Namma Metro Phase II delays; cost surges to Rs 400 billion
RAILWAYS & METRO RAIL

Namma Metro Phase II delays; cost surges to Rs 400 billion

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD).

Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor.

BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion.

Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD). Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor. BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion. Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

Next Story
Infrastructure Transport

Chembur Metro to Boost East Mumbai Links

MMRDA is advancing eastern Mumbai’s urban mobility network, with the upcoming Chembur Metro Station set to emerge as a key interchange and the Mumbai Monorail preparing for relaunch.Dr Sanjay Mukherjee, Metropolitan Commissioner, MMRDA, conducted a site visit to Chembur Metro Station along with Kanhuraj Bagate, Managing Director, MMMOCL. He also visited the nearby VN Purav Monorail Station to review system preparedness and ease of interconnectivity.Once operational, the interchange is expected to offer commuters across the eastern suburbs quicker access, smoother transfers and seamless conne..

Next Story
Equipment

Herrenknecht TBMs Drive Thane–Borivali Tunnel Progress

Herrenknecht India has supplied two of the four tunnel boring machines (TBMs) required for the 11-km Thane–Borivali Twin Tunnel Project being developed by the Mumbai Metropolitan Region Development Authority (MMRDA). The project is expected to reduce travel time between Thane and Borivali from 60–90 minutes to around 15 minutes while easing congestion across the Mumbai Metropolitan Region.The first two Single Shield TBMs, named Nayak and Arjuna, feature 13.34-m cutterhead diameters and are designed for hard-rock excavation. They will be deployed to tunnel through the challenging geological..

Next Story
Resources

KBL Launches Smart Skid Mounted Fire Pump Set

Kirloskar Brothers (KBL) has launched its Smart Skid Mounted Fire Pump Set, an integrated fire protection solution designed to improve operational efficiency, remote monitoring and installation flexibility. The system was inaugurated by Ms Madhuritai Misal, Hon. Minister of State for Urban Development, Government of Maharashtra.The Smart Skid Mounted Fire Pump Set is a factory-tested, pre-packaged solution that combines FM/UL-certified motor and engine pump sets with IoT-enabled remote monitoring. Designed to deliver a flow rate of 170 m³/hr at a head of 100 metres, the system aims to provide..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->