Nagpur Metro Phase-II Gets First Track Crossover Near Lekha Nagar
RAILWAYS & METRO RAIL

Nagpur Metro Phase-II Gets First Track Crossover Near Lekha Nagar

MahaMetro has completed the first track crossover on Nagpur Metro Phase-II near Lekha Nagar after night work coordinated with the general consultant and the track contractor. The work formed an operational link that will later allow trains to change running lines, with two turnouts together forming a crossover. Phase-II is expected to have 40 turnouts on its elevated main line sections, matching the number installed during Phase-I. The completion marks a key infrastructure milestone on the new corridors.

Track laying and integration of other systems will gather pace as construction advances along the corridors. Teams followed a planned schedule to carry out the crossover installation at night to minimise disruption and to align with safety and engineering requirements. The contractor and consultant worked under the supervision of MahaMetro technical leads to ensure alignment, rail geometry and ballast and fastening arrangements met specifications. Temporary protections and access controls were maintained for worker safety.

Before the new corridors can begin trial runs and be commissioned, signalling, traction, telecommunications and other metro systems will need to be installed and integrated with the track infrastructure. Testing and trial protocols will assess interoperability across systems and confirm that switching and interlocking functions operate reliably under operational scenarios. Systems commissioning will proceed in phases, with progress gated by test outcomes and statutory approvals. Operational staff training and maintenance planning are part of the preparatory activities.

The project update also noted ancillary market information provided in the release, including prevailing precious metal rates and a recommended sarafa making charge of 13 per cent as offered for local reference. The release advised readers to follow Nagpur Today for further progress reports and provided the source link for detailed updates. The crossover completion reflects ongoing momentum on Phase-II as stakeholders move towards system integration and eventual passenger services.

MahaMetro has completed the first track crossover on Nagpur Metro Phase-II near Lekha Nagar after night work coordinated with the general consultant and the track contractor. The work formed an operational link that will later allow trains to change running lines, with two turnouts together forming a crossover. Phase-II is expected to have 40 turnouts on its elevated main line sections, matching the number installed during Phase-I. The completion marks a key infrastructure milestone on the new corridors. Track laying and integration of other systems will gather pace as construction advances along the corridors. Teams followed a planned schedule to carry out the crossover installation at night to minimise disruption and to align with safety and engineering requirements. The contractor and consultant worked under the supervision of MahaMetro technical leads to ensure alignment, rail geometry and ballast and fastening arrangements met specifications. Temporary protections and access controls were maintained for worker safety. Before the new corridors can begin trial runs and be commissioned, signalling, traction, telecommunications and other metro systems will need to be installed and integrated with the track infrastructure. Testing and trial protocols will assess interoperability across systems and confirm that switching and interlocking functions operate reliably under operational scenarios. Systems commissioning will proceed in phases, with progress gated by test outcomes and statutory approvals. Operational staff training and maintenance planning are part of the preparatory activities. The project update also noted ancillary market information provided in the release, including prevailing precious metal rates and a recommended sarafa making charge of 13 per cent as offered for local reference. The release advised readers to follow Nagpur Today for further progress reports and provided the source link for detailed updates. The crossover completion reflects ongoing momentum on Phase-II as stakeholders move towards system integration and eventual passenger services.

Related Stories

Gold Stories

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Next Story
Technology

ABB Unveils Intelligent Motor to Accelerate Industrial AI Adoption

ABB recently launched Intelleqt, which it describes as the world’s first low-voltage motor with factory-integrated intelligence, at the SPS trade fair in Germany. Designed to deliver real-time operational insights from its first rotation, the motor enables industrial operators to integrate equipment-level data into existing digital platforms while retaining full ownership of their data.The launch addresses growing challenges in scaling artificial intelligence (AI) across industrial operations, particularly data quality and availability. According to Deloitte, while 84 per cent of manufacture..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code