Namma Metro Phase II delays; cost surges to Rs 400 billion
RAILWAYS & METRO RAIL

Namma Metro Phase II delays; cost surges to Rs 400 billion

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD).

Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor.

BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion.

Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

The cost of Bengaluru Metro?s Phase-2 network has surged to nearly Rs 400 billion, marking a 52% increase from the original estimate a decade ago. Approved in 2014, the project initially spanned 72 km at a cost of Rs 264.05 billion, with an additional 3 km later incorporated, and was set for completion by 2019. By 2021, the cost had escalated to Rs 306.95 billion. The revised proposal has now been sent by Bangalore Metro Rail Corporation Ltd (BMRCL) to the State Finance Department for approval through the Urban Development Department (UDD). Additional Chief Secretary of UDD, SR Umashankar, cited several factors for the increased costs, including revised land acquisition costs, extension of kilometres, inflation, pandemic-related delays, and fluctuations in international currencies. The primary reason for the cost hike is attributed to delays. Phase-II, initially set for completion in 2019, remains unfinished five years later. A senior UDD official noted that adhering to the original timeline would have prevented such a massive escalation. Land acquisition delays were a significant contributing factor. BMRCL has undertaken several extensions and additions, contributing to the increased costs. The Reach-2 extension, originally terminating at Kengeri, now extends to Challaghatta. A new depot has been added at Kadugodi (Whitefield) on the eastern side. Additionally, 128.36 hectares of land have been acquired versus the initially planned 84.33 hectares, raising compensation costs to nearly Rs 63 billion, up by Rs 4.38 billion. Road-widening projects near many metro stations, including the stretches from Baiyappanahalli to Kadugodi and Yelachenahalli to Silk Institute, have also added to the costs. Additional land was acquired for the Reach-5 line (R V Road-Bommasandra). Following approval from the State Finance Department, the revised proposal will be sent to the Centre?s Urban Development Department. (Source: TNIE)

Next Story
Infrastructure Transport

Large Format Store Planned At M G Road Metro Station

M G Road station in Bengaluru is set to host the city’s first large-format commercial and experience space, with planning led by Bangalore Metro Rail Corporation Limited. BMRCL has invited proposals to develop and operate a central business district destination at the Purple?Pink Line interchange. The plan positions the station as a commercial hub designed to serve a broad commuter base across the city. The proposal is part of a broader effort to activate transit nodes commercially. Tender documents set a minimum monthly rental of Rs 0.944 million (mn), inclusive of GST, for the large-format..

Next Story
Infrastructure Energy

Government Cancels Auction Of Eleven Critical Mineral Blocks

The government has cancelled the auction of 11 critical and strategic mineral blocks after receiving a poor investor response and failing to attract a sufficient number of qualified bidders. The decision represents a setback to plans to ramp up domestic exploration and production of critical minerals amid global supply chain disruptions and rising demand for materials used in clean energy and advanced technologies. The mines ministry issued an annulment notice setting out the reasons for the cancellations. The annulment notice indicated that the auction process for five mineral blocks was canc..

Next Story
Infrastructure Energy

Gujarat Pushes Biogas Growth With 193 Operational Units

Gujarat has operationalised 193 biogas plants across the state and is planning to add 60 more units as part of a broader push to scale up clean and sustainable energy solutions. The existing plants, established under various government-supported schemes, process organic waste including cattle dung and agricultural residue to produce biogas and a nutrient-rich slurry. The output is mainly used for cooking and other energy needs in rural and semi-urban communities, while also improving local waste management practices. The Gujarat Energy Development Agency (GEDA) is leading the initiative and is..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement