MMRDA Deposits Rs 5.60 Bn in Metro Arbitration Case
RAILWAYS & METRO RAIL

MMRDA Deposits Rs 5.60 Bn in Metro Arbitration Case

Following a Supreme Court directive, MMRDA deposited 50 per cent of the Rs 11.69 billion arbitration award in a case related to project cost disputes with MMOPL, which operates Mumbai’s first metro line. The Bombay High Court had earlier asked MMRDA to pay the full award by 15 July 2025.

The arbitration award—amounting to Rs 9.92 billion—was granted in August 2023 by a three-member tribunal. MMRDA had contested the order under Section 34 of the Arbitration and Conciliation Act, but the Bombay High Court upheld the award in MMOPL’s favour.

The cost of the 12-km Versova–Andheri–Ghatkopar corridor project had nearly doubled from the initial estimate of Rs 23.56 billion to Rs 43.21 billion, triggering disputes.

MMOPL, a joint venture with Reliance Infra holding 74 per cent and MMRDA the remaining 26 per cent, was awarded the project in 2007 under a public-private partnership (PPP) framework. The project was India’s first metro initiative executed on a PPP model.

Financed by a consortium led by Canara Bank, MMOPL faced further financial strain, leading to insolvency proceedings by SBI and IDBI Bank in 2023. The petitions were later withdrawn in April 2024 after a one-time settlement was reached. Meanwhile, National Asset Reconstruction Company (NARCL) had submitted a bid of Rs 10.63 billion in late 2024 to acquire Rs 12.26 billion of stressed loans from the MMOPL consortium.

News source: Business Standard

Following a Supreme Court directive, MMRDA deposited 50 per cent of the Rs 11.69 billion arbitration award in a case related to project cost disputes with MMOPL, which operates Mumbai’s first metro line. The Bombay High Court had earlier asked MMRDA to pay the full award by 15 July 2025.The arbitration award—amounting to Rs 9.92 billion—was granted in August 2023 by a three-member tribunal. MMRDA had contested the order under Section 34 of the Arbitration and Conciliation Act, but the Bombay High Court upheld the award in MMOPL’s favour.The cost of the 12-km Versova–Andheri–Ghatkopar corridor project had nearly doubled from the initial estimate of Rs 23.56 billion to Rs 43.21 billion, triggering disputes.MMOPL, a joint venture with Reliance Infra holding 74 per cent and MMRDA the remaining 26 per cent, was awarded the project in 2007 under a public-private partnership (PPP) framework. The project was India’s first metro initiative executed on a PPP model.Financed by a consortium led by Canara Bank, MMOPL faced further financial strain, leading to insolvency proceedings by SBI and IDBI Bank in 2023. The petitions were later withdrawn in April 2024 after a one-time settlement was reached. Meanwhile, National Asset Reconstruction Company (NARCL) had submitted a bid of Rs 10.63 billion in late 2024 to acquire Rs 12.26 billion of stressed loans from the MMOPL consortium.News source: Business Standard

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement