Namma Metro Phase II delays; cost surges to Rs 400 billion
RAILWAYS & METRO RAIL

Namma Metro Phase II delays; cost surges to Rs 400 billion

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD).

Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor.

BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion.

Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD). Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor. BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion. Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

Next Story
Infrastructure Transport

Railways approves major upgrade for Telangana traction lines

The Ministry of Railways has approved the upgradation of the electric traction system in two crucial railway sections — Medchal–Mudkhed (225 km) and Mahbubnagar–Dhone (184 km). The projects, costing Rs 1.93 billion and Rs 1.23 billion respectively, will enhance the electric traction capacity from 1X25 KV to 2X25 KV. The work includes modifications to circuit breakers and switching stations, along with the installation of additional conductors. These routes serve as vital links between Northern and Southern India via Hyderabad. Once completed, the upgraded system will reduce voltage dro..

Next Story
Infrastructure Transport

Adani to invest Rs 425 billion more in Maharashtra’s Dighi Port

The Adani Group has committed to invest an additional Rs 425 billion in the Dighi Port project, located along Maharashtra’s coastal Konkan belt, government officials announced on Monday. Adani Ports and Special Economic Zone (APSEZ)-run Dighi Ports signed a memorandum of understanding (MoU) with the Maharashtra government to undertake the expansion of the port and related infrastructure. This new commitment comes as part of a broader investment initiative by the state. Chief Minister Devendra Fadnavis said the agreement is among 15 MoUs worth over Rs 560 billion signed during the opening d..

Next Story
Infrastructure Transport

HUDCO, JNPA sign Rs 50 billion deal for port development

In a strategic move, the Housing and Urban Development Corporation Ltd (HUDCO) has signed a Memorandum of Understanding (MoU) with the Jawaharlal Nehru Port Authority (JNPA) for an investment of Rs 50 billion to revamp and develop port infrastructure. The non-binding agreement is intended to strengthen cooperation on both existing and upcoming infrastructure projects, with a focus on development, financing, and refinancing of port facilities at the Jawaharlal Nehru Port. The MoU was formalised with the signatures of Sanjay Kulshrestha, Chairman and Managing Director of HUDCO, and Unmesh Shar..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?