Mumbai–Ahmedabad Bullet Train Progresses Steadily
RAILWAYS & METRO RAIL

Mumbai–Ahmedabad Bullet Train Progresses Steadily

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.
As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.
Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.
Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.
On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement