Mumbai Metro-3 project faces cash crunch
RAILWAYS & METRO RAIL

Mumbai Metro-3 project faces cash crunch

The long delayed Mumbai Metro 3 project from Cuffe Parade to SEEPZ is now facing a major cash crunch.

Suzuki Satoshi, the Japanese ambassador to India, wrote to Chief Minister Uddhav Thackeray on February 17, 2021, expressing concerns about an impending cash crunch and significant delay or stagnation for the project.

The suburban collector's decision to hand over the Kanjurmarg plot for the car shed was stayed by the Bombay High Court in December.

According to protocol, the state must first approve the cost escalation proposal and then notify the union ministry of housing and urban affairs of its decision. Japan International Cooperation Agency (JICA) disburses the loan once the centre has cleared it.

The letter said that the issue of the depot's location is resolved and JICA stands ready to consider another loan to support the depot's construction.

The approval of the revision of the total project cost to reflect actual fund requirements, according to a two-page annex note attached to the ambassador's letter, is indispensable for Mumbai Metro Rail Corporation Limited(MMRCL).

The letter stated that it was recognised during JICA's detailed fact finding mission with MMRCL, which took place from December 2020 to January 2021, that there is a real possibility for MMRCL to face fund shortage within the next fiscal year (FY2021) if an additional loan cannot be provided by the end of this fiscal year (FY2020).

MMRCL, the project's implementing authority, has already spent Rs 18,000 crore on the 33.5 km Metro 3 line. About 70% of the work, including 95% of the tunnelling, has been completed. Despite the fact that the metro car shed accounts for only 4% of the project's total cost, the project cannot be completed without it.

Image Source


Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough

Also read: Mumbai Metro 2A, 7 to be fully operational from January 2022

The long delayed Mumbai Metro 3 project from Cuffe Parade to SEEPZ is now facing a major cash crunch. Suzuki Satoshi, the Japanese ambassador to India, wrote to Chief Minister Uddhav Thackeray on February 17, 2021, expressing concerns about an impending cash crunch and significant delay or stagnation for the project. The suburban collector's decision to hand over the Kanjurmarg plot for the car shed was stayed by the Bombay High Court in December. According to protocol, the state must first approve the cost escalation proposal and then notify the union ministry of housing and urban affairs of its decision. Japan International Cooperation Agency (JICA) disburses the loan once the centre has cleared it. The letter said that the issue of the depot's location is resolved and JICA stands ready to consider another loan to support the depot's construction. The approval of the revision of the total project cost to reflect actual fund requirements, according to a two-page annex note attached to the ambassador's letter, is indispensable for Mumbai Metro Rail Corporation Limited(MMRCL). The letter stated that it was recognised during JICA's detailed fact finding mission with MMRCL, which took place from December 2020 to January 2021, that there is a real possibility for MMRCL to face fund shortage within the next fiscal year (FY2021) if an additional loan cannot be provided by the end of this fiscal year (FY2020). MMRCL, the project's implementing authority, has already spent Rs 18,000 crore on the 33.5 km Metro 3 line. About 70% of the work, including 95% of the tunnelling, has been completed. Despite the fact that the metro car shed accounts for only 4% of the project's total cost, the project cannot be completed without it. Image Source Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough Also read: Mumbai Metro 2A, 7 to be fully operational from January 2022

Next Story
Infrastructure Transport

Kavach 4.0 Commissioned on Delhi–Mumbai and Delhi–Howrah

"Kavach version four has been commissioned on 1,452 route km, covering the high density Delhi–Mumbai and Delhi–Howrah corridors. The rollout included laying 8,570 km of optical fibre, installation of 1,100 telecom towers, deployment of trackside equipment over 6,776 RKm and establishment of 767 station data centres. Trackside implementation has been taken up on 24,427 RKm covering Golden Quadrilateral, Golden Diagonal and High Density Network sections. The programme aims to strengthen signalling and train protection on key routes.Kavach is an indigenously developed automatic train protecti..

Next Story
Infrastructure Transport

Railways Advance Kalyan–Murbad Line And Mumbai Capacity Expansion

"Indian Railways is advancing multiple rail infrastructure projects in Maharashtra, including the sanctioned Kalyan–Murbad new line and sizable investments under the Mumbai Urban Transport Project and the Mumbai–Ahmedabad High Speed Rail project. The Kalyan–Murbad 28 km new line has been sanctioned at Rs 8.36 billion (bn) on a 50:50 cost-sharing basis with the Government of Maharashtra and has been declared a Special Railway Project for land acquisition; proposals covering 214 hectares are at various stages of acquisition. Budgetary outlay for projects falling fully or partly in Maharash..

Next Story
Infrastructure Urban

Parliamentary Panel Flags Funding Gaps in Heavy Industries

"The Department-Related Parliamentary Standing Committee on Industry (Rajya Sabha) presented its 332nd report on the Demands for Grants 2026-27 of the Ministry of Heavy Industries (MHI). Figures converted from crore and lakh are expressed in million (mn). The Budget Estimates 2026-27 for the Ministry stand at Rs 79,399 mn against a projected requirement of Rs 94,843.2 mn, a shortfall of about 16 per cent, with revenue at Rs 79,370.8 mn and capital compressed to Rs 28.2 mn from Rs 5,020 mn.The committee flagged recurring BE-to-RE compression and declining revised estimate utilisation, and calle..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement