L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line
RAILWAYS & METRO RAIL

L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03.

The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal.

L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March.

According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation.

Also Read
First nine months of FY23 records Ajmera Realty sale of 6.94 billion
Delhi-NCR Developers bat for exemption from the construction ban

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03. The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal. L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March. According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation. Also Read First nine months of FY23 records Ajmera Realty sale of 6.94 billion Delhi-NCR Developers bat for exemption from the construction ban

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->