L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line
RAILWAYS & METRO RAIL

L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03.

The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal.

L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March.

According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation.

Also Read
First nine months of FY23 records Ajmera Realty sale of 6.94 billion
Delhi-NCR Developers bat for exemption from the construction ban

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03. The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal. L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March. According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation. Also Read First nine months of FY23 records Ajmera Realty sale of 6.94 billion Delhi-NCR Developers bat for exemption from the construction ban

Next Story
Infrastructure Transport

Shivraj Chouhan Launches PMGSY IV and Announces Package for Madhya Pradesh

Union Minister Shivraj Singh Chouhan launched the Pradhan Mantri Gram Sadak Yojana (PMGSY) IV at Bhairunda in Sehore district during the 25 year celebrations and announced a development package for Madhya Pradesh. The programme was organised by the Union Ministry of Rural Development and attended by Chief Minister Dr Mohan Yadav, ministers of state, state ministers, legislators and senior officials from the centre and the state. The minister said the central government under the Prime Minister is committed to strengthening rural livelihoods through improved connectivity, housing and women's in..

Next Story
Infrastructure Urban

DMR Engineering Reports FY 25-26 Financial Results

DMR Engineering reported its half year results for the financial year ended 31 March 2026 and published full year figures on a standalone basis. Standalone revenue from operations decreased by 2.01 per cent year-over-year to Rs 102.58 million (mn), while profit after tax declined by 43.94 per cent to nine point five six mn, leaving a profit after tax margin of nine point zero five per cent. Earnings per share stood at Rs zero point nine two, a fall of 44.71 per cent year-over-year. The company attributed part of the decline to one-off provisioning for bad debts and additional financing charges..

Next Story
Infrastructure Urban

Atlanta Electricals Posts Strong FY26 Growth And Debt Free Finish

Atlanta Electricals reported audited consolidated results for the quarter and year ended 31 March 2026. The company recorded significant year-on-year revenue growth driven by capacity ramp-up at new facilities and higher utilisation at legacy plants. The announcement summarised operating improvements and strategic milestones achieved during the year. For Q4 the company reported revenue of Rs 7.48 bn and for FY26 revenue of Rs 18.52 bn, representing robust growth versus the prior year. EBITDA in Q4 was Rs. 1.49 bn and Rs. 3.44 bn for the full year, with margins expanding to 20 per cent in the q..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement