+
Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push
RAILWAYS & METRO RAIL

Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push

Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.

To date, 552 piles—about 28 per cent of the viaduct requirement—are in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.

KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.

The agency insists the heavy lifting—literally and figuratively—is under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.


Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.To date, 552 piles—about 28 per cent of the viaduct requirement—are in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.The agency insists the heavy lifting—literally and figuratively—is under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.

Next Story
Infrastructure Energy

Reliable Energy Storage Vital for 24/7 Renewable Power: TKIL

Reliable, scalable, and efficient energy storage systems are essential to ensuring uninterrupted renewable energy supply, said engineering firm TKIL Industries at the India Energy Storage Week (IESW) 2025.India aims to achieve 500 GW of renewable energy capacity within the next five years.Speaking at IESW, organised by the India Energy Storage Alliance (IESA), Vivek Bhatia, Managing Director and CEO of TKIL Industries, emphasised that the country’s energy sector is experiencing a major transformation. This shift is being driven by innovations in storage technology, aimed at improving grid re..

Next Story
Infrastructure Energy

IIT Madras, Hyundai Launch £17m Hydrogen Research Centre

The Indian Institute of Technology Madras (IIT Madras) and Hyundai Motor India Ltd (HMIL) have announced the establishment of the Hyundai HTWO Innovation Centre, a cutting-edge hydrogen research facility set to begin operations by 2026.The Rs 180 crore (approx. £17 million or USD 21.5 million) project will be located at IIT Madras' Discovery Campus in Thaiyur, near Chennai. Of the total, Rs 100 crore (approx. £9.4 million) has been committed by HMIL and its philanthropic arm, Hyundai Motor India Foundation (HMIF), with support from the Government of Tamil Nadu and its investment promotion ag..

Next Story
Infrastructure Energy

India’s Hydrogen Demand to Hit 8.8 MTPA by 2032: IESA Report

India’s hydrogen demand is projected to grow at a compound annual growth rate (CAGR) of 3 per cent, reaching 8.8 million tonnes per annum (MTPA) by 2032, according to a report released by the India Energy Storage Alliance (IESA).Unveiled on the first day of the India Energy Storage Week (IESW) 2025, the report points out a gap between ambitious project announcements and actual progress. While green hydrogen (GH₂) projects totalling 9.2 MTPA have been announced, only a limited number have reached Final Investment Decision (FID) or secured long-term domestic or international offtake agreemen..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?