Kochi Water Metro Expansion Hit by Seven-Year Delays
RAILWAYS & METRO RAIL

Kochi Water Metro Expansion Hit by Seven-Year Delays

The Kochi Water Metro project, originally planned for completion within four years, has faced delays extending to seven years, leaving much of its proposed fleet and terminal infrastructure incomplete. Of the 78 boats and 38 jetties planned under the Rs. 11.36 bn project, only 20 boats and 12 terminals have been commissioned.

The project is largely financed through a long-term loan from KfW Development Bank under an Indo-German financial cooperation agreement. It was initially intended to become fully operational by 2019, but the loan period has been extended several times and is now due to expire in June 2027. Kochi Metro Rail (KMRL), the implementing agency, is seeking another extension.

Delays have been attributed to holdups in the manufacture and delivery of boats by Cochin Shipyard (CSL), contractor timelines, monsoon disruptions and elections. A total of 26 terminals and 58 boats remain to be commissioned. The project was proposed in 2015 in two phases, with the first phase covering seven routes and 43 boats, and the second extending services to 16 routes.

The infrastructure plan provided for 18 major jetties and 20 minor jetties. Three major jetties at Elamkunnapuzha, Kadamakudy and Varapuzha, along with seven minor facilities, were earmarked for later development. Only the Eloor and Cheranalloor minor jetties among these are currently operational. Around 40 per cent of the funds remain unutilised, while lower ridership at Vypeen, Bolgatty and Cheranalloor has added to concerns.

KMRL has said construction of new terminals is nearing completion, with Kadamakudy and Paliyamthuruthu ready apart from approach-road work. It expects 30 piling works and five pile-chipping works to be completed in October, while contracts for Edakochi and Varapuzha terminals, an operation control centre and office facilities may soon be awarded. One remaining CSL boat is due in December and two in June 2028, while tenders have been invited for 15 additional boats. Floating jetties are also scheduled for installation by December 2026 after dredging.

The Kochi Water Metro project, originally planned for completion within four years, has faced delays extending to seven years, leaving much of its proposed fleet and terminal infrastructure incomplete. Of the 78 boats and 38 jetties planned under the Rs. 11.36 bn project, only 20 boats and 12 terminals have been commissioned. The project is largely financed through a long-term loan from KfW Development Bank under an Indo-German financial cooperation agreement. It was initially intended to become fully operational by 2019, but the loan period has been extended several times and is now due to expire in June 2027. Kochi Metro Rail (KMRL), the implementing agency, is seeking another extension. Delays have been attributed to holdups in the manufacture and delivery of boats by Cochin Shipyard (CSL), contractor timelines, monsoon disruptions and elections. A total of 26 terminals and 58 boats remain to be commissioned. The project was proposed in 2015 in two phases, with the first phase covering seven routes and 43 boats, and the second extending services to 16 routes. The infrastructure plan provided for 18 major jetties and 20 minor jetties. Three major jetties at Elamkunnapuzha, Kadamakudy and Varapuzha, along with seven minor facilities, were earmarked for later development. Only the Eloor and Cheranalloor minor jetties among these are currently operational. Around 40 per cent of the funds remain unutilised, while lower ridership at Vypeen, Bolgatty and Cheranalloor has added to concerns. KMRL has said construction of new terminals is nearing completion, with Kadamakudy and Paliyamthuruthu ready apart from approach-road work. It expects 30 piling works and five pile-chipping works to be completed in October, while contracts for Edakochi and Varapuzha terminals, an operation control centre and office facilities may soon be awarded. One remaining CSL boat is due in December and two in June 2028, while tenders have been invited for 15 additional boats. Floating jetties are also scheduled for installation by December 2026 after dredging.

Related Stories

Gold Stories

Next Story
Resources

K Raheja Corp Homes hosts Joyfest 2.0 at Navi Mumbai project

K Raheja Corp Homes hosted the second edition of Joyfest at Raheja Jade City in Juinagar, Navi Mumbai, bringing together more than 500 residents and visitors for an evening of games, music and family activities.The event, themed ‘Streets of India’, drew inspiration from traditional Indian fairs and included food stalls, interactive games and entertainment for different age groups. Activities included virtual reality cricket, balloon shooting, motion dance, Ring the Pot and Hit the Tins. A jumping castle, bubble artist and mascots added to the attractions.Participants also took part in diya..

Next Story
Real Estate

Ashiana Housing launches third phase of Chennai senior living project

Ashiana Housing has launched Phase 3 of Ashiana Vatsalya, its active senior living project in Chennai. The new phase will add 168 residential units, with an estimated investment of Rs 1.004 billion. Construction is scheduled for completion by March 2029.Spread across 17.9 acre, the new phase will offer one-, two-, and three-bedroom homes priced between Rs 8.5 million and Rs 16.9 million. The International Finance Corporation (IFC) will fund the investment.The larger development includes a 42,000 sq ft clubhouse, 6.3 acres of landscaped and park areas, and more than 40 lifestyle and sports amen..

Next Story
Infrastructure Transport

Seco Marks 30 Years in India, Strengthens Pune Operations Wins Rs 8.39 Billion Vande Bharat Sleeper Orders

"Wabtec Corporation (NYSE: WAB) has secured orders worth approximately US$94 million (Rs 8.39 billion, or Rs 8,390 million) from Indian Railways for systems for the Vande Bharat Sleeper programme. The equipment is intended to increase service availability, simplify maintenance and improve passenger safety.Wabtec will supply onboard brake systems, doors and gangway solutions. Its scope also includes system delivery, integration support, testing, commissioning and long-term operational reliability support.Pascal Schweitzer, President, Wabtec Transit, said the orders reflect the company’s commi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code