India, Japan Review Progress Of Mumbai–Ahmedabad Bullet Train
RAILWAYS & METRO RAIL

India, Japan Review Progress Of Mumbai–Ahmedabad Bullet Train

Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology Ashwini Vaishnaw, along with Japan’s Minister of Land, Infrastructure, Transport and Tourism H.E. Hiromasa Nakano, inspected the Mumbai–Ahmedabad High-Speed Rail (HSR) construction sites in Surat and Mumbai today.
Minister Nakano was welcomed at Surat International Airport with a traditional Garba performance. The reception was attended by Surat MP Mukesh Dalal, Mayor Daxesh Mavani, the Chairman of the Railway Board, senior officials of Indian Railways, NHSRCL, and the district administration.
Visit to Track Slab Laying Site, Surat
The ministers visited the track construction base at the Surat High-Speed Rail site, where they observed the installation of the J-slab ballast-less track system on the viaduct. The track slab installation and permanent rail laying are progressing swiftly. Earlier, Shri Vaishnaw had witnessed the first track turnout installation near the Surat HSR station, marking a key milestone in the project’s execution.
Visit to BKC HSR Station, Mumbai
The ministers travelled from Surat to Mumbai aboard the Vande Bharat Express and reviewed the progress at the Bandra Kurla Complex (BKC) underground bullet train station — a major terminal on the Mumbai–Ahmedabad HSR corridor. Minister Nakano and the Japanese delegation praised the quality and performance of the Vande Bharat trains.
BKC Station Highlights
The BKC bullet train station will be an underground facility featuring three levels — platform, concourse, and service floor. Excavation has reached a depth of over 30 metres, equivalent to a 10-storey building, with approximately 84 per cent of work completed. Designed for passenger convenience, the station will offer road and metro connectivity, with two access points—one near the metro station and another near the MTNL building. Spacious interiors, modern amenities, and skylights for natural lighting will ensure a comfortable passenger experience.
Project Progress (As of September 2025)
The Mumbai–Ahmedabad Bullet Train corridor, spanning 508 kilometres, continues to make rapid progress. Of this, 323 kilometres of viaduct and 399 kilometres of pier work have been completed. Significant milestones include 17 river bridges, 5 PSC bridges, and 9 steel bridges now completed.
A total of 211 kilometres of track bed has been laid, and over 400,000 noise barriers have been installed along the corridor. Excavation is advancing for seven mountain tunnels in Palghar, while 5 kilometres of the 21-kilometre NATM tunnel between BKC and Shilphata has achieved breakthrough. Construction of rolling stock depots at Surat and Ahmedabad is underway, with superstructure works on all Gujarat stations nearing completion. Additionally, work has commenced on all three elevated stations in Maharashtra.
The visit of Minister Nakano underscores the strong partnership between India and Japan in delivering India’s first high-speed rail corridor, a flagship infrastructure project symbolising technological collaboration and shared progress.

Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology Ashwini Vaishnaw, along with Japan’s Minister of Land, Infrastructure, Transport and Tourism H.E. Hiromasa Nakano, inspected the Mumbai–Ahmedabad High-Speed Rail (HSR) construction sites in Surat and Mumbai today.Minister Nakano was welcomed at Surat International Airport with a traditional Garba performance. The reception was attended by Surat MP Mukesh Dalal, Mayor Daxesh Mavani, the Chairman of the Railway Board, senior officials of Indian Railways, NHSRCL, and the district administration.Visit to Track Slab Laying Site, SuratThe ministers visited the track construction base at the Surat High-Speed Rail site, where they observed the installation of the J-slab ballast-less track system on the viaduct. The track slab installation and permanent rail laying are progressing swiftly. Earlier, Shri Vaishnaw had witnessed the first track turnout installation near the Surat HSR station, marking a key milestone in the project’s execution.Visit to BKC HSR Station, MumbaiThe ministers travelled from Surat to Mumbai aboard the Vande Bharat Express and reviewed the progress at the Bandra Kurla Complex (BKC) underground bullet train station — a major terminal on the Mumbai–Ahmedabad HSR corridor. Minister Nakano and the Japanese delegation praised the quality and performance of the Vande Bharat trains.BKC Station HighlightsThe BKC bullet train station will be an underground facility featuring three levels — platform, concourse, and service floor. Excavation has reached a depth of over 30 metres, equivalent to a 10-storey building, with approximately 84 per cent of work completed. Designed for passenger convenience, the station will offer road and metro connectivity, with two access points—one near the metro station and another near the MTNL building. Spacious interiors, modern amenities, and skylights for natural lighting will ensure a comfortable passenger experience.Project Progress (As of September 2025)The Mumbai–Ahmedabad Bullet Train corridor, spanning 508 kilometres, continues to make rapid progress. Of this, 323 kilometres of viaduct and 399 kilometres of pier work have been completed. Significant milestones include 17 river bridges, 5 PSC bridges, and 9 steel bridges now completed.A total of 211 kilometres of track bed has been laid, and over 400,000 noise barriers have been installed along the corridor. Excavation is advancing for seven mountain tunnels in Palghar, while 5 kilometres of the 21-kilometre NATM tunnel between BKC and Shilphata has achieved breakthrough. Construction of rolling stock depots at Surat and Ahmedabad is underway, with superstructure works on all Gujarat stations nearing completion. Additionally, work has commenced on all three elevated stations in Maharashtra.The visit of Minister Nakano underscores the strong partnership between India and Japan in delivering India’s first high-speed rail corridor, a flagship infrastructure project symbolising technological collaboration and shared progress.

Next Story
Products

TOTO India Launches Premium G & L Showers with Sleek Faucet Range

TOTO India has launched its G Shower and L Shower series, alongside an expanded range of GT, LH, and Pull-Out lavatory faucets. The collection blends advanced technology, refined aesthetics, and everyday comfort, staying true to TOTO’s philosophy of creating spaces that are both beautiful and functional. The G Shower series delivers the 3Rs of showering: Relaxing, Refreshing, and Revitalizing. Features include the Calming Shawl spray mode, Warm Spa technology, and multiple overhead and hand-shower options across eight finishes. The L Shower complements this with easy-to-use controls sui..

Next Story
Infrastructure Energy

Hero Future Energies Secures Funding for 120 MW Hybrid Project

Hero Future Energies (HFE), through its SPV Clean Renewable Energy Hybrid Three, has secured Rs 19.08 billion in funding from the State Bank of India (lead) and Canara Bank. The funds will be used to develop and construct HFE’s 120 MW renewable energy hybrid project at Kurnool, Andhra Pradesh. The project, contracted with SJVN, integrates wind, solar, and storage technologies to deliver reliable peak power. With a 21-year repayment period, the funding ensures timely execution and the commencement of commercial operations. The financial closure demonstrates continued lender confidence in..

Next Story
Infrastructure Energy

IOC GPS Renewables Raises Rs 8.36 billion Debt for Compressed Biogas Plants

IOC GPS Renewables Private Limited (IGRPL), a joint venture between IndianOil Corporation  and GPS Renewables, has raised Rs 8.36 billion (approx. US$ 95 million) in debt financing from Indian Bank to execute nine Compressed Biogas (CBG) projects across India.   The funding is the largest single-bank debt raise in the CBG sector and the first fully non-recourse financing in India for these projects. The plants—four in Haryana, three in Uttar Pradesh, one each in Chhattisgarh and Andhra Pradesh—will each produce 15 tonnes of CBG per day using paddy straw as feedstock. All nin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?