Namma Metro Phase II delays; cost surges to Rs 400 billion
RAILWAYS & METRO RAIL

Namma Metro Phase II delays; cost surges to Rs 400 billion

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD).

Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor.

BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion.

Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD). Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor. BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion. Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

Next Story
Infrastructure Urban

India To Invest $37 Billion To Boost Petrochemical Capacity

India is set to become a major global player in the petrochemicals industry, driven by a planned capital expenditure of $37 billion (Rs 3.1 trillion) aimed at reducing import dependency and enhancing self-sufficiency, according to S&P Global Ratings.In its latest report titled “First China, Now India: Self-Sufficiency Goals Will Add To Petrochemicals Supply”, S&P said India’s large-scale capacity expansion—mirroring China’s earlier push—will likely intensify oversupply pressures in Asia’s petrochemical markets.Currently the world’s third-largest petrochemical consumer a..

Next Story
Infrastructure Transport

Indian Railways Expands Global Exports Of Rail Equipment

Indian Railways has announced that it is rapidly emerging as a global exporter of railway equipment, including bogies, coaches, locomotives, and propulsion systems, under the government’s ‘Make in India, Make for the World’ initiative.According to an official statement, India’s railway products are now reaching over 16 international markets, reflecting the country’s growing capacity to design, develop, and deliver world-class rail solutions.Metro coaches have been exported to Australia and Canada; bogies to the United Kingdom, Saudi Arabia, France, and Australia; propulsion systems t..

Next Story
Infrastructure Transport

RailTel Awards Rs 163 Million Contract To RTNS Technology

RailTel Corporation of India Limited (RailTel), a Mini Ratna Public Sector Undertaking, has awarded a domestic work order worth Rs 163 million to RTNS Technology Private Limited.The contract, issued on 30 September 2025, involves the supply and installation of equipment and related services for one of RailTel’s key customers. The project underscores RailTel’s commitment to advancing technology and communication infrastructure through collaboration with domestic system integrators.RTNS Technology Private Limited, an ISO-certified system integrator, provides comprehensive solutions for perim..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?