Kochi Water Metro Expansion Hit by Seven-Year Delays
RAILWAYS & METRO RAIL

Kochi Water Metro Expansion Hit by Seven-Year Delays

The Kochi Water Metro project, originally planned for completion within four years, has faced delays extending to seven years, leaving much of its proposed fleet and terminal infrastructure incomplete. Of the 78 boats and 38 jetties planned under the Rs. 11.36 bn project, only 20 boats and 12 terminals have been commissioned.

The project is largely financed through a long-term loan from KfW Development Bank under an Indo-German financial cooperation agreement. It was initially intended to become fully operational by 2019, but the loan period has been extended several times and is now due to expire in June 2027. Kochi Metro Rail (KMRL), the implementing agency, is seeking another extension.

Delays have been attributed to holdups in the manufacture and delivery of boats by Cochin Shipyard (CSL), contractor timelines, monsoon disruptions and elections. A total of 26 terminals and 58 boats remain to be commissioned. The project was proposed in 2015 in two phases, with the first phase covering seven routes and 43 boats, and the second extending services to 16 routes.

The infrastructure plan provided for 18 major jetties and 20 minor jetties. Three major jetties at Elamkunnapuzha, Kadamakudy and Varapuzha, along with seven minor facilities, were earmarked for later development. Only the Eloor and Cheranalloor minor jetties among these are currently operational. Around 40 per cent of the funds remain unutilised, while lower ridership at Vypeen, Bolgatty and Cheranalloor has added to concerns.

KMRL has said construction of new terminals is nearing completion, with Kadamakudy and Paliyamthuruthu ready apart from approach-road work. It expects 30 piling works and five pile-chipping works to be completed in October, while contracts for Edakochi and Varapuzha terminals, an operation control centre and office facilities may soon be awarded. One remaining CSL boat is due in December and two in June 2028, while tenders have been invited for 15 additional boats. Floating jetties are also scheduled for installation by December 2026 after dredging.

The Kochi Water Metro project, originally planned for completion within four years, has faced delays extending to seven years, leaving much of its proposed fleet and terminal infrastructure incomplete. Of the 78 boats and 38 jetties planned under the Rs. 11.36 bn project, only 20 boats and 12 terminals have been commissioned. The project is largely financed through a long-term loan from KfW Development Bank under an Indo-German financial cooperation agreement. It was initially intended to become fully operational by 2019, but the loan period has been extended several times and is now due to expire in June 2027. Kochi Metro Rail (KMRL), the implementing agency, is seeking another extension. Delays have been attributed to holdups in the manufacture and delivery of boats by Cochin Shipyard (CSL), contractor timelines, monsoon disruptions and elections. A total of 26 terminals and 58 boats remain to be commissioned. The project was proposed in 2015 in two phases, with the first phase covering seven routes and 43 boats, and the second extending services to 16 routes. The infrastructure plan provided for 18 major jetties and 20 minor jetties. Three major jetties at Elamkunnapuzha, Kadamakudy and Varapuzha, along with seven minor facilities, were earmarked for later development. Only the Eloor and Cheranalloor minor jetties among these are currently operational. Around 40 per cent of the funds remain unutilised, while lower ridership at Vypeen, Bolgatty and Cheranalloor has added to concerns. KMRL has said construction of new terminals is nearing completion, with Kadamakudy and Paliyamthuruthu ready apart from approach-road work. It expects 30 piling works and five pile-chipping works to be completed in October, while contracts for Edakochi and Varapuzha terminals, an operation control centre and office facilities may soon be awarded. One remaining CSL boat is due in December and two in June 2028, while tenders have been invited for 15 additional boats. Floating jetties are also scheduled for installation by December 2026 after dredging.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Supreme Infrastructure posts first post-scheme quarterly profit

Supreme Infrastructure India reported its first profitable quarter following the completion of its Composite Scheme, with a sharp increase in revenue and a significant reduction in finance costs driving its financial turnaround in Q2 FY27.Revenue from operations rose 114.8 per cent year-on-year to Rs 290.04 million in Q2 FY27, compared with Rs 135.02 million in the corresponding quarter last year. Total income increased 130.3 per cent to Rs 335.63 million from Rs 135.56 million.The company reported a profit after tax (PAT) of Rs 36.78 million in Q2 FY27, against a loss of Rs 591.43 million in ..

Next Story
Infrastructure Transport

J. Kumar Infraprojects Q2 profit rises 25 per cent to Rs 1.13 billion

J. Kumar Infraprojects reported a 25 per cent year-on-year increase in net profit to Rs 1.13 billion in Q2 FY27, while revenue from operations grew 15 per cent to Rs 15.39 billion.Profitability improved faster than revenue, with EBITDA rising 18 per cent to Rs 2.29 billion. The EBITDA margin expanded to 14.9 per cent, supported by cost control and steady project execution. Net profit margin increased to 7.4 per cent from 6.7 per cent in the corresponding quarter last year.The company's order book stood at Rs 227.11 billion, equivalent to nearly four times its annual revenue. It secured fresh o..

Next Story
Equipment

NORD India to invest Rs 4 billion in new Pune manufacturing facility

NORD Drivesystems India (NDPL) has commenced construction of a new manufacturing facility at RMK Industrial Park 3, near MIDC Talegaon Phase V, Pune, with a planned investment of Rs 4 billion. The expansion will double the company's gearbox and geared motor production capacity and introduce gear-component manufacturing.The facility will cater to domestic demand and exports to other NORD subsidiaries, including its headquarters in Germany. The company also plans to manufacture gears and related components at the new plant, supporting both the Indian market and global operations.Dhanraj Kalbhor,..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code