L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line
RAILWAYS & METRO RAIL

L&T’s TBM Urja achieves third breakthrough of Bengaluru Pink Line

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03.

The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal.

L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March.

According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation.

Also Read
First nine months of FY23 records Ajmera Realty sale of 6.94 billion
Delhi-NCR Developers bat for exemption from the construction ban

Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) achieved its third and final breakthrough at the Shadi Mahal TBM Retrieval Shaft on Bengaluru Metro‘s Pink Line (Reach 6), which is 21.386 km in length on 10 January 2023. This marks the 5th in a series of 6 tunnel breakthroughs planned for the 73.92 km Phase 2 project’s Package RT-03. The Bengaluru Metro Rail Corporation (BMRCL) awarded the construction of the 2.884 km twin tunnels between Shivajinagar and Tannery Road in February 2019. After its second breakthrough at Pottery Town Station in June 2022, TBM Urja, a Ø6.67 m CRCHI slurry machine, began its final drive in July to build the 688.5 m northbound tunnel towards Shadi Mahal. L&T’s official completion estimate for the tunnelling drive at the start was 170 days, but they easily beat it. However, even though the milestone was achieved, celebrations were muted due to a fatal construction accident on the 56 km Blue Line at HBR Layout earlier in the day. Urja (Machine DZ670) was the first of nine commissioned for Phase 2 in July 2020, and it started its first drive of 860m from Cantonment Station to Shivajinagar. Its sister machine TBM Vindhya (DZ671), started its third and final drive towards Shadi Mahal Shaft in September 2022 and is expected to finish in March. According to BMRCL’s December newsletter, by November-end, 65.65 per cent of tunnelling work had been completed for Phase 2 (total scope: 21,041m), with a total of 17 out of 26 tunnel breakthroughs recorded 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 5 on RT-03 by L&T, and 4 on RT-04 by ITD Cementation. Also Read First nine months of FY23 records Ajmera Realty sale of 6.94 billion Delhi-NCR Developers bat for exemption from the construction ban

Next Story
Infrastructure Energy

Adani Power To Build 2,400 MW Plant in Bihar

Adani Power on Saturday (September 13, 2025) announced plans to set up a 2,400 MW ultra super-critical power plant in Bihar at an investment of $3 billion (around Rs 26.48 billion).The company has signed a 25-year Power Supply Agreement (PSA) with Bihar State Power Generation Company Ltd (BSPGCL) to supply electricity from the project, which will be located at Pirpainti in Bhagalpur district.The PSA follows a Letter of Award issued by BSPGCL to Adani Power on behalf of North Bihar Power Distribution Company Ltd (NBPDCL) and South Bihar Power Distribution Company Ltd (SBPDCL) in August. Adani P..

Next Story
Infrastructure Energy

NTPC Plans Nuclear Power Projects Via JV and Standalone Routes

Power major NTPC is planning to develop nuclear power projects both through joint ventures and on a standalone basis, CMD Gurdeep Singh has said.The company is collaborating with nuclear technology providers and state governments to explore individual nuclear projects, Singh added.Currently, the NTPC Group has an installed capacity of 82,926 MW across 53 NTPC-owned stations and 53 joint venture or subsidiary stations, drawing power from coal, liquid fuel, hydro, and solar sources.In December 2024, Singh had announced NTPC’s ambitious plan to enter the nuclear energy sector, a move expected t..

Next Story
Infrastructure Transport

RVNL Wins $21.6 Million Bhopal Division Traction Substation

Rail Vikas Nigam (RVNL) has been declared the lowest bidder for a $21.6 million traction substation contract awarded by the West Central Railway.The project covers the design, modification, supply, erection, testing, and commissioning of a 220/132kV/2×25kV Scott-connected traction substation, switching posts, Auto-Transformer installations, and Supervisory Control and Data Acquisition (SCADA) systems in the Bina–RTA section of the Bhopal Division. The execution period is set at 540 days.In a regulatory filing, RVNL stated that the order was secured in the ordinary course of business and doe..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?