Mumbai–Ahmedabad Bullet Train Progresses Steadily
RAILWAYS & METRO RAIL

Mumbai–Ahmedabad Bullet Train Progresses Steadily

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.
As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.
Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.
Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.
On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

Next Story
Infrastructure Transport

Modi Launches Rs 318.5 Billion Projects in Maharashtra

Prime Minister Narendra Modi on Wednesday launched infrastructure projects worth Rs 318.5 billion during his two-day visit to Maharashtra, including two landmark developments — the first phase of the Rs 196.5 billion Navi Mumbai International Airport (NMIA) and the second phase of the Rs 122 billion Mumbai Metro Line 3. India’s first fully digitised airport, NMIA, has been designed for multimodal connectivity and is being developed under a public-private partnership between Adani Airport Holdings, which holds a 74 per cent stake, and the City and Industrial Development Corporation of Maha..

Next Story
Real Estate

Tata Housing Sells Rs 10 Billion Homes in Bengaluru

Real estate developer Tata Housing on Wednesday announced that it has achieved home sales worth over Rs 10 billion in its newly launched residential project in Bengaluru, driven by strong demand. In a statement, the company said Tata Housing Varnam Phase I — part of the 135-acre integrated township Carnatica in North Bengaluru — has surpassed Rs 10 billion in sales since its launch in August 2025. Spread across 20 acres, Varnam Phase I has recorded sales of 377 units out of 582 apartments, along with 48 townhouses and row houses. The project has attracted substantial interest from both e..

Next Story
Infrastructure Transport

OMRON to Train 1,000 Graduates Annually at Bengaluru Centre

Japanese industrial automation giant OMRON announced on Wednesday that it will train and skill 1,000 fresh engineering graduates annually at its newly launched Automation Centre in Bengaluru. The initiative aims to enhance India’s employable manufacturing talent and build a resilient, future-ready industrial ecosystem. Motohiro Yamanishi, President of the Industrial Automation Company at OMRON Corporation, said, “We see immense potential in the dynamism of India’s manufacturing sector. The new Automation Centre underscores India’s vital role in our global and Asia-Pacific vision. It i..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?