+
India, Japan Review Progress Of Mumbai–Ahmedabad Bullet Train
RAILWAYS & METRO RAIL

India, Japan Review Progress Of Mumbai–Ahmedabad Bullet Train

Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology Ashwini Vaishnaw, along with Japan’s Minister of Land, Infrastructure, Transport and Tourism H.E. Hiromasa Nakano, inspected the Mumbai–Ahmedabad High-Speed Rail (HSR) construction sites in Surat and Mumbai today.
Minister Nakano was welcomed at Surat International Airport with a traditional Garba performance. The reception was attended by Surat MP Mukesh Dalal, Mayor Daxesh Mavani, the Chairman of the Railway Board, senior officials of Indian Railways, NHSRCL, and the district administration.
Visit to Track Slab Laying Site, Surat
The ministers visited the track construction base at the Surat High-Speed Rail site, where they observed the installation of the J-slab ballast-less track system on the viaduct. The track slab installation and permanent rail laying are progressing swiftly. Earlier, Shri Vaishnaw had witnessed the first track turnout installation near the Surat HSR station, marking a key milestone in the project’s execution.
Visit to BKC HSR Station, Mumbai
The ministers travelled from Surat to Mumbai aboard the Vande Bharat Express and reviewed the progress at the Bandra Kurla Complex (BKC) underground bullet train station — a major terminal on the Mumbai–Ahmedabad HSR corridor. Minister Nakano and the Japanese delegation praised the quality and performance of the Vande Bharat trains.
BKC Station Highlights
The BKC bullet train station will be an underground facility featuring three levels — platform, concourse, and service floor. Excavation has reached a depth of over 30 metres, equivalent to a 10-storey building, with approximately 84 per cent of work completed. Designed for passenger convenience, the station will offer road and metro connectivity, with two access points—one near the metro station and another near the MTNL building. Spacious interiors, modern amenities, and skylights for natural lighting will ensure a comfortable passenger experience.
Project Progress (As of September 2025)
The Mumbai–Ahmedabad Bullet Train corridor, spanning 508 kilometres, continues to make rapid progress. Of this, 323 kilometres of viaduct and 399 kilometres of pier work have been completed. Significant milestones include 17 river bridges, 5 PSC bridges, and 9 steel bridges now completed.
A total of 211 kilometres of track bed has been laid, and over 400,000 noise barriers have been installed along the corridor. Excavation is advancing for seven mountain tunnels in Palghar, while 5 kilometres of the 21-kilometre NATM tunnel between BKC and Shilphata has achieved breakthrough. Construction of rolling stock depots at Surat and Ahmedabad is underway, with superstructure works on all Gujarat stations nearing completion. Additionally, work has commenced on all three elevated stations in Maharashtra.
The visit of Minister Nakano underscores the strong partnership between India and Japan in delivering India’s first high-speed rail corridor, a flagship infrastructure project symbolising technological collaboration and shared progress.

Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology Ashwini Vaishnaw, along with Japan’s Minister of Land, Infrastructure, Transport and Tourism H.E. Hiromasa Nakano, inspected the Mumbai–Ahmedabad High-Speed Rail (HSR) construction sites in Surat and Mumbai today.Minister Nakano was welcomed at Surat International Airport with a traditional Garba performance. The reception was attended by Surat MP Mukesh Dalal, Mayor Daxesh Mavani, the Chairman of the Railway Board, senior officials of Indian Railways, NHSRCL, and the district administration.Visit to Track Slab Laying Site, SuratThe ministers visited the track construction base at the Surat High-Speed Rail site, where they observed the installation of the J-slab ballast-less track system on the viaduct. The track slab installation and permanent rail laying are progressing swiftly. Earlier, Shri Vaishnaw had witnessed the first track turnout installation near the Surat HSR station, marking a key milestone in the project’s execution.Visit to BKC HSR Station, MumbaiThe ministers travelled from Surat to Mumbai aboard the Vande Bharat Express and reviewed the progress at the Bandra Kurla Complex (BKC) underground bullet train station — a major terminal on the Mumbai–Ahmedabad HSR corridor. Minister Nakano and the Japanese delegation praised the quality and performance of the Vande Bharat trains.BKC Station HighlightsThe BKC bullet train station will be an underground facility featuring three levels — platform, concourse, and service floor. Excavation has reached a depth of over 30 metres, equivalent to a 10-storey building, with approximately 84 per cent of work completed. Designed for passenger convenience, the station will offer road and metro connectivity, with two access points—one near the metro station and another near the MTNL building. Spacious interiors, modern amenities, and skylights for natural lighting will ensure a comfortable passenger experience.Project Progress (As of September 2025)The Mumbai–Ahmedabad Bullet Train corridor, spanning 508 kilometres, continues to make rapid progress. Of this, 323 kilometres of viaduct and 399 kilometres of pier work have been completed. Significant milestones include 17 river bridges, 5 PSC bridges, and 9 steel bridges now completed.A total of 211 kilometres of track bed has been laid, and over 400,000 noise barriers have been installed along the corridor. Excavation is advancing for seven mountain tunnels in Palghar, while 5 kilometres of the 21-kilometre NATM tunnel between BKC and Shilphata has achieved breakthrough. Construction of rolling stock depots at Surat and Ahmedabad is underway, with superstructure works on all Gujarat stations nearing completion. Additionally, work has commenced on all three elevated stations in Maharashtra.The visit of Minister Nakano underscores the strong partnership between India and Japan in delivering India’s first high-speed rail corridor, a flagship infrastructure project symbolising technological collaboration and shared progress.

Related Stories

Gold Stories

Next Story
Real Estate

Peninsula Land launches 19 luxury villas in Pune

Pune’s residential landscape is witnessing a shift as premium homebuyers increasingly seek larger spaces, privacy and independent living options beyond high-rise apartments. Addressing this demand, Peninsula Land Limited, part of the Ashok Piramal Group, has launched AshokVillas, an exclusive collection of 19 premium furnished villas in Gahunje, Pune.The development combines the independence of a standalone home with the convenience and security of a managed residential community. Designed around low-density horizontal living, AshokVillas offers residents private spaces while providing acces..

Next Story
Infrastructure Urban

MyBranch Expands South India Network with 16 Workspace Centres

MyBranch has expanded its South India presence with a 50,000 sq ft flexible workspace network comprising 16 centres across 14 cities in Andhra Pradesh, Karnataka, Tamil Nadu and Telangana.The expansion reflects growing demand for flexible office infrastructure as businesses establish regional teams, satellite offices and operations beyond traditional metropolitan markets. MyBranch’s network spans Bengaluru, Coimbatore, Guntur, Hanamkonda, Hubballi, Hyderabad, Madurai, Mangaluru, Rajahmundry, Salem, Tirupati, Vellore, Vijayawada and Visakhapatnam, with a large office space in Chennai also und..

Next Story
Building Material

Walplast Launches Moisture-Resistant Gypsum Plaster Solutions

Walplast Products Pvt. Ltd. has expanded its HomeSure GypEx portfolio with the launch of GypEx MoistShield and GypEx Gold, two gypsum plaster solutions designed to address moisture-prone applications and improve plastering efficiency.The new products have been developed in response to the growing demand for faster construction processes, improved material performance and consistent surface quality. The solutions aim to simplify interior plastering while addressing specific application requirements across construction environments.“Through HomeSure GypEx MoistShield and GypEx Gold, we are exp..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code