Kasarwadavli-Gaimukh Metro 4A Completion Delayed to April 2025
RAILWAYS & METRO RAIL

Kasarwadavli-Gaimukh Metro 4A Completion Delayed to April 2025

The completion of the Kasarwadavli-Gaimukh Metro 4A corridor has been delayed to April 2025, surpassing the original deadline of March 2024, according to a reply from the Mumbai Metropolitan Region Development Authority (MMRDA) to an RTI query. The delay has caused a cost escalation of Rs 630 million, raising the project’s total cost from Rs 4.4 billion to Rs 5.03 billion.

Mumbai-based activist Anil Galgali, who filed the RTI, expressed concerns over the prolonged construction timeline. “I have witnessed significant traffic congestion on Ghodbunder Road due to the ongoing Metro 4A work. The delay has caused massive inconvenience to commuters,” said Galgali.

The project, initiated in September 2019, was expected to alleviate pressure on the state highway and serve as a vital commuting alternative. However, the timeline extension has disrupted plans. The contractor has been penalized Rs 2.2 million for the delay, but the MMRDA did not disclose the reasons behind the setbacks.

As traffic snarls persist and costs mount, commuters eagerly await the Metro 4A’s completion, which is expected to significantly improve connectivity in the region.

The completion of the Kasarwadavli-Gaimukh Metro 4A corridor has been delayed to April 2025, surpassing the original deadline of March 2024, according to a reply from the Mumbai Metropolitan Region Development Authority (MMRDA) to an RTI query. The delay has caused a cost escalation of Rs 630 million, raising the project’s total cost from Rs 4.4 billion to Rs 5.03 billion. Mumbai-based activist Anil Galgali, who filed the RTI, expressed concerns over the prolonged construction timeline. “I have witnessed significant traffic congestion on Ghodbunder Road due to the ongoing Metro 4A work. The delay has caused massive inconvenience to commuters,” said Galgali. The project, initiated in September 2019, was expected to alleviate pressure on the state highway and serve as a vital commuting alternative. However, the timeline extension has disrupted plans. The contractor has been penalized Rs 2.2 million for the delay, but the MMRDA did not disclose the reasons behind the setbacks. As traffic snarls persist and costs mount, commuters eagerly await the Metro 4A’s completion, which is expected to significantly improve connectivity in the region.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code