Mumbai–Ahmedabad Bullet Train Progresses Steadily
RAILWAYS & METRO RAIL

Mumbai–Ahmedabad Bullet Train Progresses Steadily

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.
As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.
Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.
Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.
On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

Next Story
Infrastructure Energy

J&K CM Rules Out Power Privatisation, Focuses on Sector Reform

Jammu and Kashmir Chief Minister Omar Abdullah has dismissed speculation regarding privatisation of electricity in the Union Territory, emphasising that his priority is to strengthen and reform the power sector.“We are not discussing privatisation. By reducing losses, improving billing efficiency, and enhancing revenue, there will be no need for it. My vision is to strengthen and reform the power sector in J&K,” Abdullah stated.He addressed the gathering at the 58th Engineers’ Day at SKICC on Monday evening, an event honouring Bharat Ratna Sir M Visvesvaraya for his pioneering contri..

Next Story
Infrastructure Urban

Mumbai’s Sassoon Dock to Get Tech-Driven Modernisation with Finland

The Maharashtra government, in collaboration with Finland, will modernise Mumbai’s historic Sassoon Dock using advanced technology, state minister Nitesh Rane announced on Wednesday.Rane met a delegation of Finnish officials and representatives of Finnish companies at the dock to discuss strategic plans for upgrading the facility in south Mumbai, according to an official statement.Built in the 19th century, Sassoon Dock is one of Mumbai’s oldest and busiest fishing harbours. Operations currently exceed its original capacity, raising concerns over hygiene, odour, fish handling standards, an..

Next Story
Infrastructure Energy

Agarwal Industrial Wins Rs 3.3 Billion IOCL Bitumen Tender

Agarwal Industrial Corporation rose 3.84 per cent to Rs 945.65 after announcing it had secured a prestigious tender from Indian Oil Corporation (IOCL) worth Rs 3.3 billion.In a regulatory filing during market hours, the company confirmed it had won the tender to supply Bulk Bitumen (VG-30 and VG-40 grades) to IOCL’s Kakinada locations.The firm quantity under the award totals around 60,500 tonnes across 11 parcels, while the optional quantity is approximately 33,000 tonnes across six parcels. This brings the total awarded quantity to roughly 93,500 tonnes. At current market prices, the firm o..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?