L&T Exit Hits Bengaluru Rail Project, Sparks Political Row
RAILWAYS & METRO RAIL

L&T Exit Hits Bengaluru Rail Project, Sparks Political Row

The withdrawal of Larsen & Toubro (L&T) from two major corridors of the Bengaluru Suburban Railway Project (BSRP) has drawn strong political backlash, with BJP Members of Parliament accusing the Congress-led Karnataka government of bureaucratic inefficiency that has impeded the city’s much-anticipated transit initiative.
Bangalore Central MP P.C. Mohan called the exit a “betrayal” of the people of Bengaluru. “L&T exits Bengaluru Suburban Rail Corridors 2 and 4 citing only 8.28 per cent land handover in two years. K-RIDE failed because the State Government did not clear land in time. This delay betrays Bengalureans. The Congress Government must fix K-RIDE and remove land hurdles immediately,” he posted on social media.
Echoing similar sentiments, Bangalore South MP Tejasvi Surya attributed the collapse to a lack of urgency. “The Bengaluru Suburban Railway Project is struggling due to @KridePrm’s bureaucratic chaos,” he stated. “This reflects a broader governance failure and absence of initiative at the state level.”
L&T formally terminated its contract for Corridors 2 and 4 and submitted a closure report, citing the state’s failure to provide adequate encumbrance-free land. Since the Letter of Acceptance was issued in August 2022, only 8.28 per cent of usable land had been handed over, leading to cost overruns, idle labour and equipment, and stalled progress.
In its letter to the Rail Infrastructure Development Company (Karnataka) Ltd (K-RIDE), L&T stated that continued delays rendered further construction unviable. The company has now approached the Commercial Court in Bengaluru, which has issued an interim injunction preventing K-RIDE from invoking L&T’s bank guarantees.
L&T is also seeking compensation of approximately Rs 5 billion for Corridor 2 and Rs 1.5 billion for Corridor 4, according to a report by The New Indian Express.
This development marks a major setback for the Rs 157.67 billion BSRP, which was sanctioned in October 2020 with a planned completion timeline of six years.

The withdrawal of Larsen & Toubro (L&T) from two major corridors of the Bengaluru Suburban Railway Project (BSRP) has drawn strong political backlash, with BJP Members of Parliament accusing the Congress-led Karnataka government of bureaucratic inefficiency that has impeded the city’s much-anticipated transit initiative.Bangalore Central MP P.C. Mohan called the exit a “betrayal” of the people of Bengaluru. “L&T exits Bengaluru Suburban Rail Corridors 2 and 4 citing only 8.28 per cent land handover in two years. K-RIDE failed because the State Government did not clear land in time. This delay betrays Bengalureans. The Congress Government must fix K-RIDE and remove land hurdles immediately,” he posted on social media.Echoing similar sentiments, Bangalore South MP Tejasvi Surya attributed the collapse to a lack of urgency. “The Bengaluru Suburban Railway Project is struggling due to @KridePrm’s bureaucratic chaos,” he stated. “This reflects a broader governance failure and absence of initiative at the state level.”L&T formally terminated its contract for Corridors 2 and 4 and submitted a closure report, citing the state’s failure to provide adequate encumbrance-free land. Since the Letter of Acceptance was issued in August 2022, only 8.28 per cent of usable land had been handed over, leading to cost overruns, idle labour and equipment, and stalled progress.In its letter to the Rail Infrastructure Development Company (Karnataka) Ltd (K-RIDE), L&T stated that continued delays rendered further construction unviable. The company has now approached the Commercial Court in Bengaluru, which has issued an interim injunction preventing K-RIDE from invoking L&T’s bank guarantees.L&T is also seeking compensation of approximately Rs 5 billion for Corridor 2 and Rs 1.5 billion for Corridor 4, according to a report by The New Indian Express.This development marks a major setback for the Rs 157.67 billion BSRP, which was sanctioned in October 2020 with a planned completion timeline of six years.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement