+
Metro 3 Completes Track Laying from BKC to Cuffe Parade
RAILWAYS & METRO RAIL

Metro 3 Completes Track Laying from BKC to Cuffe Parade

The laying of tracks for both the up and down lines of the BKC-Cuffe Parade section of the Metro 3 project has been completed. This 21km-long section, which constitutes Phase II of the project, is on schedule for commissioning before the next monsoon, according to an official from the Mumbai Metro Rail Corporation (MMRC).

Despite the progress, challenges remain, particularly at Acharya Atre Chowk, where on-going utility work has caused delays. Phase I of the project, a 12.5 km corridor between Aarey and BKC, was inaugurated on October 5 and opened to commuters on October 7, with an average daily ridership of 22,000.

MMRC announced on X (formerly Twitter) that 100 per cent of track laying had been completed, describing it as a significant milestone toward the project's full commissioning. Phase II has achieved an overall progress rate of 88 per cent, with 99 per cent of station and tunnel construction and 97.6 per cent of station construction completed. Systems work and the overhead catenary system (OCS) installation are nearing 60 per cent completion.

The construction of underground stations at Kalbadevi and Girgaum remains one of the most challenging aspects of the project. These densely populated areas, characterized by heritage structures, narrow roads, and old buildings, have faced significant disruption. A total of 423 residential units and 289 commercial blocks have been affected, along with approximately 20 land parcels and 30 buildings spread across six non-contiguous blocks.

Once completed, Metro 3 will offer interchanges with the suburban train network at Churchgate, CSMT, Mumbai Central, and Mahalaxmi stations. It will also run close to major railway stations such as Charni Road, Grant Road, and Dadar.

The laying of tracks for both the up and down lines of the BKC-Cuffe Parade section of the Metro 3 project has been completed. This 21km-long section, which constitutes Phase II of the project, is on schedule for commissioning before the next monsoon, according to an official from the Mumbai Metro Rail Corporation (MMRC). Despite the progress, challenges remain, particularly at Acharya Atre Chowk, where on-going utility work has caused delays. Phase I of the project, a 12.5 km corridor between Aarey and BKC, was inaugurated on October 5 and opened to commuters on October 7, with an average daily ridership of 22,000. MMRC announced on X (formerly Twitter) that 100 per cent of track laying had been completed, describing it as a significant milestone toward the project's full commissioning. Phase II has achieved an overall progress rate of 88 per cent, with 99 per cent of station and tunnel construction and 97.6 per cent of station construction completed. Systems work and the overhead catenary system (OCS) installation are nearing 60 per cent completion. The construction of underground stations at Kalbadevi and Girgaum remains one of the most challenging aspects of the project. These densely populated areas, characterized by heritage structures, narrow roads, and old buildings, have faced significant disruption. A total of 423 residential units and 289 commercial blocks have been affected, along with approximately 20 land parcels and 30 buildings spread across six non-contiguous blocks. Once completed, Metro 3 will offer interchanges with the suburban train network at Churchgate, CSMT, Mumbai Central, and Mahalaxmi stations. It will also run close to major railway stations such as Charni Road, Grant Road, and Dadar.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code