Mumbai Metro Line Three Dharavi–Worli Stretch Awaits Safety Approval
RAILWAYS & METRO RAIL

Mumbai Metro Line Three Dharavi–Worli Stretch Awaits Safety Approval

Phase two of Mumbai's underground Metro Line Three, linking Dharavi to Acharya Atre Chowk in Worli, is nearing completion and awaiting certification from the Commissioner of Metro Rail Safety (CMRS). The certification is mandatory before passenger operations begin.

Currently, Metro Line Three operates from Aarey to Bandra Kurla Complex (BKC), spanning twelve point four four kilometres with ten stations. This section runs ninety-six daily trips from six thirty AM to ten thirty PM, reducing travel from Aarey to BKC to thirty minutes compared to over one hour by road via Western Express Highway.

On April eighteen, Mumbai Metro Rail Corporation Limited (MMRCL) adjusted operational hours to integrate trial runs between the Aarey–BKC corridor and the upcoming six-station extension to Acharya Atre Chowk. Once fully operational, the 33.5 Km connect six commercial districts, thirty major office hubs, twelve educational institutions, eleven hospitals, ten transport nodes, and twenty-five recreational and religious centres. The corridor, projected to serve one point four Mn passengers daily, will also offer direct access to Mumbai's domestic and international airports.

Source: Free Press Journal

Phase two of Mumbai's underground Metro Line Three, linking Dharavi to Acharya Atre Chowk in Worli, is nearing completion and awaiting certification from the Commissioner of Metro Rail Safety (CMRS). The certification is mandatory before passenger operations begin. Currently, Metro Line Three operates from Aarey to Bandra Kurla Complex (BKC), spanning twelve point four four kilometres with ten stations. This section runs ninety-six daily trips from six thirty AM to ten thirty PM, reducing travel from Aarey to BKC to thirty minutes compared to over one hour by road via Western Express Highway. On April eighteen, Mumbai Metro Rail Corporation Limited (MMRCL) adjusted operational hours to integrate trial runs between the Aarey–BKC corridor and the upcoming six-station extension to Acharya Atre Chowk. Once fully operational, the 33.5 Km connect six commercial districts, thirty major office hubs, twelve educational institutions, eleven hospitals, ten transport nodes, and twenty-five recreational and religious centres. The corridor, projected to serve one point four Mn passengers daily, will also offer direct access to Mumbai's domestic and international airports. Source: Free Press Journal

Next Story
Real Estate

DLF Returns to Mumbai with Premium Andheri Residential Project

Delhi-NCR based real estate major DLF announced its return to the Mumbai market on 17 July with the launch of its premium residential project, The WestPark, in Andheri. The first phase includes 416 apartments spread across four towers, with two towers launched on the announcement day. The company plans to invest over Rs 8 billion in the project and expects a topline exceeding Rs 20 billion from Phase 1.“We have launched two towers and, given the strong response, plan to unveil the remaining two towers ahead of schedule, within the next few days,” said Aakash Ohri, Joint Managing Director o..

Next Story
Infrastructure Urban

APCRDA Advances Net Zero Goal with IGBC Training for Officials

In a significant stride towards Andhra Pradesh’s Net Zero target by 2040 and the Swarna Andhra 2047 vision, the Andhra Pradesh Capital Region Development Authority (APCRDA), in partnership with the Indian Green Building Council (IGBC), conducted a high-level capacity-building programme for senior officials in Vijayawada on Friday.Held at a city hotel, the session saw the participation of over 50 senior APCRDA officials, including the Engineer-in-Chief, Chief Engineer (H&B), Director (Planning), Director (Environment), and heads of key departments. The training centred on IGBC’s Green B..

Next Story
Infrastructure Energy

Assam Solar Project Halted as Waaree EPC Contract Is Cancelled

Following the Assam government’s withdrawal from its proposed solar project, the Engineering, Procurement, and Construction (EPC) contract awarded to Waaree Renewable has been suspended. Waaree Group’s EPC division informed the stock exchange of this development through a regulatory filing.The Assam solar project was suspended due to funding challenges, which rendered the initiative unviable for the state government. Waaree Renewable Transmission Limited (RTL) explained that the Government of Assam has withdrawn the project’s funding via the Asian Development Bank (ADB) loan. Consequentl..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?