Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push
RAILWAYS & METRO RAIL

Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push

Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.

To date, 552 piles—about 28 per cent of the viaduct requirement—are in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.

KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.

The agency insists the heavy lifting—literally and figuratively—is under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.


Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.To date, 552 piles—about 28 per cent of the viaduct requirement—are in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.The agency insists the heavy lifting—literally and figuratively—is under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement