632 metres from Panagal Park metro and 625 metres from Nandanam metro. Lighthouse station at Marina Beach is located 786 metres away from Foreshore Estate station, which is located 958 metres away from Kutchery Road, the following station.

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement