L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line
RAILWAYS & METRO RAIL

L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03.

The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal.

L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March.

According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation.

Also Read
First nine months of FY23 records Ajmera Realty sale of 6.94 billion
Delhi-NCR Developers bat for exemption from the construction ban

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03. The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal. L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March. According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation. Also Read First nine months of FY23 records Ajmera Realty sale of 6.94 billion Delhi-NCR Developers bat for exemption from the construction ban

Next Story
Infrastructure Energy

GAIL to Set Up Bengaluru CBG Plant Under New Concession Pact

GAIL (India) Limited has signed a 20-year concession agreement with the Bengaluru City Municipal Corporation (BBMP) to set up a compressed biogas (CBG) plant in the city. The project, expected to produce around 10 tonnes of CBG daily, will utilise municipal solid waste as feedstock, contributing to clean energy generation and efficient waste management. The CBG produced will be used in GAIL’s City Gas Distribution network to promote cleaner fuel usage. The initiative aligns with the government’s Sustainable Alternative Towards Affordable Transportation (SATAT) scheme and GAIL’s broader ..

Next Story
Infrastructure Energy

Uttarakhand HC Lifts 31-Year Ban on ONGC’s Contractual Hiring

The Uttarakhand High Court has lifted a 31-year-old ban on the Oil and Natural Gas Corporation (ONGC) from hiring contractual workers, a restriction imposed in 1993. The decision enables ONGC’s Dehradun establishment to employ personnel on a contractual basis to meet operational requirements. The long-standing prohibition had limited ONGC’s ability to fill vacancies in its technical and administrative departments, often leading to project delays and higher dependence on outsourcing. With the court’s directive, the public sector enterprise can now proceed with temporary recruitments whil..

Next Story
Infrastructure Energy

JSW Energy’s Utkal Unit Bags 400 MW, 25-Year Power Supply Deal

JSW Energy Limited announced that its subsidiary, JSW Energy (Utkal) Limited, has secured a Letter of Award (LoA) from Karnataka’s Power Company of Karnataka Limited (PCKL) for the supply of 400 MW of electricity for 25 years. The agreement is part of a competitive bidding process for long-term procurement of power to meet the state’s growing energy demand. The 400 MW capacity will be supplied from JSW Energy’s upcoming thermal power project in Odisha. This development strengthens JSW Energy’s presence in the southern market and aligns with its strategy to enhance long-term contracte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?