+
Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push
RAILWAYS & METRO RAIL

Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push

Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.

To date, 552 piles—about 28 per cent of the viaduct requirement—are in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.

KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.

The agency insists the heavy lifting—literally and figuratively—is under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.


Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.To date, 552 piles—about 28 per cent of the viaduct requirement—are in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.The agency insists the heavy lifting—literally and figuratively—is under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.

Next Story
Infrastructure Energy

Telangana Plans Rs 135 Bn Underground Cable Project

The Telangana government has unveiled an ambitious Rs 135 billion initiative to replace 25,000 km of overhead power lines with underground (UG) cables across the Core Urban Region (CUR), which includes Greater Hyderabad, areas within the Outer Ring Road, and Bharat Future City. The project seeks to modernise the city’s electrical infrastructure, aiming to reduce outages caused by weather or accidents.Led by the Southern Power Distribution Company of Telangana Ltd (TGSPDCL), the scheme is designed to improve safety, reduce disruption during rainfall, and lower long-term maintenance costs. Cur..

Next Story
Infrastructure Energy

Nayara Ships Fuel Despite EU Sanctions Disruption

Russia-backed Indian refiner Nayara Energy has exported its first petrol cargo since being sanctioned by the European Union on 18 July, according to four shipping sources and LSEG data.The tanker Tempest Dream, carrying approximately 43,000 metric tonnes (363,350 barrels) of petrol, departed on Monday for Sohar, Oman, based on LSEG shipping data, although the buyer’s identity remains unverified. The vessel was itself sanctioned by the United Kingdom in June.A second vessel, the Sard, currently docked at Nayara’s Vadinar port in western India, is expected to load around 43,000 tonnes of die..

Next Story
Infrastructure Urban

Brokerages Bullish on Vedanta’s FY26 Growth Prospects

Major Indian and global brokerages remain optimistic about Vedanta Ltd’s performance for FY26, highlighting firm London Metal Exchange (LME) pricing, disciplined cost controls, a strong aluminium business, and deleveraging as the company’s key growth drivers.Several upcoming growth projects, slated for commissioning over the next few quarters, also support the positive outlook.JP Morgan reported that Vedanta’s consolidated EBITDA for Q1 was broadly in line with expectations. Segments such as aluminium, oil and gas, and power performed better than anticipated, resulting in a segmental EBI..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?