+
Mumbai-Ahmedabad bullet train: 1,75,000 noise barriers installed
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train: 1,75,000 noise barriers installed

The National High Speed Rail Corporation Limited (NHSRCL), overseeing the Mumbai-Ahmedabad bullet train project, announced that over 1,75,000 noise barriers have been installed along the corridor to mitigate the noise generated by the train and the associated civil structures during operations. As of September 10, these barriers have been installed across an 87.5 km stretch in Gujarat.

Each kilometre of the viaduct is equipped with approximately 2,000 noise barriers on both sides, NHSRCL revealed in a press release. To support this effort, three precast factories have been established in Surat, Anand, and Ahmedabad, specifically for the production of these barriers.

The noise barriers are made of concrete panels, standing 2 metres tall from the rail level and 1 metre wide, each weighing around 830-840 kg. They are designed to reflect and distribute the aerodynamic noise generated by the train, as well as the sound produced by the wheels running on the tracks. Importantly, the design of these barriers ensures that they do not obstruct the view for passengers during the journey.

In residential and urban areas, taller noise barriers will be installed, with an additional 1 metre of translucent polycarbonate material on top of the 2-metre concrete panels, making them 3 metres high.

Railway Minister Ashwini Vaishnaw informed Parliament on July 31 that the land required for the project, totalling 1,389.5 hectares, has been fully acquired. He also reported progress on key construction milestones, including the completion of 350 km of Pier Foundation, 316 km of Pier Construction, 221 km of Girder Casting, and 190 km of Girder Launching. Additionally, work on a 21 km undersea tunnel has commenced.(ET)

The National High Speed Rail Corporation Limited (NHSRCL), overseeing the Mumbai-Ahmedabad bullet train project, announced that over 1,75,000 noise barriers have been installed along the corridor to mitigate the noise generated by the train and the associated civil structures during operations. As of September 10, these barriers have been installed across an 87.5 km stretch in Gujarat. Each kilometre of the viaduct is equipped with approximately 2,000 noise barriers on both sides, NHSRCL revealed in a press release. To support this effort, three precast factories have been established in Surat, Anand, and Ahmedabad, specifically for the production of these barriers. The noise barriers are made of concrete panels, standing 2 metres tall from the rail level and 1 metre wide, each weighing around 830-840 kg. They are designed to reflect and distribute the aerodynamic noise generated by the train, as well as the sound produced by the wheels running on the tracks. Importantly, the design of these barriers ensures that they do not obstruct the view for passengers during the journey. In residential and urban areas, taller noise barriers will be installed, with an additional 1 metre of translucent polycarbonate material on top of the 2-metre concrete panels, making them 3 metres high. Railway Minister Ashwini Vaishnaw informed Parliament on July 31 that the land required for the project, totalling 1,389.5 hectares, has been fully acquired. He also reported progress on key construction milestones, including the completion of 350 km of Pier Foundation, 316 km of Pier Construction, 221 km of Girder Casting, and 190 km of Girder Launching. Additionally, work on a 21 km undersea tunnel has commenced.(ET)

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code