Mumbai–Ahmedabad Bullet Train Progresses Steadily
RAILWAYS & METRO RAIL

Mumbai–Ahmedabad Bullet Train Progresses Steadily

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.
As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.
Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.
Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.
On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code