MMRCL completes 96% tunneling work for Mumbai Metro Line-3
RAILWAYS & METRO RAIL

MMRCL completes 96% tunneling work for Mumbai Metro Line-3

Mumbai Metro Rail Corporation (MMRC) accomplished its 39th breakthrough at Mahalaxmi Metro Station out of the 42 breakthroughs planned for the Colaba-Bandra-Seepz underground line, 33.5 km long (line-3), of Mumbai Metro.

Tunnel Boring Machine (TBM), known as Tansa-2, built by the Robbins Company, operated by Doğuş and Soma JV, finished 1,117.5 meters of upline drive of tunnelling from the Science Museum Metro Station to Mahalaxmi Metro Station.

To complete the work, TBM Tansa-2 took 257 days, utilising 745 concrete rings.

Package-3 (Mumbai Central–Worli) consists of Acharya Atre Chowk, Science Museum, Mahalaxmi, Worli Metro stations, and Mumbai Central.It is the longest stretch of the corridor, and out of six breakthroughs planned under this package, it has seen three as of now.

The completed three packages completed are- Science Museum to Mahalaxmi – upline-1117.5m, Science Museum to Worli – upline-2072m, and downline-2057m

By this breakthrough, the total tunnelling finished on the project is 52.60 km out of the 54.50 km double line, around 96.5% of the entire project.

Under Package-3, three more breakthroughs are remaining. The completion of these breakthroughs would mark the end of the tunnelling work on the 33.5 km long fully underground line, including 27 stations on the route.

MMRC, a joint enterprise Indian Government and Maharashtra government, is the nodal firm responsible for implementing the Mumbai Metro Line-3 project.

Image Source


Also read: Mumbai Metro-3 project faces cash crunch

Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough

Mumbai Metro Rail Corporation (MMRC) accomplished its 39th breakthrough at Mahalaxmi Metro Station out of the 42 breakthroughs planned for the Colaba-Bandra-Seepz underground line, 33.5 km long (line-3), of Mumbai Metro. Tunnel Boring Machine (TBM), known as Tansa-2, built by the Robbins Company, operated by Doğuş and Soma JV, finished 1,117.5 meters of upline drive of tunnelling from the Science Museum Metro Station to Mahalaxmi Metro Station. To complete the work, TBM Tansa-2 took 257 days, utilising 745 concrete rings. Package-3 (Mumbai Central–Worli) consists of Acharya Atre Chowk, Science Museum, Mahalaxmi, Worli Metro stations, and Mumbai Central.It is the longest stretch of the corridor, and out of six breakthroughs planned under this package, it has seen three as of now. The completed three packages completed are- Science Museum to Mahalaxmi – upline-1117.5m, Science Museum to Worli – upline-2072m, and downline-2057m By this breakthrough, the total tunnelling finished on the project is 52.60 km out of the 54.50 km double line, around 96.5% of the entire project. Under Package-3, three more breakthroughs are remaining. The completion of these breakthroughs would mark the end of the tunnelling work on the 33.5 km long fully underground line, including 27 stations on the route. MMRC, a joint enterprise Indian Government and Maharashtra government, is the nodal firm responsible for implementing the Mumbai Metro Line-3 project. Image Source Also read: Mumbai Metro-3 project faces cash crunch Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough

Next Story
Infrastructure Urban

India Expands Semiconductor Training To 500 Institutions

Under the Chips to Startups programme of the India Semiconductor Mission, the Union minister responsible for Railways, Information and Broadcasting, and Electronics and IT reported notable progress in talent development. He indicated that over the past four years substantial steps have been taken towards a 10-year target of training 85,000 engineers in semiconductor design. World-class EDA tools have been deployed in 315 academic institutions across the country to provide students with practical exposure to chip design. These EDA tools are supported by leading global firms and are accessible t..

Next Story
Infrastructure Urban

Delhi Institutions Support India Semiconductor Mission

The Government of India has prioritised talent development through training, upskilling and workforce development under the Chips to Startups initiative of the India Semiconductor Mission, with officials noting progress in four years towards a 10-year target of training 85,000 engineers in semiconductor design. Electronic design automation tools provided by Synopsys, Cadence, Siemens, Renesas, Ansys and AMD have been deployed in 315 academic institutions, enabling students to gain practical chip design experience. Chips have been fabricated and tested at the Semiconductor Laboratory, Mohali, a..

Next Story
Infrastructure Urban

NHA Announces Winners Of NHCX Hackathon At IIT Hyderabad

The National Health Authority (NHA) has concluded the NHCX Hackathon under the Ayushman Bharat Digital Mission (ABDM) to stimulate innovation around the National Health Claims Exchange (NHCX). The winning teams presented their solutions at the NHCX Innovation Meet held at IIT Hyderabad during a two-day event in March 2026 that also served as the hackathon grand finale. The hackathon itself ran from 22 to 28 February 2026 and aimed to accelerate paperless, transparent claims processing across India. The event was organised with a range of ecosystem partners, including the Insurance Regulatory a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement