L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line
RAILWAYS & METRO RAIL

L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03.

The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal.

L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March.

According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation.

Also Read
First nine months of FY23 records Ajmera Realty sale of 6.94 billion
Delhi-NCR Developers bat for exemption from the construction ban

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03. The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal. L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March. According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation. Also Read First nine months of FY23 records Ajmera Realty sale of 6.94 billion Delhi-NCR Developers bat for exemption from the construction ban

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?