L&T commences Chennai Metro Ph 2 tunnelling with TBM Siruvani
RAILWAYS & METRO RAIL

L&T commences Chennai Metro Ph 2 tunnelling with TBM Siruvani

Larsen & Toubro (L&T) officially put into operation tunnel boring machine (TBM) DZ1040, affectionately named Siruvani, as a pivotal milestone in the Chennai Metro Phase 2 project. This impressive 6.65-meter Earth Pressure Balance (EPB) machine represents the third out of a total of eight TBMs scheduled to commence tunnelling activities for Line-3's Package TU-02, connecting the Kellys and Taramani Road Junction stations.

The TBM Siruvani, crafted by China Railway Construction Heavy Industry (CRCHI), successfully completed rigorous factory acceptance tests during the summer of 2022. It is now geared up to embark on its journey southward from Chetpet Station towards Sterling Road, initially covering a distance of approximately 705 meters.

L&T, the designated project contractor, will deploy TBM Siruvani along with seven other TBMs to construct an impressive network of 12 twin tunnels, totalling a remarkable 24 kilometres between the Kellys and Taramani Road Junction stations. The contract for Package TU-02, valued at Rs 23.85 billion, was entrusted to L&T by Chennai Metro Rail. (CMRL) in May 2021, with a deadline set at 42 months.

In addition to the tunnel construction, L&T is also tasked with the construction of diaphragm walls and entry/exit structures at several stations, including Chetpet Station, Royapettah Government Hospital Station, Thiruvanmiyur Station, and a section of the diaphragm wall at Greenways Road Station. This encompasses the construction of launching and retrieval shafts at these respective stations.

In June, L&T initiated the intricate process of lowering the components of TBM Siruvani into Chetpet Station. Up to this point, the machine has assembled two temporary rings within the shaft for its initial drive, with plans to attach its backup gantry for the primary drive in the near future.

Larsen & Toubro (L&T) officially put into operation tunnel boring machine (TBM) DZ1040, affectionately named Siruvani, as a pivotal milestone in the Chennai Metro Phase 2 project. This impressive 6.65-meter Earth Pressure Balance (EPB) machine represents the third out of a total of eight TBMs scheduled to commence tunnelling activities for Line-3's Package TU-02, connecting the Kellys and Taramani Road Junction stations.The TBM Siruvani, crafted by China Railway Construction Heavy Industry (CRCHI), successfully completed rigorous factory acceptance tests during the summer of 2022. It is now geared up to embark on its journey southward from Chetpet Station towards Sterling Road, initially covering a distance of approximately 705 meters.L&T, the designated project contractor, will deploy TBM Siruvani along with seven other TBMs to construct an impressive network of 12 twin tunnels, totalling a remarkable 24 kilometres between the Kellys and Taramani Road Junction stations. The contract for Package TU-02, valued at Rs 23.85 billion, was entrusted to L&T by Chennai Metro Rail. (CMRL) in May 2021, with a deadline set at 42 months.In addition to the tunnel construction, L&T is also tasked with the construction of diaphragm walls and entry/exit structures at several stations, including Chetpet Station, Royapettah Government Hospital Station, Thiruvanmiyur Station, and a section of the diaphragm wall at Greenways Road Station. This encompasses the construction of launching and retrieval shafts at these respective stations.In June, L&T initiated the intricate process of lowering the components of TBM Siruvani into Chetpet Station. Up to this point, the machine has assembled two temporary rings within the shaft for its initial drive, with plans to attach its backup gantry for the primary drive in the near future.

Next Story
Infrastructure Transport

Shivraj Chouhan Launches PMGSY IV and Announces Package for Madhya Pradesh

Union Minister Shivraj Singh Chouhan launched the Pradhan Mantri Gram Sadak Yojana (PMGSY) IV at Bhairunda in Sehore district during the 25 year celebrations and announced a development package for Madhya Pradesh. The programme was organised by the Union Ministry of Rural Development and attended by Chief Minister Dr Mohan Yadav, ministers of state, state ministers, legislators and senior officials from the centre and the state. The minister said the central government under the Prime Minister is committed to strengthening rural livelihoods through improved connectivity, housing and women's in..

Next Story
Infrastructure Urban

DMR Engineering Reports FY 25-26 Financial Results

DMR Engineering reported its half year results for the financial year ended 31 March 2026 and published full year figures on a standalone basis. Standalone revenue from operations decreased by 2.01 per cent year-over-year to Rs 102.58 million (mn), while profit after tax declined by 43.94 per cent to nine point five six mn, leaving a profit after tax margin of nine point zero five per cent. Earnings per share stood at Rs zero point nine two, a fall of 44.71 per cent year-over-year. The company attributed part of the decline to one-off provisioning for bad debts and additional financing charges..

Next Story
Infrastructure Urban

Atlanta Electricals Posts Strong FY26 Growth And Debt Free Finish

Atlanta Electricals reported audited consolidated results for the quarter and year ended 31 March 2026. The company recorded significant year-on-year revenue growth driven by capacity ramp-up at new facilities and higher utilisation at legacy plants. The announcement summarised operating improvements and strategic milestones achieved during the year. For Q4 the company reported revenue of Rs 7.48 bn and for FY26 revenue of Rs 18.52 bn, representing robust growth versus the prior year. EBITDA in Q4 was Rs. 1.49 bn and Rs. 3.44 bn for the full year, with margins expanding to 20 per cent in the q..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement