RAILWAYS & METRO RAIL

"Breaking Barriers: A Groundbreaking Exploration of Historical Events"

The phase 1 of Nagpur Metro comprises of a 39 km elevated corridor. Afcons Infrastructure delivered Reach 2 (North South corridor) and Reach 3 (East-West corridor) of the Nagpur Metro project phase I. It has constructed 17.1 km which is almost 44 per cent of the total viaduct length, and around 51 p...

The phase 1 of Nagpur Metro comprises of a 39 km elevated corridor. Afcons Infrastructure delivered Reach 2 (North South corridor) and Reach 3 (East-West corridor) of the Nagpur Metro project phase I. It has constructed 17.1 km which is almost 44 per cent of the total viaduct length, and around 51 per cent of the overall civil works. Afcons constructed India’s first four-level transportation corridor at Gaddigodam Railway Crossing in Reach-2. This four-level transportation corridor is part of Asia’s longest double-decker (Metro-cum-NHAI) viaduct (5.3 km), which was thrown open to public on December 11, 2022, at the hands of honourable PM Narendra Modi. Besides the longest double-decker viaduct, Afcons also constructed eight stations in Reach-2 and Reach-1, and two metro depots. To its credit the Sitabuldi interchange station by Afcons is the highest metro interchange station in India. Smart solutions for speedy construction During the preparatory stage, the engineering team of Afcons manoeuvred the project’s technical complexity amidst space constraints at site, severe winter, unseasonal rains, the pandemic as well as a tight deadline. With Afcons already setting a precedent with before-time delivery of complex elements at Reach-3, it was no surprise when Maha Metro asked the team to complete the four-level transportation corridor in two months, instead of the allotted five months. A crack team was formed which innovatively completed the task within two months adhering to all quality and safety standards. Several records were also created within the short period. Afcons had to dig deep into its reserves. All forces collaborated to make this once-in-a-lifetime challenge a success. It enlisted expert support from its Chenab Railway Bridge project to critically review the preparedness. Manpower and machines were mobilised at an unprecedented pace. The tremendous support and cooperation from the client and others assisted Afcons to ensure a speedy completion of the project. Besides, for priority corridor of Reach-2, the team came up with smart solutions to ensure priority section was ready within three months. At Sitabuldi, a 44 metre composite steel girder span had to be placed over the busy Govari flyover. After the drawings were approved in November 2018, fabrication of 230 tonne composite girders, including procurement, was achieved in a record time of 45 days. As Govari flyover could not be shut for a long time, it had to be really quick. Afcons deployed three cranes of 275 tonne, 220 tonne and 200 tonne capacity to erect the steel girders using the tandem lifting method. It took just four nights to erect four steel girders, followed by concreting. Owing to the time constraints, temporary bearings were used for the steel girder erection. The entire deck was lifted with six span jacks and the temporary bearings were replaced with the permanent ones in a single day’s time. Steel erection amid stringent restrictions Afcons erected the 80 metre double-decker steel span, weighing 16,650 MT in a record time of two months. The steel superstructure was placed over the Gaddigodam railway crossing where more than 150 trains and over one lakh vehicles passed the construction site every day. Launching of a gigantic 18.9 metre wide girder is probably a first in Indian Railways. Afcons opened four work fronts that enabled to squeeze the entire five months into two months period. The entire team was able to deliver their targets within time round the clock. Afcons used heavy duty cranes ranging from 500 tonne to 300 tonne. The infrastructure company used super lift 500 tonne crane which enabled to lift the components of the flyover. The biggest challenge was to erect the entire truss in a sequential manner. The truss was divided in three parts to expediate the erections. The major challenge was to erect entire truss with the accuracy of plus minus 5 mm. Afcons were able to complete entire erection with the accuracy of plus 3 mm. Its camber adjustment was more than the required theoretical dimensions. The double-decker open web girder (OWG), which was created using 1,650 MT structural steel having 8,000 structural elements, was placed over the busy Gaddigodam railway crossing. All the activities were done in extremely tight railway block hours, given how busy this route is. The span stands at a height of 28 metre above the ground. Such a critical and complex task has never been attempted before in India. Apart from the 80 metre steel span, two adjacent composite girders with RCC deck slab, each of 25 metre span had to be completed. Challenges overcame during construction phase The erection of 80 metre double-decker steel span, weighing 1,650 MT over live railway tracks at Reach-2 in just two months was the biggest challenge. The span stands at a height of 28 metre above the ground. Afcons ensured proper coordination to ensure safe and speedy erection of the double-decker span. Four 250-500T cranes, one super lift arrangement, 22 torque wrench machines were deployed, and special lowering arrangements were made for the construction. Afcons also built a metro-cum-flyover, Asia’s longest double-decker viaduct (5.3 km) stretch over single piers. This was a unique exercise, as the design team conceptualised an in-house double decker launching girder. The fabrication of two such equipments was done within just three months. These double decker launching girders gave better productivity as compared to the conventional ones as the spans between two piers can be erected one after the other, after the completion of one auto-launching cycle. The engineering team saved 1.5 days for every span, which would not have been possible had it used the conventional launching girders. Precautions taken while execution All safety measures were taken to ensure the utmost safety of the staff and workers. Afcons organised programmes to create awareness about the safety among them. As a result, it clocked 10 million safe man hours without any lost time incident in the project. Besides, Afcons received multiple awards, including a Safe Civil Contractor award from the client, Maha Metro. The use of heavy-duty machineries, one super lift arrangement, 22 torque wrench machines, and special lowering arrangements for the erection of 80M double-decker steel span was unique. We also introduced unconventional erection methodologies such as eliminating of nosing structure altogether. “Launching of this 18.9 metre wide steel girder across a live railway track at a height of 28 metre is a first for Indian Railways. We have also constructed the highest metro interchange station in India which is 32.32 metre high from the ground level while the Sitabuldi station was completed in just 20 months.” - R Anantakumar, Director (Operations) & Urban Infra BU Head, Afcons Infrastructure Ltd.

Next Story
Infrastructure Transport

Bengaluru Unveils Rs 1,200 Bn Infra Upgrade Plan

Bengaluru is set to receive a massive infrastructure boost worth Rs 1,200 billion under new projects planned by the Karnataka government to enhance urban mobility and connectivity. The initiative includes the expansion of the city’s metro network, construction of tunnel roads, elevated corridors, and 500 km of white-topping works to improve road durability. The Bruhat Bengaluru Mahanagara Palike (BBMP) and Bengaluru Metro Rail Corporation Limited (BMRCL) will jointly execute the projects. Key projects include tunnel roads between Hebbal and Mekhri Circle, 25 new signal-free corridors, and ..

Next Story
Infrastructure Transport

Cochin Shipyard delivers first indigenous ASW vessel ‘Mahe’ to Navy

Cochin Shipyard Limited (CSL) has delivered INS Mahe, the first indigenous Anti-Submarine Warfare Shallow Water Craft (ASW SWC), to the Indian Navy. The vessel is part of an eight-ship series being constructed under the Navy’s “Atmanirbhar Bharat” initiative to strengthen coastal defence capabilities. Designed and built entirely in India, Mahe features advanced sensors and weapon systems for detecting and neutralising underwater threats in coastal waters. The vessel underwent extensive sea trials before delivery, demonstrating high performance and manoeuvrability. This milestone reinfo..

Next Story
Infrastructure Urban

Vedanta Group to invest Rs 1,000 billion more in Odisha projects

Vedanta Group has announced an additional investment of Rs 1,000 billion in Odisha to expand its operations across metals, energy, and downstream industries. Anil Agarwal, Chairman, made the announcement during the third edition of the Make in Odisha conclave, highlighting the state’s pivotal role in India’s industrial growth.The investment will focus on strengthening Vedanta’s aluminium and copper businesses, establishing new value-added facilities, and boosting employment in the region. The company already operates large-scale plants in Jharsuguda and Lanjigarh, contributing significan..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?