India, Japan Review Progress Of Mumbai–Ahmedabad Bullet Train
RAILWAYS & METRO RAIL

India, Japan Review Progress Of Mumbai–Ahmedabad Bullet Train

Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology Ashwini Vaishnaw, along with Japan’s Minister of Land, Infrastructure, Transport and Tourism H.E. Hiromasa Nakano, inspected the Mumbai–Ahmedabad High-Speed Rail (HSR) construction sites in Surat and Mumbai today.
Minister Nakano was welcomed at Surat International Airport with a traditional Garba performance. The reception was attended by Surat MP Mukesh Dalal, Mayor Daxesh Mavani, the Chairman of the Railway Board, senior officials of Indian Railways, NHSRCL, and the district administration.
Visit to Track Slab Laying Site, Surat
The ministers visited the track construction base at the Surat High-Speed Rail site, where they observed the installation of the J-slab ballast-less track system on the viaduct. The track slab installation and permanent rail laying are progressing swiftly. Earlier, Shri Vaishnaw had witnessed the first track turnout installation near the Surat HSR station, marking a key milestone in the project’s execution.
Visit to BKC HSR Station, Mumbai
The ministers travelled from Surat to Mumbai aboard the Vande Bharat Express and reviewed the progress at the Bandra Kurla Complex (BKC) underground bullet train station — a major terminal on the Mumbai–Ahmedabad HSR corridor. Minister Nakano and the Japanese delegation praised the quality and performance of the Vande Bharat trains.
BKC Station Highlights
The BKC bullet train station will be an underground facility featuring three levels — platform, concourse, and service floor. Excavation has reached a depth of over 30 metres, equivalent to a 10-storey building, with approximately 84 per cent of work completed. Designed for passenger convenience, the station will offer road and metro connectivity, with two access points—one near the metro station and another near the MTNL building. Spacious interiors, modern amenities, and skylights for natural lighting will ensure a comfortable passenger experience.
Project Progress (As of September 2025)
The Mumbai–Ahmedabad Bullet Train corridor, spanning 508 kilometres, continues to make rapid progress. Of this, 323 kilometres of viaduct and 399 kilometres of pier work have been completed. Significant milestones include 17 river bridges, 5 PSC bridges, and 9 steel bridges now completed.
A total of 211 kilometres of track bed has been laid, and over 400,000 noise barriers have been installed along the corridor. Excavation is advancing for seven mountain tunnels in Palghar, while 5 kilometres of the 21-kilometre NATM tunnel between BKC and Shilphata has achieved breakthrough. Construction of rolling stock depots at Surat and Ahmedabad is underway, with superstructure works on all Gujarat stations nearing completion. Additionally, work has commenced on all three elevated stations in Maharashtra.
The visit of Minister Nakano underscores the strong partnership between India and Japan in delivering India’s first high-speed rail corridor, a flagship infrastructure project symbolising technological collaboration and shared progress.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology Ashwini Vaishnaw, along with Japan’s Minister of Land, Infrastructure, Transport and Tourism H.E. Hiromasa Nakano, inspected the Mumbai–Ahmedabad High-Speed Rail (HSR) construction sites in Surat and Mumbai today.Minister Nakano was welcomed at Surat International Airport with a traditional Garba performance. The reception was attended by Surat MP Mukesh Dalal, Mayor Daxesh Mavani, the Chairman of the Railway Board, senior officials of Indian Railways, NHSRCL, and the district administration.Visit to Track Slab Laying Site, SuratThe ministers visited the track construction base at the Surat High-Speed Rail site, where they observed the installation of the J-slab ballast-less track system on the viaduct. The track slab installation and permanent rail laying are progressing swiftly. Earlier, Shri Vaishnaw had witnessed the first track turnout installation near the Surat HSR station, marking a key milestone in the project’s execution.Visit to BKC HSR Station, MumbaiThe ministers travelled from Surat to Mumbai aboard the Vande Bharat Express and reviewed the progress at the Bandra Kurla Complex (BKC) underground bullet train station — a major terminal on the Mumbai–Ahmedabad HSR corridor. Minister Nakano and the Japanese delegation praised the quality and performance of the Vande Bharat trains.BKC Station HighlightsThe BKC bullet train station will be an underground facility featuring three levels — platform, concourse, and service floor. Excavation has reached a depth of over 30 metres, equivalent to a 10-storey building, with approximately 84 per cent of work completed. Designed for passenger convenience, the station will offer road and metro connectivity, with two access points—one near the metro station and another near the MTNL building. Spacious interiors, modern amenities, and skylights for natural lighting will ensure a comfortable passenger experience.Project Progress (As of September 2025)The Mumbai–Ahmedabad Bullet Train corridor, spanning 508 kilometres, continues to make rapid progress. Of this, 323 kilometres of viaduct and 399 kilometres of pier work have been completed. Significant milestones include 17 river bridges, 5 PSC bridges, and 9 steel bridges now completed.A total of 211 kilometres of track bed has been laid, and over 400,000 noise barriers have been installed along the corridor. Excavation is advancing for seven mountain tunnels in Palghar, while 5 kilometres of the 21-kilometre NATM tunnel between BKC and Shilphata has achieved breakthrough. Construction of rolling stock depots at Surat and Ahmedabad is underway, with superstructure works on all Gujarat stations nearing completion. Additionally, work has commenced on all three elevated stations in Maharashtra.The visit of Minister Nakano underscores the strong partnership between India and Japan in delivering India’s first high-speed rail corridor, a flagship infrastructure project symbolising technological collaboration and shared progress.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement