Mumbai–Ahmedabad Bullet Train Progresses Steadily
RAILWAYS & METRO RAIL

Mumbai–Ahmedabad Bullet Train Progresses Steadily

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.
As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.
Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.
Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.
On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code