Namma Metro Phase II delays; cost surges to Rs 400 billion
RAILWAYS & METRO RAIL

Namma Metro Phase II delays; cost surges to Rs 400 billion

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD).

Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor.

BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion.

Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD). Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor. BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion. Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

Next Story
Infrastructure Urban

Digital First: Bridging the Skilled Talent Gap in India’s Construction Sector

India stands at a defining juncture in its economic journey as it accelerates toward becoming a US$7 trillion economy by 2030. India’s construction sector, encompassing infrastructure and real estate development will play a pivotal role in its economic transformation. Expansion in developments such as the national highways, smart cities, airports, metro networks, logistics hubs, housing, etc. underscores the physical expression of India’s development ambition. The construction sector is already the second-largest contributor to India’s GDP, accounting for nearly 18 per cent of total..

Next Story
Infrastructure Transport

Titagarh Rail to Raise Rs 2 billion via Preferential Allotment to Promoters

Titagarh Rail Systems has announced a proposal to raise approximately Rs 2 billion through a preferential issue of 21,16,402 convertible warrants to members of its Promoter Group. The board of directors approved the move at its meeting held on July 9, 2025, subject to shareholder and regulatory approvals. The warrants, priced at Rs 945 each, will be allotted to Mrs Rashmi Chowdhary and Mr Prithish Chowdhary in line with Chapter V of SEBI’s ICDR Regulations. Each warrant is convertible into one equity share of ₹2 face value within 18 months from the date of allotment.   ..

Next Story
Real Estate

Hindware Strengthens Eastern Footprint with New Brand Store in Kolkata

Bathware major Hindware has expanded its retail footprint in West Bengal with the launch of a new state-of-the-art brand store in Ichapore, Kolkata. This marks the company’s fourth brand store in the city and 30th in the state, underlining its strategic focus on the eastern market. The newly launched store, operated by Tirupati Sales Corporation, showcases the entire spectrum of Hindware’s bathware offerings, including sanitaryware, faucets, showers, basins, and products from its premium lines — Queo and the Hindware Italian Collection. It is aimed at providing an immersive experien..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?