Mumbai–Ahmedabad Bullet Train Progresses Steadily
RAILWAYS & METRO RAIL

Mumbai–Ahmedabad Bullet Train Progresses Steadily

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.
As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.
Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.
Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.
On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

The Mumbai–Ahmedabad High-Speed Rail (MAHSR) project is progressing steadily, with significant advancement in civil works, station foundations, river bridge construction, and tunnelling, Union Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday. The 508-kilometre bullet train corridor, implemented with financial and technical support from Japan, spans Gujarat, Maharashtra, and the Union Territory of Dadra & Nagar Haveli.As of June 30, 2025, the project has incurred cumulative expenditure of Rs 788.39 billion. Land acquisition totalling 1,389.5 hectares and all statutory approvals have been completed, while 24 out of 28 tender packages have been awarded. Civil works are well underway: foundations are complete for 406 km, piers for 395 km, and girders have been launched for 312 km. Track laying has begun on 127 km of viaducts, and overhead equipment mast erection is in progress.Out of the 12 proposed stations, foundation works have been completed at eight in Gujarat, while construction continues at three in Maharashtra, including the Bandra Kurla Complex (BKC) terminal. Additionally, 16 river bridges have been completed, with work on nine more underway. Tunnelling work in Gujarat has been finalised, and construction has commenced on the 21-kilometre undersea tunnel segment in Maharashtra, with 4 kilometres already completed.Vaishnaw noted that the project has created both direct and indirect employment opportunities through construction activities, supply chains, and ancillary services. However, he cautioned that precise timelines and final cost estimates can only be determined after the completion of key components such as track installation, electrification, signalling systems, and trainset deployment.On the broader high-speed rail front, the minister reported that 150 Vande Bharat trains are currently operational across India. These semi-high-speed trainsets, manufactured indigenously at the Integral Coach Factory in Chennai, are part of the central government’s Make in India push. Additionally, 200 Vande Bharat sleeper rakes are under production to expand services across longer routes. 

Next Story
Real Estate

Birla Estates Tops Global GRESB 2025 Rankings

Birla Estates (BEPL), a wholly owned subsidiary of Aditya Birla Real Estate (formerly Century Textiles and Industries Limited), has been recognised as a Sector Leader in the 2025 GRESB Real Estate Assessment, securing top honours across multiple global and regional categories.Birla Estates’ Achievements in GRESB 2025:Global Sector Leader – ResidentialGlobal Sector Leader – Non-Listed ResidentialRegional Sector Leader – Asia – ResidentialRegional Sector Leader – Non-Listed – Asia – ResidentialThese distinctions reaffirm Birla Estates’ exceptional performance in Environmental, ..

Next Story
Infrastructure Transport

Progota India Secures RDSO Clearance for Kavach 4.0

Concord Control Systems, one of India’s leading manufacturers of embedded electronic and critical system solutions, announced that its associate company, Progota India, has received Technical Prototype Clearance from the Research Designs and Standards Organisation (RDSO) for Kavach 4.0, the latest version of Indian Railways’ indigenous Automatic Train Protection (ATP) system.With this clearance, Progota has been formally approved to execute its ongoing trial order from South Central Railway, marking a key milestone in India’s railway modernization journey. The approval also establishes P..

Next Story
Infrastructure Urban

MPS Interactive Systems Completes Full Acquisition of Liberate Group

MPS Interactive Systems (MPSi), a material subsidiary of MPS, has completed the acquisition of the remaining shareholding in the Liberate Group of Companies—comprising Liberate Learning, App-eLearn, and Liberate eLearning.With this transaction, MPSi now holds 100 per cent ownership of all entities within the Liberate Group, making them its wholly owned subsidiaries. The acquisition was executed in line with the valuation methodology defined in the original transaction documents.Commenting on the development, Rahul Arora, Chairman and CEO of MPS, said, “The corporate learning sector continu..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?